Zoning Approval Temp | 8/13/2020 | 8/13/2020 | 8/13/2020 | | DONE |
Cody Riddle
|
|
|
Inspected the site on 8/12/2020. Temporary occupancy to allow parents and staff to conduct computer pick-up activities okay. Paved, accessible routes to, from, and around site, in place.
|
BLD-Final | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PART |
Tony Young
|
|
|
Phase 2 TCO. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// 2nd phase ok for temp occupancy
|
FIRE-Final Inspection | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PART |
Jim Page
|
|
|
Life fire safety inspection for TCO phase 2 complete, exit signs that were noted missing have been placed.
Phase 2 TCO. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Final | 8/5/2020 | 8/6/2020 | 8/6/2020 | A | PART |
Tony Young
|
|
|
Building Re-inspection. Access through South gate. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// temp occupancy ok
|
PubWorks Temp Occupancy Appr | 8/6/2020 | 8/6/2020 | 8/6/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Temporary Occupancy | 7/21/2020 | 10/19/2020 | 7/21/2020 | | DONE |
Gemma Flores
|
|
|
|
BLD-Final | 7/17/2020 | 7/20/2020 | 7/20/2020 | P | PART |
Jim Storey
|
|
|
TCO Phone #: ###-#### Inspection requested via web by Chris Fuhrman handrail returns/ missing exit signs/ need smoke seal on fire door/ occ load signage/ temp occ
|
FIRE-Final Inspection | 7/17/2020 | 7/20/2020 | 7/20/2020 | A | PART |
Jim Page
|
|
|
Life fire safety inspection for TCO phase 1 complete.
TCO Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
FIRE-Final Inspection | 4/7/2020 | 4/7/2020 | 4/7/2020 | A | PART |
Jim Page
|
|
|
Fire sprinkler riser monitoring has been tested and complete, storage of furntiure in building is authorized. After this entry fire sprinklers are to remain active and monitored (Allowed to be put on test during normal working hours, fire sprinkler monitoring must be taken off of test at the end of the business day, if monitoring is not active then furntiure storage will be revoked).
|
BLD-Ceiling Grid Inspection | 4/2/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Dave Hannah
|
|
|
library, cafeteria ; music Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Ceiling Grid Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Jim Storey
|
|
|
no wires need at pirimtor admin and hallway ok to cover.
|
BLD-Ceiling Grid Inspection | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PART |
Jim Storey
|
|
|
1B Administration Area Phone #: ###-#### Inspection requested via web by Chris Fuhrman main wirers ok pending sica listing to not need perimitor wirers.
|
FIRE-Conference | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | DONE |
Jim Page
|
|
|
Fire conferene complete.
Review new BSD occupancy and phasing schedule and requirements. Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Framing/Rough-in | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PART |
Tony Young
|
|
|
Area C Gyp Ceilings Phone #: ###-#### Inspection requested via web by Chris Fuhrman.. ok pending trades
|
BLD-Ceiling Grid Inspection | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PART |
Tony Young
|
|
|
2B Classrooms Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, ok pending trades
|
BLD-Ceiling Grid Inspection | 2/12/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Tony Young
|
|
|
Grid Ceiling 2A Phone #: ###-#### Inspection requested via web by Chris Fuhrman// work in progress,, ok
|
BLD-Framing/Rough-in | 2/12/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Tony Young
|
|
|
Hard Ceiling Area 2B and Cafe Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Ceiling Grid Inspection | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Dave Hannah
|
|
|
1A Phone #: ###-#### Inspection requested via web by Chris Fuhrman see plans for locations
|
BLD-Framing/Rough-in | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Dave Hannah
|
|
|
Hard Ceilings 1B Phone #: ###-#### Inspection requested via web by Chris Fuhrman see plans for locations
|
BLD-Framing/Rough-in | 1/7/2020 | 1/7/2020 | 1/7/2020 | A | PART |
Tony Young
|
|
|
Gypsum Ceilings 1A - 2A Phone #: ###-#### Inspection requested via web by Chris Fuhrman// ok pending trades
|
BLD-Framing/Rough-in | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PART |
Tony Young
|
|
|
1B Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// ok to start covering pending trades
|
FIRE-Conference | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete, discussed items required for life fire safety for phase 1 occupancy.
