BLD-Blower Door Test Results | 5/14/2019 | 5/21/2019 | 5/22/2019 | P | DONE |
Tony Young
|
|
|
Jeanette Phone #: ###-####,, 6.60
|
DOC - Permit Finaled | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PEND |
Tony Young
|
|
|
Jeanette Phone #: ###-####,, will text the report
|
BLD-Final | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | PART |
Tony Young
|
|
|
Jeanette Phone #: ###-####,, all ok except for the blower door test results
|
BLD-Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | P | CANC |
Tony Young
|
|
|
Jannett Phone #: ###-####
|
BLD-Energy code compliance | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | PASS |
Tony Young
|
|
|
Jeantte Phone #: ###-####
|
BLD-Framing/Rough-in | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Tony Young
|
|
|
Jeanette Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 2/8/2019 | 2/8/2019 | 2/8/2019 | P | FAIL |
Tony Young
|
|
|
Janette Phone #: ###-####,, c/n posted,, need truss fix per engineering,, need hangers nailed,, need hanger,, strap plate/beam,, fix shed roof per normal frame practices at hvac pop out,, fireblock stairs,, needs mech permit and inspection for the fireplace of justify, do not insulate
|
BLD-Wall Bracing | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PART |
Tony Young
|
|
|
call for acess- Jenatte Phone #: ###-####,, exterior ok
|
BLD-Wall Bracing | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | NR |
Brandon Shaw
|
|
|
|
BLD-Footing | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Tony Young
|
|
|
vali Phone #: ###-####
|
OVERRIDE | | | 11/9/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/9/2018 | 11/9/2018 | 11/9/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/9/2018 | | 11/9/2018 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 11/9/2018 | | 11/9/2018 | | PASS |
Leon Letson
|
|
|
|
Override - Parcel Holds | | | 11/9/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
per plan reviewer no plan mod fees-only took a couple minutes
|
Telephone call | | | 11/9/2018 | | DONE |
|
|
|
called Jeanette to let know permit is ready again after plan mod and no fees were assessed for plan mod
|
Override - Parcel Holds | | | 11/9/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/9/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/9/2018 | | DONE |
|
|
|
Resubmittals submitted after permit was ready-changes to sheet A1-took to Brian McGowan
|
OVERRIDE | | | 11/8/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 6/20/2018 | 6/20/2018 | 11/8/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete - 7-3 sfd L1 paper- Must pass Planning! Need SUEZ Fireflow and email confirming sprinklers.
|
Inspection Record Card- Bld | | | 11/8/2018 | | DONE |
|
|
|
|
Telephone call | | | 11/8/2018 | | DONE |
|
|
|
Called Jeanette to advise permit is ready to issue and gave fees due
|
Case Summary (BLD) | | | 11/8/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2018 | | DONE |
Brian McGowan
|
|
|
|
Override - Parcel Holds | | | 11/8/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 11/8/2018 | | DONE |
|
|
|
Per fire marshall no sprinkler system required see notes in fire plan review-plans were ready and put in drawer but they turned in a resubmittal so took out of the drawer and took to Brian McGowan with resubmittals
|
Plan Reviewer's activity | | | 11/7/2018 | | |
Brian McGowan
|
|
|
Leon provided the filed paper work for vacating the easement.
|
Routing - FIRE | 10/5/2018 | 10/5/2018 | 10/5/2018 | | PASS |
Tim Frost
|
|
|
The assitant fire marshal has indicated this house does not need to have sprinklers due to access distance. The driveway is rated for 75000# and is 20' wide.
|
Routing - FIRE | 9/26/2018 | 9/26/2018 | 9/26/2018 | | FAIL |
Tim Frost
|
|
|
Did not address previous comments.
|
Plan Reviewer's activity | | | 9/26/2018 | | DONE |
Brian McGowan
|
|
|
Spoke with Jeanette about the easement and fire sprinklers. She requested an early foundation start but we are unable to do so because the easement issue is not settled.
|
Routing - MECHANICAL | | | 8/14/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/10/2018 | | 8/10/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 8/10/2018 | | DONE |
Brian McGowan
|
|
|
|
Plan resubmittals received | | | 7/26/2018 | | DONE |
|
|
|
Resubmittals recieved 2 of each-wall bracing, tall wall calcs, a0, A1, A2, A3, A4, A4.1, A5, A5.1, A5.2, A6, A7 AND TOOK TO Brain MacGowan-the plans that were made ready and put in the drawer are now with Brian while he does the resubmittal
|
Routing - FIRE | 7/3/2018 | 6/20/2018 | 7/5/2018 | | FAIL |
Tim Frost
|
|
|
7/09 New SFH paper
Fire sprinklers required due to access distance (Flag Lot)
|
Routing - PLAN CHECK | | | 7/3/2018 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 7/3/2018 | | FAIL |
Brian McGowan
|
|
|
CANNOT ACCEPT "BEAMS BY OTHERS".
|
Routing - PLANNING | 6/21/2018 | | 6/22/2018 | | FAIL |
Leon Letson
|
|
|
10' utility and access easement must be vacated prior to issuing permit.
Fire sprinklers required.
|
Route to Impact Fee Review | 6/20/2018 | 6/23/2018 | 6/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 6/20/2018 | | 6/21/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 6/20/2018 | | 6/20/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2018 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 6/20/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2018 | | DONE |
|
|
|
|
Application received | | 6/20/2018 | | | |
|
|
|
|