BLD-Aging Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | | PASS |
Jim Storey
|
|
|
|
Change Expiration Date Only | | | 7/14/2020 | | DONE |
|
|
|
|
BLD-Aging Inspection | 6/1/2020 | 6/1/2020 | 6/1/2020 | | PASS |
Jim Storey
|
|
|
|
Zoning Approval | 4/28/2020 | 4/28/2020 | 4/28/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Aging Inspection | 3/30/2020 | 3/30/2020 | 3/30/2020 | | PASS |
Jim Storey
|
|
|
|
Temporary Occupancy | 1/30/2020 | 4/29/2020 | 1/30/2020 | | DONE |
Gemma Flores
|
|
|
|
BLD-Final | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Jim Storey
|
|
|
I have fire life and safety also scheduled for the afternoon. Phone #: ###-#### Inspection requested via web by chad stradley final ok pending others
|
FIRE-Final Inspection | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed for Bldg #1/Club House.
Final inspection is also scheduled for today. We should be ready anytime. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Ceiling Grid Inspection | 1/23/2020 | 1/24/2020 | 1/24/2020 | P | PASS |
Jim Storey
|
|
|
ACT inspection at the clubhouse. Phone #: ###-#### Inspection requested via web by chad stradley ok pending ele
|
BLD-Framing/Rough-in | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PASS |
Jim Storey
|
|
|
exterior framing inspection Phone #: ###-#### Inspection requested via web by chad stradley c/n perviously table 602 not a issue.
|
BLD-Framing/Rough-in | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | FAIL |
Mike Jordan
|
|
|
Clubhouse framing. Phone #: ###-#### Inspection requested via web by chad stradley. Noted Type II construction. exterior OSB and wood siding does not meet criteria for type II construction.
|
BLD-Framing/Rough-in | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | CANC |
Tell Riley
|
|
|
clubhouse framing inspection. Phone #: ###-#### >> Inspection requested via web by chad stradley Inspection cancelled from web by: chad stradley
|
BLD-Framing/Rough-in | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PART |
Dave Hannah
|
|
|
Cody Phone #: ###-#### bldg 1a south end ok to insulate
|
Zoning Approval Temp | 10/18/2019 | 10/18/2019 | 10/18/2019 | | DONE |
Katelyn Menuge
|
|
|
BND19-00190
|
BLD-Footing | 8/14/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Brandon Shaw
|
|
|
rebar inspection for rest of building 1A. Work in progress...
|
BLD-Footing | 8/12/2019 | 8/13/2019 | 8/13/2019 | P | PART |
Tell Riley
|
|
|
rebar inspection for clubhouse. would like to have inspection done at 2pm they would like to pour at 2:30 PM Phone #: ###-#### Inspection requested via web by chad stradley//club house footings ok per plans//pending special inspections//rebar installed per plans//
|
BLD-Footing | 8/9/2019 | 8/12/2019 | 8/12/2019 | P | CANC |
Jim Storey
|
|
|
rebar inspection for footer at clubhouse. We want to pour at 230 if we could get inspection at 2 pm that would be great. Phone #: ###-#### >> Inspection requested via web by chad stradley Inspection cancelled from web by: chad stradley
|
BLD-Footing | 8/8/2019 | 8/9/2019 | 8/8/2019 | P | CANC |
Jim Storey
|
|
|
Rebar inspection for footer Phone #: ###-#### >> Inspection requested via web by chad stradley Inspection cancelled from web by: chad stradley
|
Change Expiration Date Only | | | 7/17/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Print Occupancy Form | | | 7/16/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/15/2019 | | DONE |
|
|
|
DO NOT REISSUE - PLAN MOD
|
Plan assigned to (JHB) | 6/13/2019 | 6/13/2019 | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
(plan mod) Falcon One, Bldg 1A
|
Routing Off Site - STRUCTURAL | 7/11/2019 | | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 7/11/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 7/8/2019 | | DONE |
Joe Bruce
|
|
|
Emailed structural comments to architect.
|
Routing - PLAN CHECK | 6/19/2019 | | 7/8/2019 | | PASS |
Joe Bruce
|
|
|
Received revised foundation drawings showing office foundation.
|
Routing Off Site - STRUCTURAL | 6/21/2019 | | 7/3/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan Modification Accepted | | | 6/13/2019 | | DONE |
|
|
|
Plan mod accepted in e plan-changing footing & framing design -assigned to Joe B
|
Meeting | | | 3/22/2019 | | DONE |
|
|
|
Plan mod started in e plan-changing buildings design including footing and framing design for building 7, 8A & 8B - sheets-permit numbers BLD18-04075 BLD18-04076 & BLD19-00317. 3 plan mod apps uploaded in e plan for review-assigned to Joe B
|
Telephone call | | | 3/21/2019 | | DONE |
|
|
|
plan mod request came in but they need to resubmitt using 1 plan mod app for each permit-emailed Matt back letting him know
|
Issue PAID IN FULL permit | | | 2/13/2019 | | |
|
|
|
|
Print Occupancy Form | | | 2/13/2019 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 2/13/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Permit Ready to Issue | | | 2/12/2019 | | DONE |
|
|
|
met
Revised Value- (for each building)
(DO NOT ISSUE WITHOUT ALL PERMITS, BLD18-03877, BLD18-04070 TO BLD18-04076, BLD19-00314 TO BLD19-000317)
All met -
Need GC
Need ACHD
|
Plan assigned to (JHB) | 11/14/2018 | 11/14/2018 | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
(3rd Rev Comp) 12/07 - (502) Falcon One Storage Condos Bldg 1(A) (Struc, Sewer)
|
Routing Off Site - STRUCTURAL | 2/8/2019 | | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/8/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
Structural resubmittal required.
