BLD-Final | 7/6/2020 | 7/6/2020 | 7/6/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by russell reber
|
DOC - Permit Finaled | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PASS |
Mike Jordan
|
|
|
|
Letter of compliance/Occupancy | | | 7/6/2020 | | DONE |
|
|
|
|
BLD-Final | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Ed Kron. Needs to complete driveway.
|
BLD-Framing/Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade. . All issues resolved.
|
BLD-Energy code compliance | 3/31/2020 | 3/31/2020 | 3/31/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD-Energy code compliance | 3/26/2020 | 3/30/2020 | 3/30/2020 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ed Kron Inspection cancelled from web by: Ed Kron
|
BLD-Energy code compliance | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | NR |
Mike Jordan
|
|
|
Ed Phone #: ###-####
|
BLD-Energy code compliance | 3/18/2020 | 3/18/2020 | 3/18/2020 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD-Framing/Rough-in | 3/18/2020 | 3/18/2020 | 3/18/2020 | A | FAIL |
Mike Jordan
|
|
|
Please call 15 minutes prior to inspection Phone #: ###-#### Inspection requested via web by Shane Shade. fire caulk pentrations in firewall, repair holes in draft stop. Address sill heights for egress windows, extend the 1hr. wall upstairs to the exterio wall and rock soffitt. ok to insulate.
|
Fees Due Hold | 3/13/2020 | | 3/16/2020 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/11/2020 | | 3/12/2020 | | PASS |
Troy James
|
|
|
Resubmitted ACCA report
|
Plan Modification Accepted | | | 3/10/2020 | | DONE |
|
|
|
plan mod for manual J request per Megan Fuller
|
BLD-Wall Bracing | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD-Foundation | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 11/25/2019 | 11/26/2019 | 11/26/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 11/24/2019 | 11/25/2019 | 11/25/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru. Cancelled by contractor via phone call.
|
BLD-Footing | 11/17/2019 | 11/18/2019 | 11/18/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
Issue PAID IN FULL permit | | | 6/24/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/24/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/5/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 4/30/2019 | 4/30/2019 | 6/5/2019 | | DONE |
Jenny Nelson
|
|
|
05/17 duplex L2 ePlan. 1st complete 5/15 clarify notes, update PFG detail
|
Routing - PLAN CHECK | 6/5/2019 | | 6/5/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/5/2019 | | DONE |
|
|
|
West Boise Sewer District per Morgan
|
Routing - MECHANICAL | 5/31/2019 | | 5/31/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 4/30/2019 | | 5/15/2019 | | PASS |
Angela Hardy
|
|
|
|
1st review completed | | | 5/15/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 4/30/2019 | | 5/15/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 4/30/2019 | 5/3/2019 | 5/1/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/30/2019 | | 5/1/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 4/30/2019 | | 4/30/2019 | | PASS |
Doug Chausow
|
|
|
7252 and 7238 W Denton St
|
Routing - MECHANICAL | 4/30/2019 | | 4/30/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to Connor
|
Plans ACCEPTED BY PLAN TECH | | | 4/30/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/30/2019 | | PASS |
|
|
|
|
Meeting | | | 4/29/2019 | | DONE |
|
|
|
Emailed Applicant and GC to confirm the floor plans and site plans submitted for prescreen match DRH18-00214 plan modification approval.
|
Meeting | | | 2/28/2019 | | DONE |
|
|
|
Per Andrea T, there is a plan mod for the DRH case that needs to be compelted before submitting for building permit.
|
Application received | | | 2/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2019 10:12AM
|