Permit Information
Permit NumberBLD17-04464
StatusFinaled
Name VISSER BUILDING CO
Site Address 503 S ASH ST
Project NameAsh Street Townhomes East Bldg
Customer Number17-04465 & 18-00248
ePlanReviewYes
Description
(ASH STREET TOWNHOMES - EAST BUILDING) There are three building permits under this Eplan (BLD17-04464, BLD17-04465 and BLD18-00248). // 06/21/19 PLAN MOD TO REVISE WINDOW SCHEDULE TO PROVIDE ONLY CODE REQUIRED EEROS. JAR // 11/02/18 PLAN MOD TO SEWER CONNECTION LOCATIONS, GRADING, AND SURFACE FINISH, LANDSCAPING PLANTING AND IRRIGATION, MECHANICAL EQUIPMENT ADN LOCATIONS, PLUMBING SEWER CONNECTIONS MODIFIED TO MATCH CIVIL. JAR // Permit to build the East Building, a 23,742 sq ft multi-family R2 apartment building. This project consists of two 3-story, multi-family residential buildings and one single-story detached carport, and related site work. The two multi-family buildings are of Type VB construction and fully sprinklered with an NFPA 13 system for building area increase. Separate fire sprinkler and fire alarm permits are required as regulated by Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Reviewer's activity  4/14/2020 DONE
DetailsJason Blais
Received LEED Certification documentation - LEED Gold for Homes.
BLD-Final7/17/20197/18/20197/18/2019PPASS
DetailsDave Hannah
Wes Phone #: ###-####
Permanent Occupancy  7/18/2019 DONE
BLD-Final7/16/20197/17/20197/17/2019ANR
DetailsDave Hannah
Wes Phone #: ###-####
Temporary Occupancy7/15/201910/13/20197/15/2019 DONE
DetailsTiffany Carson-Herker
BLD-Final7/10/20197/11/20197/11/2019APART
DetailsDave Hannah
Wes Phone #: ###-#### ok for tco needs to fix windows and sinks in type b units rest rooms
Zoning Approval7/3/20197/3/20197/3/2019 PASS
DetailsJosh Wilson
FIRE-Final Inspection6/24/20196/25/20196/25/2019APASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete.

Wes Phone #: 208-###-####
OVERRIDE  6/24/2019  
Telephone call  6/24/2019 DONE
a call came in for an inspection but i told them the permit was in ready status and fees were due so that needed to be taken care of before anymore inspections can be done. Also emailed Angie B to let her know
CHANGE STATUS TO (ISS)  6/24/2019 DONE
Print Occupancy Form  6/24/2019 DONE
Permit Ready to Issue  6/24/2019 DONE
PLAN MOD
Plan assigned to (JAR)6/6/20196/6/20196/21/2019 DONE
DetailsJulie Romig
06/17 - Plan Mod Ash St Townhomes EERO Windows
Routing - PLAN CHECK6/11/2019 6/21/2019 PASS
DetailsJulie Romig
Plan Mod 2 - Windows
Routing - Design Review6/21/2019 6/21/2019 PASS
DetailsJosh Wilson
Plan Mod 2 - Windows
PubWorks Occupancy Approval6/7/20196/7/20196/7/2019 DONE
DetailsTiffany Lowery
Plan Modification Accepted  6/6/2019 DONE
Page 3 of plan mod app has list of changes
Print Occupancy Form  5/7/2019 DONE
BLD-Wall Bracing3/28/20193/29/20193/29/2019PPASS
DetailsDave Hannah
Interior Shear inspection in units #122, #124, #126, #128, #130, #132, #134 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance3/28/20193/29/20193/29/2019PPASS
DetailsDave Hannah
Insulation inspection in units #122, #124, #126, #128, #130, #132, #134 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall cover3/28/20193/29/20193/29/2019PPASS
DetailsDave Hannah
Wall Cover inspection in units #122, #124, #126, #128, #130, #132, #134 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Framing/Rough-in3/21/20193/21/20193/21/2019PPASS
DetailsDave Hannah
Rough-in inspection prior to insulation on Units #122, #124, #126, #128, #130, #132, #134 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing3/18/20193/18/20193/18/2019PPASS
DetailsDave Hannah
Interior shear inspection on units #114, #116, #118, #120 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance3/18/20193/18/20193/18/2019PPASS
DetailsDave Hannah
Insulation inspection on units #114, #116, #118, #120 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall cover3/18/20193/18/20193/18/2019PPASS
DetailsDave Hannah
wall cover inspection on units #114, #116, #118, #120 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Framing/Rough-in3/11/20193/12/20193/12/2019APASS
DetailsDave Hannah
Pre-insulation framing inspection in units #114, #116, #118. #120 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall cover3/11/20193/12/20193/12/2019APASS
DetailsDave Hannah
Wall cover inspection in unit #112 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing3/11/20193/12/20193/12/2019APASS
DetailsDave Hannah
Interior shear inspection in unit #112 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance3/11/20193/12/20193/12/2019APASS
DetailsDave Hannah
