Information based on query as of Tuesday, May 14, 2024.
Permit Information
Permit NumberBLD18-01080
StatusFinaled
Name OLIVE GROVE LLC
Site Address 4252 W ROSE HILL ST
Project NameOlive Grove Apartments II
Customer Number 
ePlanReviewYes
Description
(OLIVE GROVE APARTMENTS II – OLIVE GROVE SENIOR LIVING DEVELOPMENT – PHASE II) (DRH17-00590) (PUD17-00030) (10-30-18 PLAN MODIFICATION TO REMOVE THE FORMERLY PROPOSED ENERGY RECOVER EXHAUST AND MAKE-UP AIR SYSTEM FROM EACH APARTMENT AND TO PROVIDE A CONTINUOUS EXHAUST SYSTEM, WITHOUT MAKE-UP AIR, TO SERVE EACH APARTMENT.) The NFPA 13R fire sprinkler system is used for occupancy. To construct a new 10,276 square foot apartment building (5,248 square feet 1st story and 5,028 square feet 2nd story) having a total of 16 dwelling units (8 units per story). All ground floor units are required to comply as Type B dwelling units with at least one ground floor unit also complying as a Type A dwelling unit. Work is to include concrete footings, concrete stem walls, concrete piers, concrete slab on grade with thickened sections at interior bearing walls, wood stud bearing walls, wood columns, wood stud shear walls with structural sheathing and hold downs, a 1-hr fire-resistance-rated 2nd story floor constructed of wood joists and wood sheathing, an egress balcony and stairways to serve the 2nd story, guards at the 2nd story, exterior doors and windows, cast stone exterior wall wainscot, exterior horizontal lap siding, exterior vertical board and batten siding, 1-hr fire-resistance-rated wood truss roof system with wood roof sheathing, attic draft stops, fiberglass shingles, interior nonbearing walls, 1-hr fire-resistance-rated dwelling unit separation walls, millwork, and finishes. Special Inspection is required for soils, steel connectors for wood, and for anchors post-installed in hardened concrete. The design for the roof trusses is a deferred submittal item. Existing Building C and the new building are considered to be one building. Both buildings are required to have an NFPA 13R fire sprinkler system, both buildings are required to be of Type V-A construction, and both buildings are required to have an R-2 type fire alarm system. The separation of existing Building C from the other existing buildings on site is required to comply with the 2015 IBC based on an imaginary property line drawn between them. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval7/2/20197/2/20197/2/2019 DONE
DetailsTiffany Lowery
Permanent Occupancy  7/2/2019 DONE
Temporary Occupancy6/26/20199/24/20196/26/2019 DONE
DetailsGemma Flores
Zoning Approval6/26/20196/26/20196/26/2019 PASS
DetailsKatelyn Menuge
BLD-Final6/21/20196/21/20196/21/2019PPASS
DetailsTell Riley
window safety devices installed approved plans// final is complete//
BLD-Final6/20/20196/21/20196/21/2019AFAIL
DetailsTell Riley
Rocco- Phone #: ###-####//add window opening control device per plans// call for re-inspection//
PubWorks Temp Occupancy Appr6/21/20196/21/20196/21/2019 DONE
DetailsTiffany Lowery
FIRE-Final Inspection6/19/20196/19/20196/19/2019PPASS
DetailsTroy Cobbley
life safety passed

Matt Phone #: ###-####
BLD-Conference6/17/20196/18/20196/18/2019ADONE
DetailsTell Riley
Rocco Phone #: ###-####//discuss review notes for final inspect//
FIRE-Conference6/17/20196/18/20196/18/2019ADONE
DetailsTroy Cobbley
We went over life safety requirements, need plans, need to relocate fire extinguisher, need to verify the smoke alarms ring back.

