INSP-Final | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | DONE |
Troy Cobbley
|
|
|
permit finaled
|
DOC - Permit Finaled | | | 8/25/2017 | | DONE |
|
|
|
Passed final per Troy
|
INSP-Final | 8/9/2017 | 8/11/2017 | 8/11/2017 | A | FAIL |
Troy Cobbley
|
|
|
Repair the retaining straps, provide the calc sticker and provide the updated approved drawings for the earthquake bracing locations
|
INSP-Sprinkler Rough-in/Hydro | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Troy Cobbley
|
|
|
Inspection turned into a conference. Hydro test has already been performed. Earth quake bracing is not installed in the approved locations. It will need to be installed as approved or calculations resubmitted for the new locations. Retaining straps are still not installed correctly. Need cap on FDC. Need sticker on bell. Need service tag on riser. Need data sheet on the test valve that it has the correct orfice for the inspector test. Need forward flush done. And ultimately need the fire alarm interconnections verified.
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2017 | 7/17/2017 | 7/17/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete. Sway bracing installation does not match what is on the city approved drawings, sway bracing will need to be repaired, numerous retaining straps throughout space are not installed correctly (straps found need to be bent around truss to retain beam clamp) As-builts will need to be completed and submitted for pipe that was installed around HVAC penetrations through deck.
|