Insulation inspection in unit #112 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall cover3/5/20193/5/20193/5/2019APASS
DetailsDave Hannah
Wall cover inspection in Unit #102 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing3/5/20193/5/20193/5/2019APASS
DetailsDave Hannah
Interior Shear inspection in Unit #102 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance3/5/20193/5/20193/5/2019APASS
DetailsDave Hannah
Insulation inspection in Unit #102 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Framing/Rough-in3/5/20193/5/20193/5/2019APASS
DetailsDave Hannah
Framing inspection prior to insulation in unit #112 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing2/27/20192/27/20192/27/2019PPASS
DetailsBrandon Shaw
Interior Shear inspection for unit #204 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall cover2/27/20192/27/20192/27/2019PPASS
DetailsBrandon Shaw
wall cover inspection for unit #204 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance2/27/20192/27/20192/27/2019PPASS
DetailsBrandon Shaw
Energy Code inspection for unit #204 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing2/26/20192/26/20192/26/2019PPASS
DetailsBrandon Shaw
Insulation inspection on units #202, #204, #106, #108, #110
BLD-Wall cover2/26/20192/26/20192/26/2019PPASS
DetailsBrandon Shaw
Insulation inspection on units #202, #204, #106, #108, #110
BLD-Energy code compliance2/26/20192/26/20192/26/2019PPASS
DetailsBrandon Shaw
Insulation inspection on units #202, #204, #106, #108, #110
BLD-Framing/Rough-in2/19/20192/20/20192/20/2019APASS
DetailsDave Hannah
Framing inspection prior to insulation in units #102, #104 #106, #108, #110, #202, #204 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Framing/Rough-in2/12/20192/12/20192/14/2019PNR
DetailsDave Hannah
Framing inspection in units #102, #202, #204, #104, #106, #108, #110, #112 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Framing/Rough-in2/7/20192/7/20192/7/2019APART
DetailsDave Hannah
Inspection of Roof trusses prior to spray foam application. Phone #: ###-#### Inspection requested via web by Hunter Gomez ok to spray trusses
BLD-Framing/Rough-in2/7/20192/7/20192/7/2019ACANC
DetailsDave Hannah
Inspection of roof truss system prior to spray foam application Phone #: ###-#### >> Inspection requested via web by Hunter Gomez Inspection cancelled from web by: Hunter Gomez
Print Occupancy Form  2/5/2019 DONE
BLD-Wall Bracing1/17/20191/18/20191/18/2019APASS
DetailsDave Hannah
Exterior Shear inspection on all remaining shear walls (East side already inspected) and the final missing hold down (HDU4) in the northwest Sw-3 shearwall. Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing12/20/201812/21/201812/21/2018APASS
DetailsDave Hannah
Exterior 3rd floor shear inspection on eastside north shear walls prior to masonry Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing12/17/201812/17/201812/17/2018APASS
DetailsDave Hannah
Shear inspection on 3rd floor east facing shear walls from Gridline 15-10. Mid to late AM if possible. Please call Hunter prior to arrival @ ###-#### Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing12/14/201812/14/201812/14/2018APASS
DetailsDave Hannah
Exterior Shear inspections of 1st ; 2nd floor East wall from gridline 9-3 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing12/6/201812/6/201812/7/2018PPASS
DetailsDave Hannah
Exterior Shear inspection on 1st and 2nd floor walls. East Side of east building, gridlines 14,13,12,11 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing12/7/201812/7/201812/7/2018APASS
DetailsDave Hannah
Exterior Sheer inspection, 1st;2nd floor, east side of building, gridlines 14, 13, 12, 11 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Wall Bracing11/20/201811/20/201811/20/2018PPART
DetailsDave Hannah
Inspection of Hold down anchors (HDU4) prior to being covered by framing Phone #: ###-#### Inspection requested via web by Hunter Gomez first floor ok
CHANGE STATUS TO (ISS)  11/14/2018 DONE
Print Occupancy Form  11/14/2018 DONE
OVERRIDE  11/13/2018  
Plan assigned to (JAR)10/31/201810/31/201811/13/2018 DONE
DetailsJulie Romig
11/13 - Plan Mod Ash Street - General - Plan updates made to comply with DR modification approved on 7/12/18. Civil modification - Sewer connection locations, grading and surface finsh type, PW sewer and drainage to review. Landscape - Surface materials to match civil, landscaping scope, planting materials, irrigation layout. Mechanical - update interior unit types and out door condenser types and locations (all interior wall mounted cassettes). Plumbing - sewer connection modifications to match civil drawings.
