Permanent Occupancy | | | 4/1/2020 | | DONE |
|
|
|
|
Zoning Approval | 3/30/2020 | 3/30/2020 | 3/30/2020 | | PASS |
Katelyn Menuge
|
|
|
Owner said will finish sealing corten panels and clean up rust stains.
|
Temporary Occupancy | 3/26/2020 | 6/24/2020 | 3/26/2020 | | DONE |
Gabe Brenner
|
|
|
|
Telephone call | | | 3/25/2020 | | DONE |
|
|
|
Per Inspector Dave Hannah, Building is Ok to final. Email in Documents.
|
Temporary Occupancy | 3/20/2020 | 6/15/2020 | 3/20/2020 | | DONE |
Gabe Brenner
|
|
|
|
Temporary Occupancy | 3/23/2020 | 6/15/2020 | 3/20/2020 | | DONE |
Gabe Brenner
|
|
|
reprint with new address
|
PubWorks Occupancy Approval | 3/20/2020 | 3/20/2020 | 3/20/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/17/2020 | 3/17/2020 | 3/19/2020 | P | PART |
Dave Hannah
|
|
|
Tim - Inspection for Temporary Occ Phone #: ###-#### ok for tco
|
FIRE-Final Inspection | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete, signature card not available at time of inspection.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | FAIL |
Jim Page
|
|
|
Fire riser room is not a rated room as required by Boise Municipal Code, Chapter 7 Fire Prevention Code section 903.1.2. Provide building permit fire review comments for project, documents are required to be onsite, per conversation with point of contact they are not onsite. Install addressing that is compliant with 2016 IFC section 505, current addressing does not meet the requirements of section 505. Provide corner lot addressing as defined in the BMC Chapter 7 section 505.3. Provide fire extinguishers with current inspection tags for each unit, fire extingiushers can be mounted under the sink. Correct the addressing with the monitoring company.
Tim Phone #: ###-####
|
Zoning Approval Temp | 3/16/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Katelyn Menuge
|
|
|
Temporary - BND20-00064
|
BLD-Conference | 1/6/2020 | 1/6/2020 | 1/7/2020 | P | DONE |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Energy code compliance | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Dave Hannah
|
|
|
Units 106, 107, 108 - Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 11/4/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Dave Hannah
|
|
|
Unit 106 - Curt Phone #: ###-####
|
BLD-Energy code compliance | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | PASS |
Dave Hannah
|
|
|
Unit 109 and 110 - Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Dave Hannah
|
|
|
units 106 & 107 // Kurt Phone #: ###-#### unit 107 only
|
BLD-Framing/Rough-in | 10/24/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Dave Hannah
|
|
|
unit 108 only // Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PASS |
Mike Jordan
|
|
|
Kirt Phone #: ###-####. Unit 109 only.
|
BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending PLM rough-in approval...
|
Routing - MECHANICAL | 8/21/2019 | | 8/21/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Foundation | 4/25/2019 | 4/25/2019 | 4/26/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####third floor center walls ok
|
BLD-Foundation | 4/15/2019 | 4/15/2019 | 4/16/2019 | P | PART |
Dave Hannah
|
|
|
Tim Phone #: ###-#### third floor ext walls ok
|
BLD-Foundation | 2/11/2019 | 2/11/2019 | 2/12/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-#### second level and ext stair north bld and south stair
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Dave Hannah
|
|
|
wall-tim Phone #: ###-#### first floor center walls
|
BLD-Footing | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | PART |
Dave Hannah
|
|
|
wall // tim Phone #: ###-#### first level north building
|
BLD-Foundation | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | NR |
Mike Jordan
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PART |
Dave Hannah
|
|
|
pouring at 3:30 Tim Phone #: ###-#### walls between units ok
|
BLD-Foundation | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PART |
Dave Hannah
|
|
|
Tim-pour time 3:00 Phone #: ###-#### first 4 ft ok
|
BLD-Footing | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Dave Hannah
|
|
|
Pour at 3 // Tim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/10/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/10/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/2018 | | DONE |
|
|
|
|
Telephone call | | | 8/28/2018 | | DONE |
|
|
|
Left a message for Greg informing him this permit is 10 days past the expiration date and that is he would like to he may send in a request for one final 180 day extension
|
Telephone call | | | 8/17/2018 | | DONE |
|
|
|
Left a message for Greg informing that these permits are going to expire tomorrow (8/18/18) at 5pm. Informed that he may send in a 2nd and final extension request for 180 days
|
