Permit Information
Permit NumberPLM17-02776
StatusFinaled
Name GRANITE EXCAVATION INC
Site Address 6633 S FEDERAL WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration: Install (2) new 6" sewer services to (2) new sewer lift stations. Install new 1.25" pressure sewer line to existing manhole
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/11/201710/12/201710/12/2017PPASS
DetailsEric Strole
Grease Interceptor gasketed lids have been installed as well as 48" ring and lid for lift station behind auto body shop. Request Final Inspection. Phone #: ###-#### Inspection requested via web by Taylor Landa
Water and/or Sewer8/18/20178/21/20178/21/2017PCANC
DetailsEric Strole
Scheduling for Final Inspection at 3:00 pm. Phone #: ###-#### Inspection requested via web by Taylor Landa
Water and/or Sewer8/9/20178/9/20178/9/2017PPART
DetailsEric Strole
Baffels are installed in interceptor, need gasketed lids and sewer from bathrooms tie-in.
Water and/or Sewer8/8/20178/9/20178/9/2017ANR
DetailsEric Strole
Inspection of Sewer Lift Station Pumps. Phone #: ###-#### Inspection requested via web by Taylor Landa
Water and/or Sewer8/4/20178/7/20178/7/2017PPART
DetailsEric Strole
We are planning on pressure testing the 1.25" pressure sewer line at 1:00 pm. Phone #: ###-#### Inspection requested via web by Taylor Landa-Test on pressure sewers pass.
Water and/or Sewer8/3/20178/4/20178/4/2017PPART
DetailsEric Strole
Test on interceptor pass and upstream and downstream piping. Still need tie-in to lift station and pressure line on this system of two.
Water and/or Sewer8/3/20178/3/20178/3/2017PPART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Taylor Landa-Start of 24 hr test on interceptor.
Storm Drains8/3/20178/4/20178/3/2017ACANC
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Taylor Landa
Other7/25/20177/31/20177/31/2017ADONE
DetailsEric Strole
Onsite Pre-Construction Meeting scheduled with Eric Stole at 8:00 a.m. Phone #: ###-#### Inspection requested via web by Taylor Landa-Pre-construction meeting. Per Rick with public works the truck wash building will have a fuel intercepor with a valve before that when not washing trucks will divert rain water to the old septic system system and not alow storm water into the new pressure sewer system.