INSP-Final | 10/10/2018 | 10/10/2018 | 10/10/2018 | P | DONE |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
DOC - Permit Finaled | | | 10/10/2018 | | DONE |
|
|
|
per Troy C. doc final-he can't do that in the field
|
INSP-Final | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the canopy put on the head in the upper level closet and a 175 degree head to be installed in the Laundry Room as per plan. When that is done we will need to test the fire pump. Also the sign, as per plan, needs to be installed at pump.
Call Anthony to coordinate, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/27/2018 | 7/31/2018 | 7/31/2018 | A | PASS |
Troy Cobbley
|
|
|
Tenting Inspection passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 7/27/2018 | 7/27/2018 | 7/27/2018 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for tenting. Half of the piping has already been covered with sheet rock so I can't check tenting. The half that has not been covered looks good. There were no ladders on site to get high enough to look across the ceiling.
Tenting inspection, ready when you have time. Thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Spacing for pendant at stove will be checked at final. First and second floor piping can be covered but third floor can not until a tenting inspection has passed.
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2018 | 7/13/2018 | 7/13/2018 | P | PART |
Troy Cobbley
|
|
|
General rough-in for overhead pipe passed. I noted in the Kitchen area the pendant is not placed as per plan and may be too close to the oven when installed. I noted in the Dining room the pendant head is too far off of the stair wall (8' max.) and the stair landing at this same location has no sprinkler protection. Plans have been marked in red at corrections. First ansnd second floor piping can be covered but third floor piping can not until a tenting inspection has been passed. Heads have not been verified (no ladder) and neither has the pump/riser. The riser piping will need to be steel due to the cpvc piping is not listed to be more than 1 1/2" from walls.
Call ahead to coordinate time, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|