Review phase 1 occupancy / egress plan. Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
FIRE-Conference | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | CANC |
Jim Page
|
|
|
Tried calling point of contact listed 2 times over a 15 minute time period, first time went right to voicemail but no message could be left because mailbox was full. 2nd call phone rang through, still went to voicemail but could not leave a message. procceeded to next inspection, conference will need to be rescheduled. This conference is cancelled.
Review phase 1 turnover plan. Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Wall cover | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PART |
Tony Young
|
|
|
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// area A1 and A2 ok to cover
|
BLD-Energy code compliance | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Tony Young
|
|
|
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, exterior insulation wrap ok
|
BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PART |
Tony Young
|
|
|
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, area 1a walk through
|
BLD-Wall Bracing | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PART |
Tony Young
|
|
|
SHEAR // Terry Phone #: ###-####.. areas marked on the plans
|
BLD-Framing/Rough-in | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | PART |
Tony Young
|
|
|
Terry Phone #: ###-####,, area A-1 interior ok pending trades,, B-1 interior ok pending trades,, B-1 exterior shear work in progress,, ok to cover when ready
|
BLD-Wall Bracing | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | DEFR |
Tony Young
|
|
|
Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Wall Bracing | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PART |
Dave Hannah
|
|
|
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman area a ok
|
BLD-Conference | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PART |
Tony Young
|
|
|
Review upcoming framing inspections and egress phasing plan for new school Phone #: ###-#### Inspection requested via web by Chris Fuhrman/// walk through.. will need fire/ l/ s on egress issues 1st,, ok to start sheeting exterior on south walls
|
BLD-Conference | 10/8/2019 | 10/9/2019 | 10/9/2019 | P | DEFR |
Tony Young
|
|
|
Review upcoming framing inspections and egress phasing plan for new school Phone #: ###-#### Inspection requested via web by Chris Fuhrman// called and left a voicemail,, out of time
|
BLD-Energy code compliance | 7/17/2019 | 7/18/2019 | 7/18/2019 | A | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### insulated cmu units
|
Override - Condition Holds | 7/17/2019 | 1/1/1900 | 7/17/2019 | | |
|
|
|
This is a energy inspection, hold is for street light
|
BLD-Foundation | 7/1/2019 | 7/1/2019 | 7/2/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, special inspector on site.. pending report
|
BLD-Foundation | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | PEND |
Tony Young
|
|
|
Chris-pour time 1:30 Phone #: ###-####,, special inspection report
|
Override - Condition Holds | 6/27/2019 | 1/1/1900 | 6/27/2019 | | |
|
|
|
not doing the final so can schedule insp for foundation
|
BLD-Footing | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PEND |
Tony Young
|
|
|
for area B interior // Chris Phone #: ###-####,, work in progress,, special inspector will be on site for rebar and sample etc.
|
Override - Condition Holds | 6/20/2019 | 1/1/1900 | 6/20/2019 | | |
|
|
|
not for occupancy
|
BLD-Foundation | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PART |
Tony Young
|
|
|
area B-Chris Phone #: ###-####,, ok pending special inspection reports
|
Override - Condition Holds | 6/13/2019 | 1/1/1900 | 6/13/2019 | | |
|
|
|
.
