BLD-Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | DONE |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson 365
|
BLD-Energy code compliance | 1/8/2019 | 1/9/2019 | 1/9/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Energy code compliance | 1/8/2019 | 1/8/2019 | 1/8/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// needs fire blocking at top of main floor chase,, then ok
|
Plan Modification Accepted | | | 1/4/2019 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 1/4/2019 | | 1/4/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Framing/Rough-in | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Tony Young
|
|
|
Give me a call when you are 30 minutes away and I will meet you out there. Thanks! Phone #: ###-#### Inspection requested via web by James Jackson// ok to insulate
|
BLD-Framing/Rough-in | 12/17/2018 | 12/17/2018 | 12/17/2018 | A | DEFR |
Brandon Shaw
|
|
|
Not ready
|
BLD-Wall Bracing | 11/18/2018 | 11/19/2018 | 11/19/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Conference | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | DONE |
Dave Hannah
|
|
|
Gene Phone #: ###-####
|
BLD-Wall Bracing | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PART |
Jim Sly
|
|
|
Willy Phone #: ###-#### Foundation wall.....OK.
|
BLD-Footing | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Inspection Record Card- Bld | | | 9/28/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/28/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 9/19/2018 | | 9/21/2018 | | DONE |
Michael Hanson
|
|
|
09/25 sfd L1 ePlan. 1st review completed - Energy and structural deficiences. MDH
|
Routing - PLAN CHECK | 9/21/2018 | | 9/21/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/21/2018 | | DONE |
|
|
|
Need- met
GC Form
|
1st review completed | | | 9/20/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and structural deficiences. MDH
|
Routing - PLAN CHECK | 9/11/2018 | | 9/20/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and structural deficiences. MDH
|
Plan assigned to (BJM) | 9/11/2018 | 9/11/2018 | 9/19/2018 | | DEFR |
Brian McGowan
|
|
|
09/25 sfd L1 ePlan
|
Routing - PLANNING | 9/11/2018 | | 9/13/2018 | | PASS |
Brent Moore
|
|
|
|
Route to Impact Fee Review | 9/11/2018 | 9/14/2018 | 9/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/11/2018 | | 9/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/11/2018 | | 9/11/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 9/11/2018 | | 9/11/2018 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/11/2018 | | PASS |
|
|
|
|
Application received | | | 5/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2018 9:20AM
|
Intake Approval | | | 5/24/2018 | | FAIL |
|
|
|
See checklist items and wait to submit for new single family residence until the new parcels and addresses have been assigned to lots from lot split.
Demo of current house will need to be finsihed before issuing new SF house.
|
Telephone call | | | 5/24/2018 | | DONE |
|
|
|
Spoke with Deirdra and BJM. Shear wall and foundation/footings plan details are shown on plans.
|