Permit Information
Permit NumberBLD18-04014
StatusFinaled
Name RUSS MCCREA BUILDERS
Site Address 802 W BANNOCK ST
Project NameHoff Building 8 Floor TI
Customer Number 
ePlanReviewYes
Description
(TANGO CARD) 02/8/19 PLAN MOD - NEW WORK TO REFLECT EXISTING STORAGE ROOM CLOSET WITHIN THE TENANT SPACE NOT ORIGINALLY SHOWN ON PLANS. **JHB** Permit is for an office space remodel and restroom remodel of the 8th floor of the existing historic building. Work to include: remodeled accessible restrooms, new plumbing fixtures, new interior non-bearing walls, and new interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is fully fire sprinklered because it is a high-rise building and any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. The work is required to comply with the approved drawings and all applicable codes. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/20/20195/6/2019 DONE
mailed 5-10-19
Second Notice 3/21/20194/15/2019 DONE
mailed 4-16-19
First Notice 2/23/20193/11/2019 DONE
mailed 3-12
Permanent Occupancy  2/13/2019 DONE
BLD-Final2/11/20192/12/20192/12/2019PPASS
DetailsDave Hannah
Mccrea Phone #: ###-####
FIRE-Final Inspection2/12/20192/12/20192/12/2019PPASS
DetailsJim Page
Final life fire safety inspection for area of work complete.

CHANGE STATUS TO (ISS)  2/11/2019 DONE
Inspection Record Card- Bld  2/11/2019  
Plan assigned to (JHB)2/1/20192/1/20192/8/2019 PASS
DetailsJoe Bruce
02/08 (Plan MOD) Tango Card, ePlan
Routing - PLAN CHECK2/6/2019 2/8/2019 PASS
DetailsJoe Bruce
PLANS/APPL TAKEN TO FRONT DESK  2/8/2019 DONE
Permit Ready to Issue  2/8/2019 DONE
plan mod please do not re iss
Intake Approval  2/1/2019 FAIL
DetailsJoe Bruce
Plan Modfication prescreen: Provide room name/description on the plans for the room that remains under this plan modification.
Plan Modification Accepted  1/31/2019 DONE
There were two existin walls not shown on the plans. There will be no work to these walls, but they are now shown on the floor plans
FIRE-Final Inspection1/29/20191/30/20191/30/2019AFAIL
DetailsJim Page
Fire alarms did not pass inspection. Room has been added that is not on the site drawings, site drawings are not stamped, need city approved drawings for life fire safety inpspection.

Russ Phone #: ###-####
Telephone call  1/30/2019 DONE
left message for phillip to see was they are doing for plan mod
BLD-Wall Bracing12/26/201812/28/201812/31/2018APASS
DetailsDave Hannah
Russ Phone #: ###-#### ok to cover restrooms
BLD-Framing/Rough-in12/17/201812/18/201812/18/2018PPASS
DetailsDave Hannah
Russ Phone #: ###-####
FIRE-Conference12/5/201812/6/201812/6/2018ADONE
DetailsJim Page
Fire conference complete.

Russ Phone #: ###-####
Issue PAID IN FULL permit  11/28/2018 DONE
Print Occupancy Form  11/28/2018 DONE
Plan assigned to (JHB)11/8/201811/8/201811/23/2018 PASS
DetailsJoe Bruce
*(1st Rev Comp) - 11/13 L1 Hoff Building 8 Floor TI (Bldg)
Routing - PLAN CHECK11/23/2018 11/23/2018 PASS
DetailsJoe Bruce
PLANS/APPL TAKEN TO FRONT DESK  11/23/2018 DONE
Permit Ready to Issue  11/23/2018 DONE
all met - NEED
GC
Rev cert of val
Plan resubmittals received  11/16/2018 DONE
DetailsJoe Bruce
Route to Impact Fee Review11/15/201811/18/201811/15/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK11/8/2018 11/15/2018 FAIL
DetailsJoe Bruce
1st review completed  11/15/2018 FAIL
Plan resubmittals requested  11/15/2018 DONE
DetailsJoe Bruce
Routing - PLUMBING11/8/2018 11/9/2018 PASS
DetailsDan Ediger
Per plans and ISPC
Routing - Addressing11/8/2018 11/8/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS11/8/2018 11/8/2018 PASS
DetailsAngela Hardy
Intake Approval  11/7/2018 PASS
DetailsJavier Guzman
Application received  11/2/2018 DONE
Application submitted via PDS Online on Nov 2 2018 4:43PM