Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | | 9/19/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
BLD-Final | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Permanent Occupancy | | | 9/9/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected except for the round type door hardware that is still on 3 doors, the mech room door, janitors closet and large room southside basement, round type door hardware needs to be replaced with code compliant door hardware before BLD final, hardware change will be verified during BLD final per conversation with Dave Hannah. Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags, final life fire safety inspection is complete, card has been signed for fire alarm, fire sprinkler and life safety.
Mike Phone #: ###-####
|
FIRE-Final Inspection | 8/26/2019 | 8/27/2019 | 8/27/2019 | P | CANC |
Jim Page
|
|
|
FIR permit for fire alarm \s needs to be finaled before life fire safety inspection can be completed, last fire alarm inspection resulted in a fail, this request is cancelled.
Mike Phone #: ###-####
|
FIRE-Final Inspection | 8/23/2019 | 8/26/2019 | 8/26/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide knox box, provide annual inspection for fire sprinkler system, provide single action hardware for the three doors in basement, provide address as discussed,
Mike Phone #: ###-####
|
Print Occupancy Form | | | 8/26/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 8/1/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 6/20/2019 | 6/21/2019 | 6/24/2019 | P | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/10/2019 | | DONE |
|
|
|
emailed nate.walrath@steedconstruction.com
to sign building permit
|
Print Occupancy Form | | | 6/10/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/11/2019 | 4/11/2019 | 6/6/2019 | | PASS |
Javier Guzman
|
|
|
3rd rev comp, 04/24 L2 Gravity Payments ePlan, pend DR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
all met: nate.walrath@steedconstruction.com
NEED
GC FORM
REVISED VALUE
|
Routing - Design Review | 5/25/2019 | | 6/4/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 5/25/2019 | | 5/29/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 5/9/2019 | | 5/13/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 5/9/2019 | | 5/9/2019 | | FAIL |
Andrea Tuning
|
|
|
Provide a 5-foot setback from the south property line to the proposed trash enclosure. The 5-foot setback area shall be landscape to screen the enclosure from public view.
Meet all Public Works standards for the proposed trash enclosure. Please see the memo dated January 11, 2019 from Public Works in regard to solid waste.
The elevations proposed do not match the elevations approved under Design Review application DRH19-00003. The applicant should submit elevations that match the approved Design Review application or obtain a Design Review modification.
|
Route to Impact Fee Review | 4/24/2019 | 4/27/2019 | 4/25/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/24/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/11/2019 | | 4/24/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 4/11/2019 | | 4/16/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 4/11/2019 | | 4/15/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 4/11/2019 | | 4/12/2019 | | FAIL |
Andrea Tuning
|
|
|
Provide a 5-foot setback from the south property line to the proposed trash enclosure. The 5-foot setback area shall be landscape to screen the enclosure from public view.
Meet all Public Works standards for the proposed trash enclosure. Please see the memo dated January 11, 2019 from Public Works in regard to solid waste.
The weather protection devices on the west elevation will be allowed to encroach a maximum depth of 2-feet into the 27th Street setbacks (20-feet) or obtain a variance to allow further encroachment.
Relocate the proposed bicycle parking to be located outside of the planter islands. The parking shall be conveniently located and visible to individuals utilizing alternative modes of transportation and comply with ordinance standards in regard to dimensions and location.
|
Routing - Addressing | 4/11/2019 | | 4/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 4/11/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/2/2019 | | FAIL |
Michael Hanson
|
|
|
Provide location of fire extinguishers (existing and new)
Provide structural engineering demonstrating existing structure can support new roof top equipment.
|
Application received | | | 3/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2019 10:07AM
|
(F) Reprint permit | | | 3/6/2019 | | DONE |
|
|
|
|