Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD18-01250
StatusFinaled
Name EKC INC
Site Address 222 N 8TH ST
Project NameFidelity/Montandon Awnings
Customer Number 
ePlanReviewYes
Description
(FIDELITY / MONTANDON BUILDING – AWNINGS AT 8TH STREET AND IDAHO STREET) (DRH18-00043) (CZC17-00279) The fire sprinkler system is used to substitute for 1-hr fire-resistance-rated construction. To construct a new steel awning (2,145 square feet total) on the 8th Street side (6 feet 10 inches at upper projection and 13 feet 9 inches at the lower projection) and on the Idaho Street side (6 feet 9 inches projection) of the Fidelity / Montandon Building. The awnings will cover fenced sidewalk dining and drinking seating for “Diablo & Son’s” and “Bittercreek Alehouse / Red Feather Lounge”. The ceiling of the awnings will have a minimum 10 foot clearance above the sidewalk. The awning frame will be constructed of steel channels, tube steel beams, cantilevered tube steel beams, and tube steel outriggers. The frame will be attached to existing masonry and/or concrete building columns with post-installed anchors. The awning will have tube steel beams, steel angles, steel decking, glass mat sheathing on top of the steel decking, a fully adhered PVC roofing membrane on top of the glass mat sheathing, and a 2 x 2 lay-in ceiling grid with tin panels and light fixtures below. A sloped 2 inch diameter steel rod with clevis connections at the awning and at the existing exterior wall of the building will also support the awning. A steel clevis plate with through bolts and backing plate (or anchors post-installed in masonry or hardened concrete) will be provided to connect the sloped steel rods to the existing building at approximately the same elevation as the 2nd story floor diaphragm. The roof of the awnings will slope away from the building and will drain to the planters below via down spouts. Special Inspection is required for welding, for bolting, and for anchors post-installed in masonry or hardened concrete. Special Inspection is also required to investigate the 10 existing building columns and the exterior walls that will support the new canopy by ground penetrating radar or other means to establish the column and wall base material and reinforcing. Once the existing conditions are determined, a structural evaluation is required to verify that the existing elements will not be overloaded by the new awnings. This structural evaluation is a deferred submittal item. A retractable canvas awning will also be installed next to the fixed steel awning on the Idaho Street side. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The area below the fixed awning is required to have fire sprinkler coverage. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  7/17/2019 DONE
DOC - Permit Finaled  7/17/2019 DONE
Per passing Building Final inspection on 7/2/19 by David H
BLD-Final6/29/20197/2/20197/5/2019APASS
DetailsDave Hannah
Please call me prior to inspection. I''ll meet you onsite and hand over the missing SI report needed for final inspection and permit closure. Phone #: ###-#### Inspection requested via web by Brandon McCurdy
Zoning Approval7/3/20197/3/20197/3/2019 PASS
DetailsJosh Wilson
BLD-Final4/18/20194/19/20194/19/2019AFAIL
DetailsJim Storey
As requested, I''ll bring the SI final acceptance letter with me to hand over during inspection. Phone #: ###-#### Inspection requested via web by Brandon McCurdy Brandon McCurdy mail box full// not on site// singage not in place// zoning not signed off
BLD-Final4/16/20194/17/20194/17/2019ANR
DetailsJim Storey
SI report emailed on 1/24/19. Request permit to be finaled. Phone #: ###-#### Inspection requested via web by Brandon McCurdy
BLD-Final1/23/20191/24/20191/24/2019ANR
DetailsJim Storey
Request building final and permit to be closed out. Phone #: ###-#### Inspection requested via web by Brandon McCurdy need si report.
FIRE-Final Inspection12/13/201812/14/201812/14/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications. Final life fire safety inspection for scope of work complete.Dale Phone #: ###-####
BLD-Framing/Rough-in10/1/201810/1/201810/1/2018PPASS
DetailsDave Hannah
Dale Phone #: ###-####
BLD-Ceiling Grid Inspection9/20/20189/21/20189/21/2018APASS
DetailsDave Hannah
Dale Phone #: ###-####
Expiration Notice9/12/201810/3/20189/12/2018 DONE
DetailsBrittany Hill
Inspection Record Card- Bld  9/12/2018 DONE
Issue PAID IN FULL permit  9/12/2018 DONE
Plan assigned to (CJW)4/25/20184/25/20186/18/2018 PASS
DetailsCarl Westfall
* (3rd done) (May 15 - 15 days) (14 sheets) Fidelity Building Awinings L-3
Routing - PLAN CHECK6/14/2018 6/18/2018 PASS
DetailsCarl Westfall
Structural approved
PLANS/APPL TAKEN TO FRONT DESK  6/18/2018 DONE
Permit Ready to Issue  6/18/2018 DONE
DetailsChristina Prado
Need
GC Form - met
Revised Cert of Value - met

Email permits to brandon@ekcconstruction.com
Routing Off Site - STRUCTURAL6/14/2018 6/14/2018 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Routing Off Site - STRUCTURAL6/6/2018 6/14/2018 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Plan resubmittals requested  6/14/2018 DONE
Plan resubmittals received  6/14/2018 DONE
Routing - PLAN CHECK6/5/2018 6/6/2018 PASS
DetailsCarl Westfall
Pending structural
Plan resubmittals received  6/5/2018 DONE
Plan resubmittals requested  6/4/2018 DONE
Routing Off Site - STRUCTURAL5/31/2018 6/4/2018 FAIL
DetailsCarl Westfall
Jan Welch (Stapley) Since new drawings and structural calculations need to be uploaded, the workflow went back to the applicant. The Structural review was suspended until additional drawings and documents are uploaded.
Routing - Design Review5/31/2018 6/1/2018 PASS
DetailsAndrea Tuning
Routing - PLANNING5/31/2018 6/1/2018 PASS
DetailsNicolette Womack
Routing - PLAN CHECK5/30/2018 5/31/2018 PEND
DetailsCarl Westfall
Pass pending structural
Plan resubmittals received  5/30/2018 DONE
Route to Impact Fee Review5/19/20185/22/20185/21/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  5/19/2018 DONE
Plan resubmittals requested  5/19/2018 DONE
Routing - PLAN CHECK4/25/2018 5/19/2018 FAIL
DetailsCarl Westfall
More information required
Routing - FIRE4/25/20184/25/20185/15/2018 PASS
DetailsErika Akin
Attached comments to case
Routing Off Site - STRUCTURAL4/25/2018 5/7/2018 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - PUBLIC WORKS4/25/2018 4/25/2018 PASS
DetailsMorgan Webb
Routing PW Drainage4/25/2018 4/25/2018 PASS
DetailsBrian Murphy
ACHD/CCDC AREA
Routing - PLANNING4/25/2018 4/25/2018 FAIL
DetailsNicolette Womack
See DR comments.
Intake Approval  4/25/2018 PASS
Routing - Design Review4/25/2018 4/25/2018 FAIL
DetailsAndrea Tuning
Obtain written approval from CCDC allowing the sidewalk café and the awnings to extend into the CCDC owned parcel known as 8th Street.
Plan Reviewer's activity  4/21/2018 PASS
DetailsCarl Westfall
Plan intake review approved
Intake Approval  4/11/2018 FAIL
(4-11-18) Please refer to the circled items in the plan intake checklist. Please resolve each item as directed. CJW
Application received  4/10/2018 DONE
Application submitted via PDS Online on Apr 10 2018 11:59AM
BLD-Final12/13/201812/14/2018 P 
DetailsDave Hannah
Dale Phone #: ###-####