BLD-Energy code compliance | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Tony Young
|
|
|
Blake Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Tony Young
|
|
|
Blake Phone #: ###-####,, ok to cover,, foam sprayed and then added blue foam at the rack ceiling line
|
BLD-Framing/Rough-in | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PART |
Tony Young
|
|
|
Blake Phone #: ###-####,, ok to insulate,, verify fire blocking, seal
|
BLD-Framing/Rough-in | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | PEND |
Dave Hannah
|
|
|
Blake Phone #: ###-#### framing ok but needs air seal done and fire blocking
|
BLD-Aging Inspection | 3/21/2019 | 3/21/2019 | 3/22/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 3/20/2019 | 3/20/2019 | 3/22/2019 | | PEND |
Tony Young
|
|
|
|
Routing - MECHANICAL | 2/8/2019 | | 2/8/2019 | | PASS |
Troy James
|
|
|
New manual j report
|
BLD-Wall Bracing | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | PASS |
Tony Young
|
|
|
Blake Phone #: ###-####
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PART |
Tony Young
|
|
|
Blake Phone #: ###-####,, needs trades 1st,, walk through conference only,, working on exterior,, ok to roof
|
Routing Walk-In (BLD) | 10/11/2018 | 10/11/2018 | 10/11/2018 | A | PASS |
Josh Bogle
|
|
|
Blake asked if he needed a permit to tear down a 10x10 shed. I said "no", just do it
|
Plan assigned to (JAB) Josh | 10/11/2018 | 10/11/2018 | 10/11/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/11/2018 | | 10/11/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2018 | | DONE |
Josh Bogle
|
|
|
NO FEES PLEEZ
|
CHANGE STATUS TO (ISS) | | | 10/11/2018 | | DONE |
|
|
|
per JAB no fees for plan mod plan review only took a couple minutes
|
(F) Reprint permit | | | 10/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/11/2018 | | DONE |
|
|
|
plan mod-adding to the permit a demo of exitisting shed-sent to JAB
|
BLD-Conference | 9/5/2018 | 9/5/2018 | 9/7/2018 | P | PEND |
Tony Young
|
|
|
complaint of piles of debris,, said they would clean up the weekend of the10th
|
BLD-Conference | 9/4/2018 | 9/4/2018 | 9/5/2018 | P | PEND |
Tony Young
|
|
|
complaint of piles of debris,, I expressed priority to get cleaned up and to keep dust down
|
BLD-Conference | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PEND |
Tony Young
|
|
|
complaint of piles of debris,, contractor said he would clean this coming week end
|
BLD-Conference | 7/5/2018 | 7/5/2018 | 7/12/2018 | P | PASS |
Dave Hannah
|
|
|
Blake--- needs a framing conference-would like a call 30 mins before inspection Phone #: ###-####--note: he is getting conflicting info from different contractors and wants to do it contractor will get beams sized for up stairs attic for cieling rafters
|
BLD-Conference | 6/8/2018 | 6/11/2018 | 6/11/2018 | P | PART |
Jim Storey
|
|
|
Blake Phone #: ###-#### need to resolve loads to bearing with beam spans in basement.
|
Routing Walk-In (BLD) | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | PASS |
Josh Bogle
|
|
|
questions - and answers
|
Issue PAID IN FULL permit | | | 5/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/1/2018 | | |
|
|
|
|
OVERRIDE | | | 5/1/2018 | | |
|
|
|
|
OVERRIDE | | | 5/1/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 5/1/2018 | 5/1/2018 | 5/1/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/1/2018 | | 5/1/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/1/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/1/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 5/1/2018 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Inspector's copy Bld permit | | | 5/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2018 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | FAIL |
Josh Bogle
|
|
|
plans unclear
|
Routing - PLAN CHECK | 4/30/2018 | | 4/30/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 4/30/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 4/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 24 2018 1:01PM
|