Charles Phone #: ###-####
BLD-Other5/9/20195/9/20195/9/2019PPASS
DetailsJim Sly
Chuck- inspection for sauna tubes Phone #: ###-####
BLD-Energy code compliance3/6/20193/7/20193/7/2019APASS
DetailsJim Storey
Charles Phone #: ###-####
BLD-Framing/Rough-in3/4/20193/5/20193/5/2019APASS
DetailsJim Sly
Chuck Phone #: ###-####
BLD-Framing/Rough-in2/28/20193/1/20193/1/2019APASS
DetailsJim Sly
Steve-(GC) Phone #: ###-####
BLD-Framing/Rough-in2/20/20192/20/20192/21/2019PNR
DetailsDave Hannah
Steve-Charles hired GC-he''s calling in the inspections Phone #: ###-#### needs to fire caulk install draft stops in attic fix i joist cut by plumber
BLD-Conference1/31/20191/31/20191/31/2019PDONE
DetailsBrandon Shaw
First story appartments to be as per plans- 1 hour rated bath fans...
BLD-Conference1/11/20191/14/20191/14/2019APASS
DetailsDave Hannah
fire rating issues with duct work // Steve Phone #: ###-#### ok to use metal duct for ext duct
BLD-Framing/Rough-in1/2/20191/2/20191/2/2019PPART
DetailsJim Sly
Steve Phone #: ###-####
Truss repairs.....OK above deck....OK to cover when trades approved in that area.
BLD-Framing/Rough-in12/12/201812/13/201812/13/2018ADONE
DetailsJim Sly
Charles Phone #: ###-####
Consultation.........
BLD-Wall Bracing11/13/201811/13/201811/13/2018PDONE
DetailsJim Sly
Charles Phone #: ###-####
Walk thru ......appears OK.......pending special insp. approval.
OVERRIDE  10/30/2018  
BLD-Conference10/29/201810/29/201810/30/2018PDONE
DetailsJim Sly
Charles Phone #: ###-####
Plan assigned to (CJW)10/23/201810/23/201810/30/2018 PASS
DetailsCarl Westfall
Plan mod - Olive Grove - routed
Plan Reviewer's activity  10/30/2018 PASS
Reviewed and approved the plan modification
Permit Ready to Issue  10/30/2018 DONE
PLAN MOD
CHANGE STATUS TO (ISS)  10/30/2018 DONE
plan mod
Routing - MECHANICAL10/25/2018 10/29/2018 PASS
DetailsTroy James
Routing - PLAN CHECK10/25/2018 10/25/2018 PASS
DetailsCarl Westfall
Plan Modification Accepted  10/23/2018 DONE
Removal of heat reovery exhaust system add continual exhaust system
BLD-Conference10/1/201810/2/201810/2/2018ADONE
DetailsJim Sly
Charles Phone #: ###-####
Inspection of.....Footings for columns, foam insulation at wall, vapor barrier, thickened slab.....all OK.
BLD-Foundation8/24/20188/27/20188/27/2018APASS
DetailsDave Hannah
Charles Phone #: ###-####
BLD-Footing8/23/20188/23/20188/23/2018APASS
DetailsJim Sly
BLD-Foundation8/22/20188/23/20188/23/2018ACANC
DetailsJim Sly
Chuck Phone #: ###-####
BLD-Conference8/22/20188/22/20188/22/2018PDONE
DetailsJim Sly
Charles Phone #: ###-####
BLD-Conference8/15/20188/15/20188/16/2018PDONE
DetailsJim Sly
Chuck Phone #: ###-####
Issue PAID IN FULL permit  8/7/2018 DONE
Print Occupancy Form  8/7/2018 DONE
OVERRIDE  7/18/2018  
Plan assigned to (CJW)4/13/20184/13/20187/18/2018 PASS
DetailsCarl Westfall
(3rd done) 05/17/18 (new - 25 days) (ePlan - 39 sheets) Olive Grove II Apartments
Routing - PLAN CHECK7/17/2018 7/18/2018 PASS
DetailsCarl Westfall
Routing completed
Routing - Design Review7/17/2018 7/18/2018 PASS
DetailsKatelyn Menuge
DRH17-00590
PLANS/APPL TAKEN TO FRONT DESK  7/18/2018 DONE
Permit Ready to Issue  7/18/2018 DONE
need
RP - met
GC - met
Rev Cert of Val - met

MET
ACHD
Routing PW Drainage7/17/2018 7/17/2018 PASS
DetailsBrian Murphy
Plan resubmittals received  7/17/2018 DONE
Plan resubmittals requested  7/2/2018 DONE
PW drainage and Design Review failed
Routing Off Site - STRUCTURAL6/21/2018 6/28/2018 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - PLAN CHECK6/20/2018 6/21/2018 PASS
DetailsCarl Westfall
Pending approval by structural (upload the plan review report)
Routing - Design Review6/21/2018 6/21/2018 FAIL
DetailsKatelyn Menuge
Changes required to site and landscape plan.
