BLD-Final | 7/10/2019 | 7/11/2019 | 7/11/2019 | A | PASS |
Brandon Shaw
|
|
|
Bobby Phone #: ###-####
|
DOC - Permit Finaled | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/11/2019 | 7/11/2019 | 7/11/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.82
|
BLD-Final | 7/8/2019 | 7/9/2019 | 7/9/2019 | A | FAIL |
Brandon Shaw
|
|
|
Post blower door test results...
|
BLD-Energy code compliance | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Jim Storey
|
|
|
Bobby Phone #: ###-####
|
BLD-Other | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Jim Storey
|
|
|
fire rated soffit // Bobby Phone #: ###-####
|
BLD-Energy code compliance | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | FAIL |
Jim Storey
|
|
|
Bobby Phone #: ###-#### no depth indcator/ no access back bed rm.
|
BLD-Energy code compliance | 4/9/2019 | 4/10/2019 | 4/10/2019 | P | NR |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Framing/Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Wall Bracing | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/21/2019 | 2/22/2019 | 2/22/2019 | P | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/20/2019 | 2/20/2019 | 2/20/2019 | P | CANC |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | NR |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | CANC |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/19/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 12/14/2018 | 12/14/2018 | 12/19/2018 | | DONE |
Jenny Nelson
|
|
|
12/27 sfd L1 ePlan. 1st review, beam doesn't match structural calculations
|
Routing - PLAN CHECK | 12/19/2018 | | 12/19/2018 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/19/2018 | | DONE |
|
|
|
met
|
Routing - Addressing | 12/14/2018 | | 12/18/2018 | | PASS |
Laura Hunter
|
|
|
|
1st review completed | | | 12/18/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 12/14/2018 | | 12/18/2018 | | FAIL |
Jenny Nelson
|
|
|
Beam doesn't match structural calculations
|
Route to Impact Fee Review | 12/14/2018 | 12/17/2018 | 12/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 12/14/2018 | | 12/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/14/2018 | | 12/17/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 12/14/2018 | | 12/17/2018 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 12/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 14 2018 3:22PM
|
Plans ACCEPTED BY PLAN TECH | | | 12/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/14/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/14/2018 | | DONE |
|
|
|
|