Expiration Notice | 8/6/2018 | 8/27/2018 | 8/6/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 8/3/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 5/9/2018 | 5/9/2018 | 8/3/2018 | | DONE |
Julie Romig
|
|
|
08/03 - 3rd Rev - 1st Rev Comp - 502 15th & River Condominiums (BLD17-03010)
|
Routing Off Site - STRUCTURAL | 7/30/2018 | | 8/3/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/3/2018 | | DONE |
|
|
|
ALL MET
NEED
GRD18-00032 NEEDS TO BE ISSUED WITH THIS
RP
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 7/30/2018 | | 8/1/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Street Lights | 7/30/2018 | | 7/30/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 7/16/2018 | | 7/25/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 7/16/2018 | | 7/20/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 7/16/2018 | | 7/19/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Design Review | 7/16/2018 | | 7/16/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 7/16/2018 | | 7/16/2018 | | PASS |
Leon Letson
|
|
|
|
Route to Impact Fee Review | 6/27/2018 | 6/30/2018 | 6/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/14/2018 | | 6/27/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 6/27/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 5/14/2018 | 5/14/2018 | 6/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 5/14/2018 | | 5/24/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 5/14/2018 | | 5/22/2018 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 5/14/2018 | | 5/18/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map and narrative approved. Certified PD, RP to be designated with contract. Site preparation inspection is required.
|
Routing PW Sewer Design | 5/14/2018 | | 5/16/2018 | | FAIL |
DeAnn Brown
|
|
|
Please add tap permit language shown in changemarks on utility plan. Please note property has two existing sewer service lines that were plugged at the property line for demo work. For new taps, these existing services will need to be plugged at the mainline.
|
Routing PW Solid Waste | 5/14/2018 | | 5/15/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLUMBING | 5/14/2018 | | 5/15/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 5/14/2018 | | 5/14/2018 | | FAIL |
Leon Letson
|
|
|
Comply with DR comments regarding parking, trash enclosures, and building design.
|
Routing - Addressing | 5/14/2018 | | 5/14/2018 | | PASS |
Doug Chausow
|
|
|
Parcels will be combined - this address is correct
|
Routing - PUBLIC WORKS | 5/14/2018 | | 5/14/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 5/14/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/14/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/14/2018 | | DONE |
|
|
|
|
Routing PW Street Lights | 5/14/2018 | | 5/14/2018 | | FAIL |
Tom Marshall
|
|
|
Need street light plan with details.
|
Routing PW Drainage | 5/14/2018 | | 5/14/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 5/14/2018 | | 5/14/2018 | | FAIL |
Andrea Tuning
|
|
|
Provide a minimum of 10 bicycle parking spaces on the site. A minimum of 3 of the 10 bicycle parking spaces shall be covered. The bicycle parking spaces shall be located within 50-feet of the main entrance to the building. The spaces shall also be a minimum of 6-feet long and 2.5-feet wide and have an overhead clearance of 7-feet if covered. A 4-foot wide aisle is required between rows of bicycle parking spaces or nearby walls. Stationary racks shall be located on improved non-permeable surfaces and anchored to the ground.
Trash Enlcosure must be located outside of the required setbacks and meet Public Works Standards.
Construct all second and third story windows to be recessed a minimum of 2-inches from the façade.
|
Intake Approval | | | 5/9/2018 | | FAIL |
|
|
|
Pending payment of BLD17-03010, passing pre-screen & routing will begin once all fees are paid in full
|
Intake Approval | | | 3/30/2018 | | FAIL |
|
|
|
|
Extend Review Timeline | | | 1/29/2018 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Intake Approval | | | 9/22/2017 | | FAIL |
|
|
|
Pre-screen #2 9-22-17 CDM
Please see the markups on the submittal checklist for the required resubmittals. all circled items are required.
Revise the code analysis to indicate applicable 2012 IBC
Indicate the type of sprinkler system to be installed.
Indicate either a riser room or PIV location
Indicate hydrant locations.
|
Intake Approval | | | 9/21/2017 | | FAIL |
|
|
|
The form 304 is required to be signed by the owner
Form 310 is required to be signed by the owner.
Please provide the completed form 506 checklist with all applicable required items.
|
Application received | | | 8/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2017 9:55AM
|
First Notice | | 4/11/2020 | | | |
|
|
|
|
First Notice | | 4/5/2020 | | | |
|
|
|
|