Permit Information
Permit NumberBLD19-00248
StatusTemporary Occupancy
Name ENGINEERED STRUCTURES INC
Site Address 5015 N PIERCE PARK LN
Project NamePierce Park Elementary School
Customer Number 
ePlanReviewYes
Description
(PIERCE PARK ELEMENTARY SCHOOL) (CUP18-00072) PROJECT MANAGEMENT- RON HILL. Permit for the construction of a new 49,813 sq. ft. elementary school to replace the existing 24,199 sq ft school that is to be demolished when the new school is completed. Work will include general site work, utilities and construction of the new building per the approved plans, attached engineering and any comments. Special inspections required per attached Form 310. This is a fully fire sprinklered and alarmed building for E fire area over 12,000 sq. ft. and building area increase. *JAR*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Zoning Approval Temp8/13/20208/13/20208/13/2020 DONE
DetailsCody Riddle
Inspected the site on 8/12/2020. Temporary occupancy to allow parents and staff to conduct computer pick-up activities okay. Paved, accessible routes to, from, and around site, in place.
BLD-Final8/12/20208/12/20208/12/2020PPART
DetailsTony Young
Phase 2 TCO. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// 2nd phase ok for temp occupancy
FIRE-Final Inspection8/12/20208/12/20208/12/2020PPART
DetailsJim Page
Life fire safety inspection for TCO phase 2 complete, exit signs that were noted missing have been placed.

Phase 2 TCO. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Final8/5/20208/6/20208/6/2020APART
DetailsTony Young
Building Re-inspection. Access through South gate. Please call when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// temp occupancy ok
PubWorks Temp Occupancy Appr8/6/20208/6/20208/6/2020 DONE
DetailsTiffany Lowery
Temporary Occupancy7/21/202010/19/20207/21/2020 DONE
DetailsGemma Flores
BLD-Final7/17/20207/20/20207/20/2020PPART
DetailsJim Storey
TCO Phone #: ###-#### Inspection requested via web by Chris Fuhrman handrail returns/ missing exit signs/ need smoke seal on fire door/ occ load signage/ temp occ
FIRE-Final Inspection7/17/20207/20/20207/20/2020APART
DetailsJim Page
Life fire safety inspection for TCO phase 1 complete.

TCO Phone #: ###-#### Inspection requested via web by Chris Fuhrman
FIRE-Final Inspection4/7/20204/7/20204/7/2020APART
DetailsJim Page
Fire sprinkler riser monitoring has been tested and complete, storage of furntiure in building is authorized. After this entry fire sprinklers are to remain active and monitored (Allowed to be put on test during normal working hours, fire sprinkler monitoring must be taken off of test at the end of the business day, if monitoring is not active then furntiure storage will be revoked).
BLD-Ceiling Grid Inspection4/2/20204/2/20204/2/2020PPASS
DetailsDave Hannah
library, cafeteria ; music Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Ceiling Grid Inspection2/28/20202/28/20202/28/2020APASS
DetailsJim Storey
no wires need at pirimtor admin and hallway ok to cover.
BLD-Ceiling Grid Inspection2/26/20202/27/20202/27/2020APART
DetailsJim Storey
1B Administration Area Phone #: ###-#### Inspection requested via web by Chris Fuhrman main wirers ok pending sica listing to not need perimitor wirers.
FIRE-Conference2/26/20202/27/20202/27/2020ADONE
DetailsJim Page
Fire conferene complete.

Review new BSD occupancy and phasing schedule and requirements. Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Framing/Rough-in2/20/20202/21/20202/21/2020APART
DetailsTony Young
Area C Gyp Ceilings Phone #: ###-#### Inspection requested via web by Chris Fuhrman.. ok pending trades
BLD-Ceiling Grid Inspection2/20/20202/21/20202/21/2020APART
DetailsTony Young
2B Classrooms Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, ok pending trades
BLD-Ceiling Grid Inspection2/12/20202/12/20202/12/2020APASS
DetailsTony Young
Grid Ceiling 2A Phone #: ###-#### Inspection requested via web by Chris Fuhrman// work in progress,, ok
BLD-Framing/Rough-in2/12/20202/12/20202/12/2020APASS
DetailsTony Young
Hard Ceiling Area 2B and Cafe Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Ceiling Grid Inspection1/30/20201/30/20201/30/2020PPASS
DetailsDave Hannah
1A Phone #: ###-#### Inspection requested via web by Chris Fuhrman see plans for locations
BLD-Framing/Rough-in1/30/20201/30/20201/30/2020PPASS
DetailsDave Hannah
Hard Ceilings 1B Phone #: ###-#### Inspection requested via web by Chris Fuhrman see plans for locations
BLD-Framing/Rough-in1/7/20201/7/20201/7/2020APART
DetailsTony Young
Gypsum Ceilings 1A - 2A Phone #: ###-#### Inspection requested via web by Chris Fuhrman// ok pending trades
BLD-Framing/Rough-in12/18/201912/18/201912/18/2019PPART
DetailsTony Young
1B Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// ok to start covering pending trades
FIRE-Conference12/13/201912/13/201912/13/2019PDONE
DetailsJim Page
Fire conference complete, discussed items required for life fire safety for phase 1 occupancy.