Routing PW Drainage11/2/2018 11/13/2018 PASS
DetailsJason C. Taylor
Routing - PLAN CHECK11/2/2018 11/13/2018 PASS
DetailsJulie Romig
Permit Ready to Issue  11/13/2018 DONE
PLAN MOD (BLD and PWK fees due)
Routing PW Sewer Design11/6/2018 11/7/2018 PASS
DetailsDeAnn Brown
Routing - PLUMBING11/2/2018 11/6/2018 PASS
DetailsDan Ediger
Per ISPC AND PLANS
Routing - MECHANICAL11/2/2018 11/5/2018 PASS
DetailsTroy James
Routing - Design Review11/2/2018 11/2/2018 PASS
DetailsAndrea Tuning
Plan Modification Accepted  10/31/2018 DONE
Plan Mod - General - Plan updates made to comply with DR modification approved on 7/12/18. Civil modification - Sewer connection locations, grading and surface finsh type, PW sewer and drainage to review. Landscape - Surface materials to match civil, landscaping scope, planting materials, irrigation layout. Mechanical - update interior unit types and out door condenser types and locations (all interior wall mounted cassettes). Plumbing - sewer connection modifications to match civil drawings.
BLD-Foundation7/17/20187/17/20187/18/2018PPASS
DetailsDave Hannah
Late afternoon inspection of the rebar in thickened footings; 7am pour tomorrow morning with MTI special inspection Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Energy code compliance6/21/20186/22/20186/22/2018APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Hunter Gomez. rigid insulation on interior side of footings ok.
BLD-Foundation6/15/20186/18/20186/18/2018APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD-Footing6/11/20186/11/20186/12/2018PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ben Sears
Issue PAID IN FULL permit  5/4/2018 DONE
Print Occupancy Form  5/4/2018 DONE
OVERRIDE  5/3/2018  
Plan assigned to (JAR)1/23/20181/23/20185/3/2018 DONE
DetailsJulie Romig
*1st Rev Comp - 5th Rev - 502 Ash Street townhomes East
Routing - PLAN CHECK5/3/2018 5/3/2018 PASS
DetailsJulie Romig
Routing - Design Review5/3/2018 5/3/2018 PASS
DetailsSarah Schafer
Approved per DRH17-00146.
Routing PW Drainage5/3/2018 5/3/2018 PASS
DetailsJason C. Taylor
PLANS/APPL TAKEN TO FRONT DESK  5/3/2018 DONE
Permit Ready to Issue  5/3/2018 DONE
ALL MET
NEED
RP
GC FORM
REVISED VALUE
Routing PW Drainage4/9/2018 4/17/2018 FAIL
DetailsJason C. Taylor
Routing - PLAN CHECK4/9/2018 4/13/2018 FAIL
DetailsJulie Romig
4th Review
Routing - Addressing4/9/2018 4/11/2018 PASS
DetailsDoug Chausow
Corrected address: 503 S Ash St
Routing - PUBLIC WORKS4/9/2018 4/10/2018 PASS
DetailsRachael Beierle
Routing PW Solid Waste4/10/2018 4/10/2018 PASS
DetailsEvan Carpenter
Routing - Design Review4/9/2018 4/9/2018 FAIL
DetailsSarah Schafer
Routing - PLANNING3/22/2018 4/3/2018 PASS
DetailsLeon Letson
Routing PW Drainage3/22/2018 4/3/2018 FAIL
DetailsJason C. Taylor
Routing - PLAN CHECK3/22/2018 3/28/2018 FAIL
DetailsJulie Romig
3rd Review - Plan Review report emailed to architect.
Routing - Design Review3/22/2018 3/26/2018 FAIL
DetailsSarah Schafer
Easements still required, lighting sheets to be uploaded but reviewed and are appropriate, window detail has been discussed.
Routing - PUBLIC WORKS3/22/2018 3/22/2018 FAIL
DetailsRachael Beierle
Routing - Addressing3/22/2018 3/22/2018 FAIL
DetailsDoug Chausow
Parcels need to be consolidated
Routing - Design Review3/12/2018 3/20/2018 FAIL
DetailsSarah Schafer
Routing PW Drainage3/12/2018 3/16/2018 FAIL
DetailsJason C. Taylor
See changemarks on plans. JCT
Routing - PLAN CHECK3/12/2018 3/15/2018 FAIL
DetailsJulie Romig
Plan Review Report emailed to Architect.