|
BLD-Footing | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PART |
Tony Young
|
|
|
Chris-stem walls area A-footings area B-pour time 12:30 Phone #: ###-####,, pending special inspection
|
Override - Condition Holds | 6/5/2019 | 1/1/1900 | 6/5/2019 | | |
|
|
|
tag does not say no inspections can be done-JCT not in office-this is a footing inspection
|
Routing PW Street Lights | 5/28/2019 | | 5/28/2019 | | FAIL |
Jason C. Taylor
|
|
|
Streetlight Pole was removed for construction entrance without COB PW Approval. Street Light will need to be replaced ASAP. Jason Taylor ###-####
|
BLD-Footing | 5/15/2019 | 5/16/2019 | 5/16/2019 | P | PART |
Tony Young
|
|
|
Concrete scheduled for 3 PM. Strata scheduled for 2 PM special inspections Please call when in route or to discuss. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, special inspector on site
|
BLD-Footing | 5/16/2019 | 5/16/2019 | 5/16/2019 | A | PART |
Tony Young
|
|
|
Concrete scheduled for 3 PM. Strata scheduled for 2 PM special inspections Please call when in route or to discuss. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, site visit,, work in progress
|
Print Occupancy Form | | | 3/29/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/29/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/18/2019 | | |
|
|
|
|
Routing PW Sewer Design | 3/18/2019 | | 3/18/2019 | | PASS |
DeAnn Brown
|
|
|
|
Permit Ready to Issue | | | 3/18/2019 | | DONE |
|
|
|
Still Need: ACHD
MET: RP
MET: GC Form
MET: Revised Value (DO NOT CHARGE MORE THAN STATE PLAN CHECK FEE)
|
Plan assigned to (JAR) | 1/28/2019 | 1/28/2019 | 3/15/2019 | | DONE |
Julie Romig
|
|
|
03/12 - 2nd Rev - 1st Rev Comp - **Expedited Review ** 502 Pierce Park Elementary School. *IBC Rev Comp; need elec/struc reviews, then route back to applicant*
|
Routing - PLAN CHECK | 3/14/2019 | | 3/15/2019 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 3/14/2019 | | 3/15/2019 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2019 | | DONE |
|
|
|
|
Routing - ELECTRICAL | 3/14/2019 | | 3/14/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 3/6/2019 | | 3/14/2019 | | FAIL |
Carl D Madsen
|
|
|
KPFF - 2nd Review
|
Routing PW Solid Waste | 3/13/2019 | | 3/13/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - ELECTRICAL | 3/6/2019 | | 3/12/2019 | | FAIL |
Javier Guzman
|
|
|
2nd Review
|
Routing - PLAN CHECK | 3/6/2019 | | 3/9/2019 | | FAIL |
Julie Romig
|
|
|
2nd Review - Report emailed to Architect.
|
Routing - FIRE | 3/6/2019 | 3/6/2019 | 3/8/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Solid Waste | 3/6/2019 | | 3/6/2019 | | FAIL |
Evan Carpenter
|
|
|
The northern dumpster's gate dimensions of 12.5’ are OK as planned. However, the southern gate opening for the two dumpsters must have 18’ of unobstructed clearance between gate posts, per the requirements linked below. This is to ensure that the collection truck can adequately access the dumpsters. The overall enclosure footprint will need to expand to accommodate these requirements, or the center gate post will need to be removed.
|
Routing - MECHANICAL | 3/6/2019 | | 3/6/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/8/2019 | 2/11/2019 | 2/11/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/28/2019 | 1/28/2019 | 2/8/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 1/28/2019 | | 2/8/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - ELECTRICAL | 1/28/2019 | | 2/8/2019 | | FAIL |
Javier Guzman
|
|
|
03/12 - **Expedited Review ** 502 Pierce Park Elementary School.
|
1st review completed | | | 2/8/2019 | | DONE |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/28/2019 | | 2/4/2019 | | FAIL |
Julie Romig
|
|
|
KPFF - 1st Review - Corrections required per ePlanReview
|
Routing PW Drainage | 1/28/2019 | | 2/1/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 1/28/2019 | | 2/1/2019 | | FAIL |
Troy James
|
|
|
|
Routing PW Environmental | 1/28/2019 | | 1/31/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 1/28/2019 | | 1/30/2019 | | PASS |
Daryl Spivey
|
|
|
May require additional backflow protection on installed equipment and a DCVA may be used for service protection.
|
Routing PW Sewer Design | 1/28/2019 | | 1/30/2019 | | FAIL |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 1/28/2019 | | 1/30/2019 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure must have at least 12 feet of unobstructed clearance between gate posts for the northern dumpster (currently measuring 10 feet), or center gate post must be removed.
|
Routing - PUBLIC WORKS | 1/28/2019 | | 1/29/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/28/2019 | | 1/28/2019 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Routing PW Street Lights | 1/28/2019 | | 1/28/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 1/28/2019 | | 1/28/2019 | | PASS |
Brent Moore
|
|
|
|
Routing - Addressing | 1/28/2019 | | 1/28/2019 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 1/28/2019 | | PASS |
Julie Romig
|
|
|
Prescreen approved by JAR
|
Meeting | | | 1/23/2019 | | DONE |
|
|
|
While paying the plan check fee we noticed that this address is owned by Boise Schools, we correct the plan check fee due and will process with fees paid task when comes up. (spoke with CDP)
|
Application received | | | 1/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2019 3:40PM
|