Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD17-02156
StatusFinaled
Name RRC CONTRACTORS
Site Address 311 N CURTIS RD
Project NameBaird Oil - Metal Building Add
Customer Number 
ePlanReviewYes
Description
(BAIRD OIL – NEW METAL BUILDING ADDITION – SOUTHWEST SIDE OF EXISTING BUILDING) (DRH17-00093) (11-13-17 PLAN MODIFICATION TO MODIFY THE FOOTINGS AND FOUNDATION ALONG GRID 6 TO BE SIMILAR TO THE FOOTINGS AND FOUNDATION ALONG GRID 1 TO ALLOW FOR AN OVERHEAD DOOR IN THE WALL AT GRID 6. THE WALL BRACING ALONG GRID 6 IS ALSO REQUIRED TO MATCH THE WALL BRACING ALONG GRID 1.) This building does not have a fire sprinkler system. To construct a 4,408 square foot building adjacent to an existing 4,800 square foot building. Both buildings are considered to be one 9,208 square foot building for the application of the building code since they are separated by only 4 feet. Work is to include concrete footings, concrete stem walls, concrete slab on grade, steel column and girder moment frames, steel rod cross bracing, horizontal wall and roof purlins, steel siding, steel roofing, exterior windows, overhead doors, and side-hinged swinging doors. The building addition will not be insulated, conditioned, or have electric lighting. An existing gas pump and gas pump cover will be demolished. Special Inspection is potentially required for welding and for bolding. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy for the existing building and for the building addition. A separate permit is required for racks more than 8 feet tall. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  12/13/2019 DONE
Spoke with Jessica regarding final fees due. She took the information and said she would relay it to Jack in accounts payable.
Print Statement  12/13/2019 DONE
Third Notice 4/16/20194/12/2019 DONE
This permit finaled on the web by derek cooper
Third Notice 3/12/20194/11/2019 DONE
mailed 4-12-19 with third and final follow up letter
Third Follow up  4/11/2019 DONE
final follow up letter
Third Notice 2/11/20193/7/2019 DONE
mailed 3-11 with second follow up letter
Second Follow up  3/7/2019 DONE
Third Notice 1/13/20192/6/2019 DONE
mailed 2/11/19 with first follow up letter
First Follow up  2/6/2019 DONE
Third Notice 12/18/20181/8/2019 DONE
mailed 1-11-19
Third Notice 11/18/201812/13/2018 DONE
mailed 12-14
Second Notice 10/22/201811/13/2018 DONE
mailed 11-14
First Notice 9/29/201810/12/2018 DONE
mailed 10-15-18
Print Occupancy Form  9/19/2018 DONE
Permanent Occupancy  9/19/2018 DONE
BLD-Final9/18/20189/18/20189/18/2018PPASS
DetailsMike Jordan
Bruce Phone #: ###-####
Zoning Approval9/18/20189/18/20189/18/2018 DONE
DetailsAndrea Tuning
FIRE-Final Inspection7/19/20187/20/20187/20/2018APASS
DetailsTroy Cobbley
Life safety passed. Fire dept verified gate function

Bruce Phone #: ###-####
PubWorks Occupancy Approval7/5/20187/5/20187/5/2018 DONE
DetailsTiffany Lowery
FIRE-Final Inspection6/28/20186/28/20187/2/2018PFAIL
DetailsTroy Cobbley
Need verification from the fire dept that the knox key for activation of the gate is functional.

Please call ahead for access - Bruce Phone #: ###-####
BLD-Final2/1/20182/2/20182/2/2018PPASS
DetailsMike Jordan
BRUCE Phone #: ###-####. Ok for Temp. occ. Will be ok for perm occ. once zoning and fire sign perm.
FIRE-Final Inspection2/1/20182/2/20182/2/2018APART
DetailsTroy Cobbley
A temporary for life safety is being given with scott and rons permission until the fire hydrant and opticon has been installed and tested.

BRUCE Phone #: ###-####
Zoning Approval Temp2/2/20182/2/20182/2/2018 DONE
DetailsKatelyn Menuge
Temp Zoning Approval- BND18-00027 Asphalt and landscape
Recd Pcfee & Taken To Pln CK  2/2/2018 DONE
CHANGE STATUS TO (ISS)  2/2/2018 DONE
Print Occupancy Form  2/2/2018 DONE
FIRE-Conference1/17/20181/17/20181/17/2018PDONE
DetailsTroy Cobbley
We discussed life safety issues. There were no fire review notes on site. I noted that an Opticon may be required at the electric gate and the contractor neeeded to verify the correct size of fire extinguishers needed. Also the fire hydrant has not been installed yet.