Routing - PLANNING3/12/2018 3/14/2018 FAIL
DetailsLeon Letson
Complete Parcel Consolidation
Routing - PLUMBING3/12/2018 3/13/2018 PASS
DetailsBill VanDegrift
these plans are approved as apartments. not townhomes.
Routing PW Street Lights3/12/2018 3/12/2018 PASS
DetailsTom Marshall
Routing PW Sewer Design3/12/2018 3/12/2018 PASS
DetailsDeAnn Brown
Routing Off Site - STRUCTURAL3/12/2018 3/12/2018 PASS
DetailsJulie Romig
Routing - Addressing3/12/2018 3/12/2018 FAIL
DetailsDoug Chausow
Parcels still need to be consolidated, prior to approval.
Routing - PUBLIC WORKS  3/12/2018 FAIL
DetailsRachael Beierle
MUST CONSOLIDATE PARCELS IN ORDER TO RATE AND ATTACH PERMITS.
Routing - PLANNING1/23/2018 3/11/2018 FAIL
DetailsLeon Letson
Failed per ePlanReview
Route to Impact Fee Review2/27/20183/2/20183/1/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK1/23/2018 2/27/2018 FAIL
DetailsJulie Romig
Non-build easement agreement from ACHD required prior to issuing permit.
1st review completed  2/27/2018 FAIL
DetailsJulie Romig
Routing - Design Review1/23/2018 2/12/2018 FAIL
DetailsSarah Schafer
Project doesn't comply with condition or drawings in DRH17-00146.
Routing - MECHANICAL2/9/2018 2/9/2018 PASS
DetailsTroy James
Routing PW Drainage1/24/2018 2/5/2018 FAIL
DetailsBrian Murphy
APDEX J 10 FOOT STUCTURAL LETTER and porous paving
Routing Off Site - STRUCTURAL1/23/2018 1/31/2018 FAIL
DetailsJulie Romig
Routing - FIRE1/23/20181/23/20181/30/2018 PASS
DetailsScott Arellano
Attached comments to case
Routing - Erosion and Sediment1/23/2018 1/29/2018 PASS
DetailsAndy J. Long
SWPPP with narrative and site map approved, RP not yet designated. Site preparation inspection required.
Routing - Addressing1/23/2018 1/26/2018 FAIL
DetailsDoug Chausow
5 Parcels need to be consolidated via ROS process.
Routing PW Sewer Design1/24/2018 1/26/2018 FAIL
DetailsMike Sheppard
Submit separate sewer plans to Public Works for review.
Routing PW Solid Waste1/24/2018 1/25/2018 PASS
DetailsEvan Carpenter
Routing PW Street Lights1/24/2018 1/25/2018 FAIL
DetailsTom Marshall
Routing - PUBLIC WORKS1/23/2018 1/24/2018 FAIL
DetailsRachael Beierle
FAILED DUE TO ADDRESSING AND LOTS NEED TO BE CONSOLIDATED PRIOR TO RATING.
Routing - MECHANICAL1/23/2018 1/24/2018 FAIL
DetailsTroy James
Routing - PLUMBING1/23/2018 1/24/2018 FAIL
DetailsBill VanDegrift
1) provide a typical plumbing plan (Drain, waste and vent and water) for each unit type. include sizing.
Routing PW Geothermal1/24/2018 1/24/2018 PASS
DetailsJon R. Gunnerson
No connection to geothermal heating district. If wanting to connect contact Public Works at ###-####
Intake Approval  1/23/2018 PASS
Plan Reviewer's activity  1/22/2018 PASS
Plan intake review approved
Intake Approval  1/18/2018 FAIL
(1-18-18) Please look at Sheets A5.02 and A3.03. These sheets appear that they still show the rated windows. Also, even though the buildings will be considered to be one building for area reason, we will still issue 3 separate permits (one for the West building, one for the East building and one for the garage). So, for every reason except allowable area, please make revisions to the drawings to represent 3 separate buildings. Thanks. CJW
Intake Approval  12/20/2017 FAIL
(12-20-17) Please refer to the circled items in the plan intake checklist. Please resolve each item as directed. CJW
Application received  12/7/2017 DONE
Application submitted via PDS Online on Dec 7 2017 3:19PM
First Notice 7/28/2019   
Routing - PUBLIC WORKS11/2/2018