Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberPLM18-03523
StatusFinaled
Name JOHANSEN PLUMBING
Site Address 3290 E BARBER VALLEY DR
Project NameVeranda at Barber Station
Customer Number 
ePlanReviewNo
Description
New Construction (Building B)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final2/19/20192/20/20192/20/2019APASS
DetailsEric Strole
Final2/18/20192/19/20192/19/2019APART
DetailsEric Strole
please call Kinley 30 before showing up Phone #: ###-#### Inspection requested via web by Brian Johansen-Need to run seperate water supply to soap dispensor at mop sink.
Final1/30/20191/31/20191/31/2019APART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Temp final ok.
Final1/24/20191/24/20191/24/2019PCANC
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-No TCO till approved by the city.
Plumbing Rough-in1/16/20191/17/20191/17/2019PPASS
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Floor sink for pedicure chair pass.
Other12/27/201812/28/201812/28/2018ADONE
DetailsEric Strole
Conf. With Eric and Kinley Phone #: ###-#### Inspection requested via web by Brian Johansen-Conferance on backflows required on pedicure. Need to install rpba's.
Plumbing Rough-in11/16/201811/19/201811/19/2018APASS
DetailsMatt Wrobel
Phone #: ###-#### Inspection requested via web by Brian Johansen
Plumbing Rough-in11/8/201811/9/201811/9/2018APART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Rough-in complete except tie-in of lift station.
Water and/or Sewer11/8/201811/9/201811/9/2018ACANC
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen
Plumbing Rough-in11/7/201811/7/201811/7/2018PPART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-All rough-in good except the 2 3" cpvc tees in overhead in common area.
Plumbing Rough-in11/6/201811/7/201811/7/2018AFAIL
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Test on water fail & 1 1/2" horizontal vent can not exceed 20 feet.
Storm Drains11/6/201811/7/201811/7/2018APART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Roof drains for canopy pass.
Plumbing Rough-in11/2/201811/5/201811/5/2018APART
DetailsEric Strole
and gas test Phone #: ###-#### Inspection requested via web by Brian Johansen-60 lb gas test pass. This completes gas pipe rough-in. Can only use like material with cpvc female adaptors.
Plumbing Rough-in10/24/201810/25/201810/25/2018APART
DetailsEric Strole
lift station Phone #: ###-#### Inspection requested via web by Brian Johansen-Vent pass.
Pressure Test10/23/201810/24/201810/24/2018APART
DetailsEric Strole
gas and condensate inspection Phone #: ###-#### Inspection requested via web by Brian Johansen
60 # gas test, both corridors only to pass
Plumbing Rough-in10/23/201810/23/201810/23/2018PFAIL
DetailsEric Strole
gas and condensate inspection Phone #: ###-#### Inspection requested via web by Brian Johansen-!st gauge will not zero out & 2nd gas test fail.
Plumbing Rough-in10/18/201810/19/201810/19/2018APART
DetailsEric Strole
Building B please Phone #: ###-#### Inspection requested via web by Brian Johansen-MC prep & area A rooms pass.
Plumbing Rough-in10/18/201810/18/201810/18/2018PPART
DetailsEric Strole
Building B please Phone #: ###-#### Inspection requested via web by Brian Johansen-Need to get water up on test and finish securing hot water in overhead.
Plumbing Rough-in10/17/201810/18/201810/18/2018AFAIL
DetailsEric Strole
building B please Phone #: ###-#### Inspection requested via web by Brian Johansen-Missing nailplates, water test fail, all overhead hot waterlines need secured.
Plumbing Rough-in10/17/201810/17/201810/17/2018PFAIL
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Need to fix reverse grade on vents and missing nailplates& fix leak on vent.
Plumbing Rough-in9/28/20189/28/20189/28/2018PNR
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen
Groundwork9/27/20189/27/20189/27/2018PPART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Brian Johansen-Section of pressure sewer ok to cover as long as it is per lift station specs.