Permit Information
Permit NumberPLM16-01124
StatusFinaled
Name MOUNTAIN WEST MECHANICAL INC
Site Address 918 W IDAHO ST
Project NameAthlos Headquarters - Phase 3
Customer Number 
ePlanReviewNo
Description
Plumbing DMV Dom water Rain Drains, Hydronic and geothermal piping
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final5/24/20175/25/20175/25/2017PPASS
DetailsDaryl Spivey
Todd Phone #: ###-####
Final3/21/20173/22/20173/22/2017APART
DetailsDaryl Spivey
We are requesting a Plumbing and Hydronic piping final for the 2nd and 4th floors. The owner is seeking temporary occupancy of the facility involving these two floors. Early AM will be appreciated. Phone #: ###-#### Inspection requested via web by Val Hill
2nd and 4th floor occupancy ok. Backflows all tested ok..........ds
Other3/7/20173/8/20173/8/2017PPASS
DetailsDaryl Spivey
Inspection of boiler flue with templates and supports in place as requested. Phone #: ###-#### Inspection requested via web by Val Hill
Groundwork3/6/20173/7/20173/7/2017APART
DetailsDaryl Spivey
installation of a sump basin and floor sink in the fire pump room. drainage and vent under test.
Also we need an inspection of the boiler flue verifying clearances as requested. Phone #: ###-####
Inspection requested via web by Val Hill
ok to cover g/w. flue needs supported at each story with clearances and graded on horizontal run......ds
Plumbing Rough-in1/18/20171/18/20171/18/2017PPART
DetailsDaryl Spivey
todd Phone #: ###-####
gas tested ok at 30 lbs..........ds
Other12/13/201612/13/201612/13/2016APART
DetailsDaryl Spivey
Gas line pressure test. Phone #: ###-#### Inspection requested via web by Val Hill
partial gas testfrom meter to about 20 feet inside......30 lb. test.........ds
Water and/or Sewer10/27/201610/27/201610/27/2016APART
DetailsDaryl Spivey
Domestic water and DWV for the main floor and the basement areas. Rough-in ready for cover. Phone #: ###-#### Inspection requested via web by Val Hill
1st floor rough in ok.......ds
Plumbing Rough-in9/27/20169/27/20169/27/2016PPASS
DetailsDaryl Spivey
Todd-mez & 3rd floor-waste and water Phone #: ###-####
Water and/or Sewer9/20/20169/21/20169/21/2016ACANC
DetailsDaryl Spivey
re-established test for DWV levels 2 ; 3 Phone #: ###-#### Inspection requested via web by Val Hill
Plumbing Rough-in9/21/20169/21/20169/21/2016APART
DetailsDaryl Spivey
re-established test for DWV levels 2 ; 3 Phone #: ###-#### Inspection requested via web by Val Hill
restrooms on 2nd and 3rd floor tested ok to cover........ds
Water and/or Sewer9/18/20169/19/20169/19/2016ANR
DetailsBill VanDegrift
DWV rough-in 2nd and third floors Phone #: ###-#### Inspection requested via web by Val Hill
Water and/or Sewer9/14/20169/15/20169/15/2016PCANC
DetailsDaryl Spivey
2nd floor water and DWV restrooms and associated areas. Phone #: ###-#### Inspection requested via web by Val Hill
Plumbing Rough-in9/15/20169/15/20169/15/2016PPART
DetailsDaryl Spivey
2nd floor water and DWV restrooms and associated areas. Phone #: ###-#### Inspection requested via web by Val Hill
2nd floor water ok....waste test failed.........ds
Water and/or Sewer7/21/20167/21/20167/21/2016PPART
DetailsDaryl Spivey
4th floor (Penthouse) DWV completed ; on test.
Hydronic piping completed and on test.
Ready for cover. Phone #: ###-#### Inspection requested via web by Val Hill
4th fl restroom ok for cover............ds
Water and/or Sewer7/12/20167/13/20167/13/2016APART
DetailsDaryl Spivey
4th floor Penthouse domestic water piping for cover. Phone #: ###-#### Inspection requested via web by Val Hill
water ok on penthouse area....ds
Other6/21/20166/21/20166/21/2016PPASS
DetailsDaryl Spivey
Rain drain pressure test // Vale Phone #: ###-####
roof drains tested ok.......ds
Water and/or Sewer6/7/20166/8/20166/8/2016ACANC
DetailsDaryl Spivey
under floor waste and vents in basement mechanical room and trench drain installation. Phone #: ###-#### Inspection requested via web by Val Hill
Groundwork6/8/20166/8/20166/8/2016APASS
DetailsDaryl Spivey
under floor waste and vents in basement mechanical room and trench drain installation. Phone #: ###-#### Inspection requested via web by Val Hill
Water and/or Sewer5/16/20165/16/20165/16/2016APART
DetailsDaryl Spivey
Hydronic piping test on 2nd floor. Phone #: ###-#### Inspection requested via web by Val Hill
2nd floor hydronics tested ok..........ds
Water and/or Sewer4/19/20164/20/20164/20/2016APART
DetailsDaryl Spivey
DWV venting in basement for cover Phone #: ###-#### Inspection requested via web by Val Hill
g/w tested ok for cover.......ds
Water and/or Sewer4/14/20164/18/20164/18/2016APART
DetailsDaryl Spivey
Partial under slab DWV and Hydronic piping pressure test on 3rd floor Phone #: ###-#### Inspection requested via web by Val Hill
partial underground in basement to interceptor ok.......turn vent on downstream side..........partial on hydronics on 3rd floor tested ok.........ds
Groundwork3/29/20163/30/20163/30/2016APART
DetailsDaryl Spivey
Val-underground drainage Phone #: ###-####
main drain line for trench drains tested ok.........ds