Review phase 1 occupancy / egress plan. Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
FIRE-Conference12/10/201912/11/201912/11/2019ACANC
DetailsJim Page
Tried calling point of contact listed 2 times over a 15 minute time period, first time went right to voicemail but no message could be left because mailbox was full. 2nd call phone rang through, still went to voicemail but could not leave a message. procceeded to next inspection, conference will need to be rescheduled. This conference is cancelled.

Review phase 1 turnover plan. Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Wall cover12/6/201912/6/201912/6/2019PPART
DetailsTony Young
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman// area A1 and A2 ok to cover
BLD-Energy code compliance12/6/201912/6/201912/6/2019PPASS
DetailsTony Young
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, exterior insulation wrap ok
BLD-Framing/Rough-in12/5/201912/6/201912/6/2019APART
DetailsTony Young
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, area 1a walk through
BLD-Wall Bracing11/18/201911/18/201911/18/2019PPART
DetailsTony Young
SHEAR // Terry Phone #: ###-####.. areas marked on the plans
BLD-Framing/Rough-in11/12/201911/12/201911/12/2019PPART
DetailsTony Young
Terry Phone #: ###-####,, area A-1 interior ok pending trades,, B-1 interior ok pending trades,, B-1 exterior shear work in progress,, ok to cover when ready
BLD-Wall Bracing11/8/201911/8/201911/8/2019PDEFR
DetailsTony Young
Please call Chris when in route. Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Wall Bracing10/21/201910/22/201910/22/2019APART
DetailsDave Hannah
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman area a ok
BLD-Conference10/9/201910/10/201910/10/2019APART
DetailsTony Young
Review upcoming framing inspections and egress phasing plan for new school Phone #: ###-#### Inspection requested via web by Chris Fuhrman/// walk through.. will need fire/ l/ s on egress issues 1st,, ok to start sheeting exterior on south walls
BLD-Conference10/8/201910/9/201910/9/2019PDEFR
DetailsTony Young
Review upcoming framing inspections and egress phasing plan for new school Phone #: ###-#### Inspection requested via web by Chris Fuhrman// called and left a voicemail,, out of time
BLD-Energy code compliance7/17/20197/18/20197/18/2019APART
DetailsDave Hannah
Chris Phone #: ###-#### insulated cmu units
Override - Condition Holds7/17/20191/1/19007/17/2019  
This is a energy inspection, hold is for street light
BLD-Foundation7/1/20197/1/20197/2/2019PPART
DetailsTony Young
Chris Phone #: ###-####,, special inspector on site.. pending report
BLD-Foundation6/27/20196/27/20196/27/2019PPEND
DetailsTony Young
Chris-pour time 1:30 Phone #: ###-####,, special inspection report
Override - Condition Holds6/27/20191/1/19006/27/2019  
not doing the final so can schedule insp for foundation
BLD-Footing6/20/20196/21/20196/21/2019APEND
DetailsTony Young
for area B interior // Chris Phone #: ###-####,, work in progress,, special inspector will be on site for rebar and sample etc.
Override - Condition Holds6/20/20191/1/19006/20/2019  
not for occupancy
BLD-Foundation6/13/20196/13/20196/13/2019PPART
DetailsTony Young
area B-Chris Phone #: ###-####,, ok pending special inspection reports
Override - Condition Holds6/13/20191/1/19006/13/2019  
.
BLD-Footing6/5/20196/6/20196/6/2019APART
DetailsTony Young
Chris-stem walls area A-footings area B-pour time 12:30 Phone #: ###-####,, pending special inspection
Override - Condition Holds6/5/20191/1/19006/5/2019  
tag does not say no inspections can be done-JCT not in office-this is a footing inspection
Routing PW Street Lights5/28/2019 5/28/2019 FAIL
DetailsJason C. Taylor
Streetlight Pole was removed for construction entrance without COB PW Approval. Street Light will need to be replaced ASAP. Jason Taylor ###-####
BLD-Footing5/15/20195/16/20195/16/2019PPART
DetailsTony Young
Concrete scheduled for 3 PM. Strata scheduled for 2 PM special inspections
Please call when in route or to discuss.
Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, special inspector on site