Routing PW Drainage6/21/2018 6/21/2018 FAIL
DetailsBrian Murphy
NEED REVISED APPROVED PLAN
Plan resubmittals received  6/20/2018 DONE
Route to Impact Fee Review5/23/20185/26/20185/29/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  5/23/2018 DONE
Plan resubmittals requested  5/23/2018 DONE
Routing - PLAN CHECK4/13/2018 5/23/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing - PLANNING5/17/2018 5/17/2018 PASS
DetailsSusan Riggs
Routing - FIRE4/13/20184/13/20185/16/2018 PASS
DetailsErika Akin
Attached comments to case
Routing PW Drainage5/15/2018 5/15/2018 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL4/13/2018 4/27/2018 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - Erosion and Sediment4/13/2018 4/25/2018 PASS
DetailsAndy J. Long
ESC plan approved. Certified Responsible Person for project must be identified prior to issuance. Site preparation inspection is required.
Routing - MECHANICAL4/13/2018 4/24/2018 PASS
DetailsTroy James
Routing PW Drainage4/13/2018 4/19/2018 FAIL
DetailsBrian Murphy
ROOF DRAINGE APDENDX J
Routing PW Solid Waste4/13/2018 4/19/2018 PASS
DetailsEvan Carpenter
Routing PW Street Lights4/13/2018 4/16/2018 PASS
DetailsTom Marshall
Routing - Addressing4/13/2018 4/16/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS4/13/2018 4/13/2018 PASS
DetailsRachael Beierle
Routing - PLUMBING4/13/2018 4/13/2018 PASS
DetailsDaryl Spivey
Install DCVA on water service lines and per plan and ISPC.
Routing - Design Review4/13/2018 4/13/2018 FAIL
DetailsKatelyn Menuge
drh17-00590 See site and landscape plans.
Routing PW Sewer Design4/13/2018 4/13/2018 PASS
DetailsDeAnn Brown
Intake Approval  4/13/2018 PASS
Intake Approval  3/30/2018 FAIL
DetailsJulie Romig
1. Soils and geotech report - indicated on checklist but not provided.
2. Verification of Legal Lot or Parcel form signed by PDS Subdivision staff. Contact Todd Tucker at TTucker@cityofboise.org.
3. Form 310 Statement of Special Inspections completed and signed by engineer for special inspections (indicated on S-000).
4. Site Drainage report - indicated on checklist but not provided.
5. Drainage System Operation and Maintenance plan - indicated on checklist but not provided.
6. Erosion & Sediment Control narrative - indicated on checklist but not provided.
7. ESC Plan - indicated on checklist but not provided.
8. Upload each drawing sheet as an individual sheet file named per the City of Boise naming convention with sheet number and brief description (ex. A1.1_Site Plan). All drawings have been deleted so they can be uploaded again with proper names and as individual sheets.
9. Envelope ComCheck is for a different project. For buildings up to 3 stories, use REScheck - Multifamily with 2015 IECC using Boise, Idaho as the location.
Application received  3/28/2018 DONE
Application submitted via PDS Online on Mar 28 2018 3:02PM
First Notice 7/12/2019