Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD18-02746
StatusIssued
Name BREON KEITH F
Site Address 1812 N 10TH ST
Project NameBreon basement
Customer Number 
ePlanReviewNo
Description
MODIFICATION - BASEMENT WALLS TO BE REPLACED WITH ICFs 6-17-19 **jab** Permit to add a 1,112sq' basement under an existing home. Basement adds 3 bedrooms, 2 bathrooms, & a family room. All work per plans, attachments, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection5/7/20205/7/20205/14/2020 PEND
DetailsTony Young
BLD-Aging Inspection5/6/20205/6/20205/7/2020 PEND
DetailsTony Young
Routing Walk-In (BLD)3/13/20203/13/20203/13/2020APASS
DetailsJosh Bogle
disdussed a possible plan modification
Meeting  3/13/2020 DONE
Permit Transfer from Levco to Keith Breon who will be the GC from now on. Parcel Owner now GC see email in docs
Telephone call  3/10/2020 DONE
Spoke with Parcel Owner: Keith. Will be ending working relationship with Levco Builders. Need letter, 302 form (exemption) , and to primary as RP on ESC permit. Will come in for a Plan Modification as a door was added that was not originally on the approved plans.
BLD-Footing12/20/201912/23/201912/24/2019APASS
DetailsDave Hannah
Pablo Phone #: ###-#### walls ok
BLD-Footing12/17/201912/18/201912/18/2019APART
DetailsTony Young
Scott Phone #: ###-####,, north side tier footing on window well,, work in progress,, ok
BLD-Foundation12/6/201912/6/201912/6/2019PPART
DetailsTony Young
rebar // Scott Phone #: ###-#### or Nick ###-#### (on site),, work in progress on 3 window well walls
BLD-Footing12/3/201912/3/201912/3/2019PPART
DetailsTony Young
rebar- Gabe Phone #: ###-####,, window well footings,, work in progress
BLD-Energy code compliance10/17/201910/18/201910/18/2019APASS
DetailsTell Riley
JOSH Phone #: ###-####
BLD-Framing/Rough-in10/14/201910/15/201910/15/2019APASS
DetailsTony Young
Josh Phone #: ###-####,, ok to insulate
BLD-Wall Bracing10/14/201910/14/201910/14/2019PPASS
DetailsTony Young
shear // Josh Phone #: ###-####
BLD-Other10/14/201910/14/201910/14/2019PPART
DetailsTony Young
culking // Josh Phone #: ###-####,, seal package ok
BLD-Wall Bracing10/4/201910/8/201910/8/2019APASS
DetailsTony Young
Josh Phone #: ###-####
CHANGE STATUS TO (ISS)  10/4/2019 DONE
Per Brandon S, didnt mean to final permit yet.
BLD-Framing/Rough-in9/3/20199/4/20199/4/2019APASS
DetailsBrandon Shaw
Josh Phone #: ###-####
DOC - Permit Finaled9/4/20199/4/20199/4/2019PPASS
DetailsBrandon Shaw
BLD-Foundation6/26/20196/28/20196/28/2019APART
DetailsTony Young
Jack Phone #: ###-####,, porch walls ok,, work in progress, ok
BLD-Footing6/26/20196/27/20196/27/2019APASS
DetailsBrandon Shaw
Work in progress...
Front porch...
BLD-Foundation6/21/20196/24/20196/24/2019APASS
DetailsTony Young
Chet Phone #: ###-####
BLD-Foundation6/20/20196/21/20196/21/2019PPART
DetailsTony Young
Chet Phone #: ###-####,, work in progress,, monolithic basement walls,, ICF
OVERRIDE  6/17/2019  
Routing Walk-In (BLD)6/17/20196/17/20196/17/2019PDONE
DetailsJosh Bogle
Plan assigned to (JAB) Josh6/17/20196/17/20196/17/2019 PASS
DetailsJosh Bogle
Routing - PLAN CHECK6/17/2019 6/17/2019 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  6/17/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  6/17/2019 DONE
DetailsJosh Bogle
Permit Ready to Issue  6/17/2019 DONE
plan mod approved
CHANGE STATUS TO (ISS)  6/17/2019 DONE
Plan Modification Accepted  6/17/2019 DONE
Changing the floorplan/foundain
Routing Walk-In (BLD)6/14/20196/14/20196/14/2019PFAIL
DetailsJosh Bogle
moving to ICF foundation - lacked information
BLD-Aging Inspection4/26/20194/26/20194/30/2019 PEND
DetailsTony Young
BLD-Aging Inspection4/25/20194/25/20194/30/2019 PEND
DetailsTony Young
BLD-Foundation12/11/201812/12/201812/12/2018APASS
DetailsTony Young
Gali Phone #: ###-####,, stairwell walls
BLD-Footing12/6/201812/6/201812/6/2018PPART
DetailsTony Young
Jorge Phone #: ###-####,, stairwell /retaining wall footing ok,, will pour and tent and heat,, work in progress
BLD-Conference11/13/201811/15/201811/15/2018PPART
DetailsTony Young
early as poss in PM // call when on way to meet // Josh Mitchell Phone #: ###-####,, exterior stair ?s,, retaining wall ?s,, need to follow engineering
OVERRIDE  9/18/2018  
Routing Walk-In (BLD)9/18/20189/18/20189/18/2018PDONE
DetailsJosh Bogle
Plan assigned to (JAB) Josh8/2/20188/2/20189/18/2018 PASS
DetailsJosh Bogle
08/06 basement addition, paper- 1st done, see e-mail 8/6
Routing - PLAN CHECK9/18/2018 9/18/2018 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  9/18/2018 DONE
DetailsJosh Bogle
Case Summary (BLD)  9/18/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  9/18/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  9/18/2018 DONE
Issue PAID IN FULL permit  9/18/2018 DONE
Routing - PLAN CHECK9/14/2018 9/14/2018 FAIL
DetailsJosh Bogle
see e-mail - 9/14/18
Plan resubmittals received  9/11/2018 DONE
Received one copy of retaining wall calculations, foam insulation specs, and foundation detail on 11x17; taken to Josh B.
Plan resubmittals received  8/31/2018 DONE
One copy of Forte Report (3 pages) and one copy of full new set of plans pages 1 to 8. Taken to Josh
Routing - PLAN CHECK8/6/2018 8/6/2018 FAIL
DetailsJosh Bogle
1st review completed  8/6/2018 FAIL
DetailsJosh Bogle
Routing Walk-In (Zoning)7/31/20187/31/20187/31/2018PPASS
DetailsKayCee Babb
Routing Walk-In (BLD)7/31/20187/31/20187/31/2018PPASS
DetailsJosh Bogle
took in as level 2 (lobby busy)
Application received 7/31/2018