First Notice | | 1/9/2020 | 1/29/2020 | | DONE |
|
|
|
This permit finaled on the web by Matt Forrester
|
Permanent Occupancy | | | 12/30/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 12/20/2019 | 12/20/2019 | 12/20/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Dave Hannah
|
|
|
Chase Phone #: ###-####
|
Zoning Approval | 11/15/2019 | 11/15/2019 | 11/15/2019 | | DONE |
Cody Riddle
|
|
|
|
Print Occupancy Form | | | 11/13/2019 | | |
|
|
|
|
Print Occupancy Form | | | 11/13/2019 | | DONE |
|
|
|
|
PubWorks Temp Occupancy Appr | 2/8/2019 | 2/8/2019 | 2/8/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 2/1/2019 | 2/1/2019 | 2/1/2019 | | DONE |
Cody Riddle
|
|
|
Temporary occupancy for school building allowed, subject to compliance with other division requirmenents. Remaining landscaping and improvements bonded under BND19-00009.
|
FIRE-Final Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | CANC |
Jim Page
|
|
|
Keith Phone #: ###-####
|
FIRE-Final Inspection | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, hood suppression system inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
.
early am please- Keith Phone #: ###-####
|
BLD-Conference | 1/22/2019 | 1/22/2019 | 1/28/2019 | P | PASS |
Dave Hannah
|
|
|
Keith-please call to meet Phone #: ###-####
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PART |
Dave Hannah
|
|
|
Temp- Keith Phone #: ###-#### ok for temp occ of phase one
|
BLD-Ceiling Grid Inspection | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PASS |
Dave Hannah
|
|
|
keith Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | PART |
Dave Hannah
|
|
|
Keith Phone #: ###-#### second floor class rooms and hallway south side ok
|
BLD-Conference | 11/26/2018 | 11/27/2018 | 11/27/2018 | P | DONE |
Dave Hannah
|
|
|
After 1:30 please - Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PART |
Brandon Shaw
|
|
|
Ceiling grid in area B
|
BLD-Energy code compliance | 11/8/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 11/7/2018 | 11/7/2018 | 11/8/2018 | P | PART |
Dave Hannah
|
|
|
Keith Phone #: ###-#### ok to insulate po to cover
|
BLD-Framing/Rough-in | 10/23/2018 | 10/24/2018 | 10/24/2018 | A | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PASS |
Dave Hannah
|
|
|
keith Phone #: ###-####
|
BLD-Conference | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | DONE |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2018 | 9/4/2018 | 9/4/2018 | P | PART |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 8/21/2018 | 8/21/2018 | 8/22/2018 | P | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-#### under stairs
|
BLD-Framing/Rough-in | 8/6/2018 | 8/8/2018 | 8/9/2018 | P | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 7/10/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-#### ext walls bldg b and d ok to cover int walls bldg b ok
|
BLD-Framing/Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | NR |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Concrete | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Concrete | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Foundation | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | CANC |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
BLD-Footing | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | PART |
Dave Hannah
|
|
|
Keith Phone #: ###-#### ok after mti sign off
|
BLD-Footing | 12/27/2017 | 12/28/2017 | 12/29/2017 | P | PEND |
Dave Hannah
|
|
|
Keith Phone #: ###-#### ok after spec inspection final signoff
|
Issue PAID IN FULL permit | | | 11/7/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/7/2017 | | DONE |
|
|
|
|
Telephone call | | | 11/6/2017 | | DONE |
|
|
|
called Beniton Construction to see if they were going to come in and sign the permit and get the sign off card-left message
|
OVERRIDE | | | 10/4/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 8/29/2017 | 8/29/2017 | 10/4/2017 | | PASS |
Carl D Madsen
|
|
|
Whittier Elementary
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/4/2017 | | |
|
|
|
Need:
ACHD - ok to issue per building official (see memo in docs)
Revised value (bld review not to exceed state fee) - met
GC form - met
|
Routing - PLAN CHECK | 9/26/2017 | | 10/4/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2017 | | 10/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing Off Site - STRUCTURAL | 9/26/2017 | | 10/4/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 10/3/2017 | | 10/3/2017 | | PASS |
Cody Riddle
|
|
|
Okay per updated landscape plan with additional tree plantings.
|
Routing PW Sewer Design | 10/3/2017 | | 10/3/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Route to Impact Fee Review | 9/11/2017 | 9/14/2017 | 9/29/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing PW Street Lights | 9/28/2017 | | 9/28/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 9/26/2017 | | 9/27/2017 | | FAIL |
Cody Riddle
|
|
|
Tree mitigation plan required.
|
Routing - Design Review | 9/26/2017 | | 9/27/2017 | | PASS |
Andrea Tuning
|
|
|
DR is not required. project is being reviewed by the Current Planning Staff.
|
Routing - Design Review | 8/29/2017 | | 9/26/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - C.D.H | 8/29/2017 | | 9/26/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/11/2017 | | FAIL |
|
|
|
|
Routing - FIRE | 8/29/2017 | 8/29/2017 | 9/8/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans and case.
|
Routing Off Site - STRUCTURAL | 8/29/2017 | | 9/7/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/29/2017 | | 9/7/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 8/29/2017 | | 9/6/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - ELECTRICAL | 8/29/2017 | | 9/5/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2017 | | 9/1/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 8/29/2017 | | 9/1/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - Erosion and Sediment | 8/29/2017 | | 8/30/2017 | | PASS |
Andy J. Long
|
|
|
SWPPP approved. Valid plan designer and onsite RP provided. Site preparation inspection required.
|
Routing PW Drainage | 8/29/2017 | | 8/30/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 8/29/2017 | | 8/30/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/29/2017 | | 8/29/2017 | | PASS |
Bill VanDegrift
|
|
|
provide a sewer cleanout every 100'
per plans and ISPC
|
Routing - PLANNING | 8/29/2017 | | 8/29/2017 | | FAIL |
Cody Riddle
|
|
|
Written approval from Boise Forestry of the tree mitigation plan is required. Also, information on lighting demonstrating compliance with Site Specific Condition #8 is needed.
|
Routing - PLANNING Land Div | 8/29/2017 | | 8/29/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 8/29/2017 | | 8/29/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 8/29/2017 | | 8/29/2017 | | FAIL |
Tom Marshall
|
|
|
|
Intake Approval | | | 8/29/2017 | | PASS |
|
|
|
|
Routing PW Solid Waste | 8/29/2017 | | 8/29/2017 | | PASS |
Evan Carpenter
|
|
|
|
Application received | | | 8/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2017 1:17PM
|