INSP-Final | 11/18/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Katie Marron
|
|
|
Previous correction items completed. Air Test was completed on 9/20/16. System test completed satisfactory. Scope of work complete. Permit Finaled.
|
INSP-Final | 11/16/2016 | 11/18/2016 | 11/18/2016 | A | CANC |
Katie Marron
|
|
|
Rescheduled with Alarm vendor for Monday afternoon.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | PASS |
Katie Marron
|
|
|
Hydrostatic test on all three systems completed satisfactory. Remaining rough in areas completed satisfacory. Still Pending: -dry system 24 hr air test. - 2nd floor protector on upright - 2nd flr mechanical room spaced with 5' verify there is an obstruction to warrant - 2nd floor missing hangar at apartments
|
INSP-Sprinkler Rough-in | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PART |
Katie Marron
|
|
|
Rough-in inspection for grid ceiling areas: -verified 'OK' north stairwell 2nd floor -verified 'OK' first floor with exception of a dozen drops that were not in yet (heads were circled on drawings) -verified 'ok' center office spacing issue previously noted.
Still Pending: - 2nd flr Drop ceiling for hallway in front of elevator and apartments - 2nd floor protector on upright - 2nd flr mechanical room spaced with 5' issue - 1st flr dozen of drop ceiling drops
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2016 | 9/20/2016 | 9/20/2016 | P | DONE |
Katie Marron
|
|
|
24 hour air test on the dry system completed satisfactory.
Verified missing siesmic bracing was installed. Front canopy ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PART |
Katie Marron
|
|
|
24 hour air test on dry system, 43.5 psi @ 2pm on 9/19/16
-Verified the rest of the dry pipe system, missing two seismic braces at elbow to canopy. - Verified drop ceiling coverage 2nd flr in conference room and center office space, a room was added to the west side of this space and messed up sprinkler coverage(plans noted) -Drop ceiling for hallway in front of elevator and apartments on 2nd flr still pending. -Coverage in operating rooms 1st flr, uprights were added, "OK"
|
INSP-Sprinkler Rough-in | 9/1/2016 | 9/6/2016 | 9/6/2016 | A | PART |
Katie Marron
|
|
|
2nd floor ceiling grid drops inspected, except for large conference rooms and a couple other areas which had no grids installed (see plans). 1st floor hardlids ok to cover. All mains and branch lines inspected (hangars & bracing). Dry system to point marked on plans verified.
The following previously noted items were corrected: kennel modification area and storage drop.
|
INSP-Sprinkler Rough-in | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PART |
Katie Marron
|
|
|
Rough-in inspection of second floor conducted. Hard lid areas (i.e, bathrooms) ok to cover. All mains, branch lines and bracing OK. A few issues are: -uprights spaced within 5' in mechanical room -kennel space shifted so uprights and pendants need to be shifted (see plans) -drop for storage space not cut in -one upright has protector still on
Sprinkler spacing for pendants will need to be verified.
|