Bruce Phone #: ###-####
BLD-Conference1/16/20181/16/20181/16/2018PDONE
DetailsMike Jordan
Bruce Phone #: ###-####
BLD-Foundation11/15/201711/16/201711/16/2017APASS
DetailsBrandon Shaw
wall 11 pour time // shawn Phone #: ###-####
BLD-Footing11/14/201711/14/201711/14/2017PPASS
DetailsMike Jordan
pour time 1:15pm- Sean Phone #: ###-####. Additional column pad footings on north side of building for added overhead door.
CHANGE STATUS TO (ISS)  11/14/2017 DONE
OVERRIDE  11/13/2017  
Plan assigned to (CJW)11/9/201711/9/201711/13/2017 PASS
DetailsCarl Westfall
Plan Modification
Routing - PLAN CHECK11/9/2017 11/13/2017 PASS
DetailsCarl Westfall
To modify the footings and foundation along Grid 6 to be similar to the footings and foundation along Grid 1 to allow for an overhead door in the wall at Grid 6. The overhead door was shown on the architectural drawings from the beginning but not on the metal building drawings. Since the proposed foundation along Grid 6 appears to be the same along Grid 1 which has already been reviewed and approved and the conditions appear to be the same, it did not seem necessary to send it back to the Consultant Structural Engineer for review.
PLANS/APPL TAKEN TO FRONT DESK  11/13/2017 DONE
Permit Ready to Issue  11/13/2017 DONE
DetailsChristina Prado
All requirements met for Plan Mod

DO NOT RE-ISSUE - Change status to ISS once all review fees are paid in full
Plan Modification Accepted  11/9/2017 DONE
DetailsChristina Prado
Plan Mod requested to revise the footing details
BLD-Foundation11/3/201711/6/201711/6/2017PCANC
DetailsBrandon Shaw
Bruce Phone #: ###-####
BLD-Footing11/2/201711/2/201711/2/2017PPASS
DetailsMike Jordan
BLD-Other11/1/201711/2/201711/2/2017ANR
DetailsMike Jordan
rebar // Bruce Phone #: ###-####. Moved to pm inspection.
Issue PAID IN FULL permit  11/1/2017 DONE
Print Occupancy Form  11/1/2017 DONE
OVERRIDE  10/12/2017  
Plan assigned to (CJW)7/7/20177/7/201710/12/2017 PASS
DetailsCarl Westfall
(4th done) (Aug 10 - 25 days) (19 sheets) Baird Oil
Plan resubmittals received  10/12/2017 DONE
Routing - PLAN CHECK10/12/2017 10/12/2017 PASS
DetailsCarl Westfall
Routing - Design Review10/12/2017 10/12/2017 PASS
DetailsAndrea Tuning
PLANS/APPL TAKEN TO FRONT DESK  10/12/2017 DONE
Permit Ready to Issue  10/12/2017 DONE
ALL MET
Need
GC FORM
Revised Cert of Value
Plan resubmittals requested  10/9/2017 DONE
Plan resubmittals received  10/6/2017 DONE
Routing - PLAN CHECK10/6/2017 10/6/2017 PASS
DetailsCarl Westfall
Started routing
Routing - Design Review10/6/2017 10/6/2017 FAIL
DetailsAndrea Tuning
The ESC, civil site plan, archteictural site plan and landscape plans do not match one another.

The applicant is also required to pave all areas where trucks and vehicles will drive, park or manuever.
Plan resubmittals requested  10/3/2017 DONE
Routing PW Drainage10/2/2017 10/3/2017 PASS
DetailsBrian Murphy
Meeting  10/2/2017 DONE
Appendix J taken to Brian Mu
Plan resubmittals received  10/2/2017 DONE
Routing - PLAN CHECK10/2/2017 10/2/2017 PASS
DetailsCarl Westfall
Drawings approved
Routing - Design Review10/2/2017 10/2/2017 FAIL
DetailsAndrea Tuning
The ESC, civil site plan, archteictural site plan and landscape plans do not match one another.