|
Routing Off Site - STRUCTURAL | 1/30/2019 | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
See structural comment in the Agency Comments folder for remaining issue to address. Provide a complete written response outlining the analysis method you are taking responsibility for.
|
Routing PW Sewer Design | 1/30/2019 | | 1/30/2019 | | PASS |
DeAnn Brown
|
|
|
|
Plan resubmittals requested | | | 1/30/2019 | | FAIL |
Joe Bruce
|
|
|
PW Sewer and Structutral have additional comments. **JHB**
|
Plan resubmittals received | | | 1/30/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 1/17/2019 | 1/17/2019 | 1/29/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 1/17/2019 | | 1/28/2019 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing - PLAN CHECK | 1/17/2019 | | 1/28/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Sewer Design | 1/17/2019 | | 1/23/2019 | | FAIL |
DeAnn Brown
|
|
|
Sewer service plan alteration is not allowed per the IDEQ and Plumbing Bureau MOU. Please review changemarks and revise.
|
Routing - Design Review | 1/17/2019 | | 1/18/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Plan resubmittals received | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan Reviewer's activity | | | 1/16/2019 | | DONE |
Joe Bruce
|
|
|
Had applicant upload corrected resubmittal drawings with architect stamp, city approval stamp area, and remove NOT FOR PERMIT language from drawings. **JHB**
|
Plan Reviewer's activity | | | 1/15/2019 | | FAIL |
Joe Bruce
|
|
|
The resubmittal is being returned for the following reasons:
1) Provide a stamped, signed and dated by the Idaho licensed architect all plan sheets and remove the “NOT FOR PERMIT” statement.
2) Uploaded sheets shall have the same filename in order to overwrite the prior sheets. Several plan sheets are not named correctly and need to be revised.
3) Sheets that have been resubmitted are missing the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
|
Plan resubmittals received | | | 1/15/2019 | | FAIL |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 12/12/2018 | 12/15/2018 | 12/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/14/2018 | 11/14/2018 | 12/12/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 12/12/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/12/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 11/14/2018 | | 12/7/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 11/14/2018 | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ - Dave Haugland
|
Routing - MECHANICAL | 11/14/2018 | | 11/26/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing PW Drainage | 11/14/2018 | | 11/20/2018 | | PASS |
Brian Murphy
|
|
|
plan mod
|
Routing - PLUMBING | 11/14/2018 | | 11/19/2018 | | PASS |
Dan Ediger
|
|
|
Per ISPC and Plans. See notes
|
Routing - Design Review | 11/14/2018 | | 11/16/2018 | | FAIL |
Katelyn Menuge
|
|
|
See Changemarks
|
Routing - PLANNING | 11/14/2018 | | 11/15/2018 | | PASS |
Leon Letson
|
|
|
Storage is an allowed use in the M-1D zone.
|
Routing PW Street Lights | 11/14/2018 | | 11/15/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 11/14/2018 | | 11/15/2018 | | FAIL |
DeAnn Brown
|
|
|
Please add tap permit language described in changemarks.
|
Routing PW Solid Waste | 11/14/2018 | | 11/14/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 11/14/2018 | | 11/14/2018 | | PASS |
Doug Chausow
|
|
|
Facility address: 2140 E Summerset Dr
|
Routing - PUBLIC WORKS | 11/14/2018 | | 11/14/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 11/14/2018 | | 11/14/2018 | | CANC |
Andy J. Long
|
|
|
No review required, ESC permit for project already issued, see ESC18-01289. This permit VOID
|
Telephone call | | | 11/7/2018 | | DONE |
|
|
|
emailed Matt (mmcanulty@neudesignarch.com) that all 8 permits are in and that he can go pay the fees for all 8
|
Intake Approval | | | 11/7/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/30/2018 | | FAIL |
Javier Guzman
|
|
|
Previous request not addressed Provide and upload the following:
• Provide an Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
|
Intake Approval | | | 10/25/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Provide and upload an application for each of the buildings with information corresponding to each of those building such as square footage, value, etc... on the application (the current uploaded application you will need to revise to correspond to one of these individual buildings) we will then in-house crate a building permit for each of the buildings.
• Provide a completed #304 form
• Provide a Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
• Provide a Site specific fire flow at hydrants letter from Suez Water
• Provide a completed Form #310 – Statement of Special Inspections must be completed by the design engineer
• Provide a Shallow Injection Well Inventory form Drainage plans with seepage beds must submit a “Shallow Injection Well Inventory” form from the Idaho Department of Water Resources available at: http://www.idwr.idaho.gov/wells/shallow-injection-wells.html
• Provide a Drainage System Operation & Maintenance Plan stamped and signed by Idaho licensed design professional
• Mark “yes” on the checklist that you have mailed the Permanent Operation & Maintenance Agreement form or dropped off the original signed and notarized document from the landowner to the Public Works Drainage Coordinator.
• Provide an Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
• Provide a stamped, signed and dated by the Idaho licensed architect all plan sheets with four digit numbers behind the letter “A” (A####) and remove the “NOT FOR PERMIT” statement
• On checklist list the sheet number where to find the door schedule, door hardware, window schedule.
• Provide building envelope Comcheck for the clubhouse
|
Application received | | | 10/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2018 2:57PM
|