BLD-Footing5/16/20195/16/20195/16/2019APART
DetailsTony Young
Concrete scheduled for 3 PM. Strata scheduled for 2 PM special inspections
Please call when in route or to discuss.
Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman,, site visit,, work in progress
Print Occupancy Form  3/29/2019 DONE
Issue PAID IN FULL permit  3/29/2019 DONE
OVERRIDE  3/18/2019  
Routing PW Sewer Design3/18/2019 3/18/2019 PASS
DetailsDeAnn Brown
Permit Ready to Issue  3/18/2019 DONE
Still Need: ACHD
MET: RP
MET: GC Form
MET: Revised Value (DO NOT CHARGE MORE THAN STATE PLAN CHECK FEE)
Plan assigned to (JAR)1/28/20191/28/20193/15/2019 DONE
DetailsJulie Romig
03/12 - 2nd Rev - 1st Rev Comp - **Expedited Review ** 502 Pierce Park Elementary School. *IBC Rev Comp; need elec/struc reviews, then route back to applicant*
Routing - PLAN CHECK3/14/2019 3/15/2019 PASS
DetailsJulie Romig
Routing Off Site - STRUCTURAL3/14/2019 3/15/2019 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  3/15/2019 DONE
Routing - ELECTRICAL3/14/2019 3/14/2019 PASS
DetailsJavier Guzman
Routing Off Site - STRUCTURAL3/6/2019 3/14/2019 FAIL
DetailsCarl D Madsen
KPFF - 2nd Review
Routing PW Solid Waste3/13/2019 3/13/2019 PASS
DetailsEvan Carpenter
Routing - ELECTRICAL3/6/2019 3/12/2019 FAIL
DetailsJavier Guzman
2nd Review
Routing - PLAN CHECK3/6/2019 3/9/2019 FAIL
DetailsJulie Romig
2nd Review - Report emailed to Architect.
Routing - FIRE3/6/20193/6/20193/8/2019 PASS
DetailsErika Akin
Attached comments to case
Routing PW Solid Waste3/6/2019 3/6/2019 FAIL
DetailsEvan Carpenter
The northern dumpster's gate dimensions of 12.5’ are OK as planned. However, the southern gate opening for the two dumpsters must have 18’ of unobstructed clearance between gate posts, per the requirements linked below. This is to ensure that the collection truck can adequately access the dumpsters. The overall enclosure footprint will need to expand to accommodate these requirements, or the center gate post will need to be removed.
Routing - MECHANICAL3/6/2019 3/6/2019 PASS
DetailsTroy James
Route to Impact Fee Review2/8/20192/11/20192/11/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
Routing - FIRE1/28/20191/28/20192/8/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK1/28/2019 2/8/2019 FAIL
DetailsJulie Romig
Routing - ELECTRICAL1/28/2019 2/8/2019 FAIL
DetailsJavier Guzman
03/12 - **Expedited Review ** 502 Pierce Park Elementary School.
1st review completed  2/8/2019 DONE
DetailsJulie Romig
Routing Off Site - STRUCTURAL1/28/2019 2/4/2019 FAIL
DetailsJulie Romig
KPFF - 1st Review - Corrections required per ePlanReview
Routing PW Drainage1/28/2019 2/1/2019 PASS
DetailsBrian Murphy
Routing - MECHANICAL1/28/2019 2/1/2019 FAIL
DetailsTroy James
Routing PW Environmental1/28/2019 1/31/2019 PASS
DetailsRick Christenson
Routing - PLUMBING1/28/2019 1/30/2019 PASS
DetailsDaryl Spivey
May require additional backflow protection on installed equipment and a DCVA may be used for service protection.
Routing PW Sewer Design1/28/2019 1/30/2019 FAIL
DetailsDeAnn Brown
Routing PW Solid Waste1/28/2019 1/30/2019 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have at least 12 feet of unobstructed clearance between gate posts for the northern dumpster (currently measuring 10 feet), or center gate post must be removed.
Routing - PUBLIC WORKS1/28/2019 1/29/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment1/28/2019 1/28/2019 PASS
DetailsMichael Zawacki
Site prep inspection required.
Routing PW Street Lights1/28/2019 1/28/2019 PASS
DetailsTom Marshall
Routing - PLANNING1/28/2019 1/28/2019 PASS
DetailsBrent Moore
Routing - Addressing1/28/2019 1/28/2019 PASS
DetailsLaura Hunter
Intake Approval  1/28/2019 PASS
DetailsJulie Romig
Prescreen approved by JAR
Meeting  1/23/2019 DONE
While paying the plan check fee we noticed that this address is owned by Boise Schools, we correct the plan check fee due and will process with fees paid task when comes up. (spoke with CDP)
Application received  1/22/2019 DONE
Application submitted via PDS Online on Jan 22 2019 3:40PM