Permit Information
Permit NumberBLD18-03174
StatusFinaled
Name SHOEBRIDEGE BRADLEY P LIFE ESTATE
Site Address 7732 W LEMHI ST
Project NameGolden Oaks Design
Customer Number 
ePlanReviewYes
Description
(GOLDEN OAKS DESIGN) Permit is for the tenant to occupy the remaining 4,000 sq. ft. area of the building as a millwork fabrication shop and accessory office space. The tenant currently occupies the southern half (4,000 sq. ft.) of the building under a certificate of occupancy issued by Ada County (Permit #9300752). This C of O is still valid and NO plan review of the existing space is required. An accessible restroom is being provided/upgraded, but no additional work is proposed under this permit. This building is fully fire sprinklered any alterations or modifications to the sprinkler system will require a separate permit and shall be installed per NFPA #13 as regulated by the fire department. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 3/3/20193/11/2019 DONE
mailed 3-12
Permanent Occupancy  2/21/2019 DONE
BLD-Final2/11/20192/13/20192/13/2019APASS
DetailsMike Jordan
Call 15 minutes ahead // Jeff Phone #: ###-####. OK for perm occ. Exterior buildings have been removed.
FIRE-Final Inspection2/11/20192/12/20192/12/2019APASS
DetailsTroy Cobbley

Life safety passed. Previous corrections made. Per notes Troy James verified dust collection. The racks have been removed and there is no paint booth within the scope of work.


Call 15 minutes ahead // Jeff Phone #: ###-####
Inspection Record Card- Bld  2/11/2019  
Routing - PLAN CHECK1/3/2019 1/4/2019 PASS
DetailsJoe Bruce
Permit Ready to Issue  1/4/2019 DONE
Plan Mod Approved (fees due)
DO NOT REISSUE
CHANGE STATUS TO (ISS)  1/4/2019 DONE
plan mod
Plan assigned to (JHB)12/19/2018 1/4/2019 PASS
DetailsJoe Bruce
*(Plan Mod Comp) 12/28 - Golden Oaks Plan Modification
Plan resubmittals received  1/2/2019 DONE
DetailsJoe Bruce
Plan resubmittals requested  12/27/2018 DONE
Routing - PLAN CHECK12/26/2018 12/27/2018 FAIL
DetailsJoe Bruce
Emailed architect additional information required for shed on west side of building. **JHB**
Routing - FIRE12/21/201812/24/201812/24/2018 PASS
DetailsErika Akin
Plan mod to demo lean to's and address existing lean to that remains on west side. A fire sprinkler permit will be required for compliance.
Plan Modification Accepted  12/19/2018 DONE
Existing Building was updated to meet code and inspector comments.
BLD-Conference12/6/201812/7/201812/7/2018ADONE
DetailsMike Jordan
Brad Phone #: ###-####.. Due to change in use the ADA restrooms are required to be upgraded. Needs to pull building permits for the shelters on the west side of the exisitng building and resolve all fire/life/safety issues and electrical issues.
BLD-Final12/4/201812/7/201812/7/2018ACANC
DetailsMike Jordan
Brad Phone #: ###-####
FIRE-Final Inspection12/4/201812/6/201812/6/2018AFAIL
DetailsTroy Cobbley
Provide revised floor plan showing the actual wall layout and that door 106 is not there , provide exit signs/emergency lights as per the plans and review comments or get revised plans, remove dead bolt from west side door and provide single action hardware for the restroom door, provide fire sprinkler coverage for the lean too's/sheds that are attatched to the building, provide racking permit for the storage racks that exceed 8'

Brad Phone #: ###-####
Routing - FIRE11/28/201811/28/201812/4/2018 PASS
DetailsErika Akin
Attached comments to case
Plan assigned to (JHB)9/5/20189/5/201812/4/2018 PASS
DetailsJoe Bruce
*(3rd Rev Comp) 09/27 (L3) Golden Oaks Design L-3 (Fire, Mech)
PLANS/APPL TAKEN TO FRONT DESK  12/4/2018 DONE
Permit Ready to Issue  12/4/2018 DONE
MET
Need
ACHD
GC Form
Revised Cert of Value
Issue PAID IN FULL permit  12/4/2018 DONE
Print Occupancy Form  12/4/2018 DONE
Routing - MECHANICAL11/28/2018 11/28/2018 PASS
DetailsTroy James
Plan resubmittals received  11/28/2018 DONE
DetailsJoe Bruce
Troy James performed a site visit on 11/27/18 and verified dust collection system for each tool. **JHB**
Routing - MECHANICAL11/7/2018 11/7/2018 FAIL
DetailsTroy James
Onsite meeting with owner and architect on the 27th of Nov.
Plan resubmittals requested  11/2/2018 FAIL
DetailsJoe Bruce
Routing - FIRE10/19/201810/19/201811/1/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - MECHANICAL10/30/2018 10/31/2018 FAIL
DetailsTroy James
Dust Collection System for cabinet/millwork shop. **JHB**
Routing - PLAN CHECK10/19/2018 10/24/2018 PASS
DetailsJoe Bruce
Plan resubmittals received  10/19/2018 DONE
DetailsJoe Bruce
Plan resubmittals requested  10/15/2018 DONE
DetailsJoe Bruce
Emailed Plan Review Reports to architect. **JHB**
Routing - PLAN CHECK10/3/2018 10/15/2018 FAIL
DetailsJoe Bruce
Routing - FIRE10/3/201810/3/201810/11/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PUBLIC WORKS10/11/2018 10/11/2018 PASS
DetailsMorgan Webb
Plan resubmittals received  10/3/2018 DONE
DetailsJoe Bruce
Added required plumbing fixtures. **JHB**
Route to Impact Fee Review10/1/201810/4/201810/1/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  10/1/2018 FAIL
DetailsJoe Bruce
Failed: Fire and Plan Check.
Plan resubmittals requested  10/1/2018 DONE
DetailsJoe Bruce
Plan Review Report sent to architect on 9/27. Spoke on the phone with architect about comments on 9/28.
Routing - FIRE9/5/20189/5/20189/28/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK9/5/2018 9/27/2018 FAIL
DetailsJoe Bruce
Emailed architect plan review report on 9/27. **JHB**
Routing - PLANNING9/5/2018 9/6/2018 PASS
DetailsNicolette Womack
Routing - Addressing9/5/2018 9/6/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/5/2018 9/6/2018 PASS
DetailsRachael Beierle
ON SPETIC. NO ROUTING TO RWC PER B_M.
Intake Approval  8/31/2018 FAIL
DetailsJoe Bruce
Spoke with architect on phone in regards to application. The application that was turned in noted a change to the occupancy from an S-1 to B. The tenant is listed as Golden Oaks Design, but no reference to what type of operations would take place in the building. **JHB**

1) Resubmit plans that describe the use of each space by the tenant (i.e. furniture manufacturing, storage, office, etc...)
2) Note any new work or demolition of existing walls on the plans.
3) If occupancy group is "B" - confirm that the use is allowed by Chapter 11 - Zoning Ordinance.
Intake Approval  8/31/2018 PASS
Application received  8/29/2018 DONE
Application submitted via PDS Online on Aug 29 2018 1:23PM