The applicant is also required to pave all areas where trucks and vehicles will drive, park or manuever.
Additional plans submitted  9/29/2017 DONE
received original O & M agreement; taken to Brian Murphy
Plan resubmittals requested  9/21/2017 DONE
Routing - FIRE9/12/2017 9/20/2017 PASS
DetailsScott Arellano
Attached comments to plans.
Routing PW Drainage9/12/2017 9/15/2017 FAIL
DetailsBrian Murphy
need drainage reportand o and m hydrocarbon filter
Routing Off Site - STRUCTURAL9/12/2017 9/14/2017 PASS
DetailsCarl Westfall
Chris Holladay (AHJ)
Routing - Design Review9/12/2017 9/12/2017 FAIL
DetailsAndrea Tuning
The site plan shall be accurate and complete. It shall include property lines, structures, surfacing, fencing, etc.
The site plana nd landscape plan do not match.
Paint the existing building to match the colors and materials proposed with the new building or construct the new building using green standing metal seam walls, white standing metal seam roof and brown trim to match the existing building.
Install weather protection that is a minimum of 3-feet in depth over the main entrance of the new building.
Pave all drive aisles where trucks and vehicles will travel.
Routing - PLAN CHECK9/11/2017 9/12/2017 PASS
DetailsCarl Westfall
Pending approval by structural
Plan resubmittals received  9/11/2017 DONE
Route to Impact Fee Review8/19/20178/22/20178/25/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan resubmittals requested  8/22/2017 DONE
Street lights signed off so that the workflow could be sent back to the Architect.
1st review completed  8/22/2017 DONE
Routing PW Street Lights7/10/2017 8/21/2017 PASS
DetailsTom Marshall
Routing - PLAN CHECK7/7/2017 8/19/2017 FAIL
DetailsCarl Westfall
Revised drawings required
Plan resubmittals requested  8/19/2017 DONE
Plan review report Emailed to the Architect. Street lights has not signed off so the workflow could not be sent back to the Architect.
Routing PW Solid Waste7/10/2017 8/1/2017 PASS
Details
Routing Off Site - STRUCTURAL7/7/2017 7/27/2017 FAIL
DetailsCarl Westfall
Chris Holladay (AHJ)
Plan Reviewer's activity  7/26/2017 DONE
Received and uploaded structural calculations for the metal building
Routing PW Drainage7/10/2017 7/21/2017 FAIL
DetailsBrian Murphy
need hydro carbon insert and enginer letter
Routing PW Sewer Design7/10/2017 7/13/2017 PASS
DetailsKyle S. Rosenmeyer
Parcel is on septic.
Routing - Erosion and Sediment7/7/2017 7/12/2017 PASS
DetailsAndy J. Long
ESC plan and site map approved. Valid PD, need to designate RP.
Routing - Addressing7/7/2017 7/11/2017 PASS
DetailsLaura Hunter
Routing - FIRE7/7/20177/7/20177/10/2017 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing PW Environmental7/10/2017 7/10/2017 PASS
DetailsTerry Alber
No interior drains noted.
Routing - PUBLIC WORKS7/7/2017 7/10/2017 PASS
DetailsRachael Beierle
Routing - PLANNING7/7/2017 7/10/2017 PASS
DetailsCody Riddle
Approved by DR.
Routing - PLANNING Land Div7/7/2017 7/10/2017 PASS
DetailsTodd Tucker
Routing - Design Review7/7/2017 7/7/2017 FAIL
DetailsAndrea Tuning
The site plan shall be accurate and complete. It shall include property lines, structures, surfacing, fencing, etc.
Paint the existing building to match the colors and materials proposed with the new building or construct the new building using green standing metal seam walls, white standing metal seam roof and brown trim to match the existing building.
Install weather protection that is a minimum of 3-feet in depth over the main entrance of the new building.
Pave all drive aisles where trucks and vehicles will travel.
Intake Approval  7/7/2017 PASS
Intake Approval  7/1/2017 FAIL
DetailsJulie Romig
Need:
1. Erosion control narrative and plans
2. Verification of Legal Lot or Parcel Form - contact Todd Tucker
3. Upload metal building drawings as individual sheets.
4. Structural details and calculations for foundation and attachment of metal building to foundation.
5. Structural calculations for metal building.
6. Door and door hardware schedule.
7. Location of required plumbing fixtures.
Application received  6/29/2017 DONE
Application submitted via PDS Online on Jun 29 2017 12:11PM