Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberNAF16-00057
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 5870 N GLENWOOD
Project NameADA COUNTY PARAMEDICS
Customer Number 
ePlanReviewNo
Description
[ADA County Paramedics]
The fire sprinkler scope of work consists of a one level building with an attic protected with a NFPA 13 system. The attic is a dry system with a steeply pitched roof. The bottom level is a combination light and ordinary hazard 1 system. There is 6” underground with a 4” riser and 4” backflow preventer. The dry system is 4” and the wet system is 3”. The wet system layout is a tree and the dry system is a loop.

The underground piping is under permit NAF16-00055
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final11/21/201611/22/201611/22/2016APASS
DetailsKatie Marron
24 Hr Air Test completed satisfactory. Phone #: ###-####
INSP-Sprinkler Rough-in11/17/201611/21/201611/21/2016APART
DetailsKatie Marron
24 air test began at 9:40 am on 11/21/16. Pressure was 42psi
INSP-Sprinkler Rough-in/Hydro11/17/201611/17/201611/17/2016APASS
DetailsKatie Marron
Hydrostatic test of FDC, Dry system and Wet system completed satisfactory.

24 hr air test still needed for dry system.
INSP-Sprinkler Rough-in/Hydro11/16/201611/16/201611/16/2016PFAIL
DetailsKatie Marron
Hydro was not able to be completed as Riser room was locked upon return after 2 hour period.
INSP-Sprinkler Rough-in/Hydro11/14/201611/15/201611/15/2016AFAIL
DetailsTroy Cobbley
Overhead hydro tests failed due to visible leak on the ground and pressure loss at the guages. I also noted that the supply piping to the FDC needs hydro tested.
INSP-Sprinkler Rough-in/Hydro11/14/201611/14/201611/14/2016PCANC
DetailsTroy Cobbley
Not ready for hydro test due to leak.

Please Contact Perly Daniels 30 minutes before inspection Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in11/9/201611/10/201611/10/2016PPART
DetailsKatie Marron
Rough in for dry and wet system completed. Grid areas ok to cover.
Correction item: Per note on plans earthquake bracing into wood shall be through bolted, contractor to correct and provide verification (photos).
INSP-Sprinkler Rough-in/Hydro10/26/201610/27/201610/27/2016AFAIL
DetailsTroy Cobbley
Stopped rough-in inspection on the dry system due to pipe routing changes including in the remote area. Stopped the rough-in inspection on the wet system due to pipe routing changes in the main that effects the remote area. I also noted a branchline size the did not match plan. Plans need to be re-submitted showing all pipe routing changes. Fitter is using 1/2 lag bolts in the bottom of the 2x6 structure. I need to verify that is ok.