BLD-Final | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | PART |
Tell Riley
|
|
|
Carl Phone #: ###-####//phase 1 TCO approved//
|
FIRE-Final Inspection | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in the Phase 1 area of work. Carl Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Tell Riley
|
|
|
Carlo Phone #: ###-####//wall cover ok//discussed maintaining the 1 hour corridor and penetrations will need to be fire stopped//
|
Issue PAID IN FULL permit | | | 7/1/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/1/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/25/2019 | 5/25/2019 | 5/29/2019 | | PASS |
Javier Guzman
|
|
|
05/30 L1 Lower Lever - IPTV Bldg. ePlan
|
1st review completed | | | 5/29/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/29/2019 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 5/25/2019 | | 5/29/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 5/25/2019 | | 5/29/2019 | | PASS |
Doug Chausow
|
|
|
Signed off in ePlan by PW Addressing Doug Chausow
|
Routing - PUBLIC WORKS | 5/25/2019 | | 5/28/2019 | | PASS |
Angela Hardy
|
|
|
|
Plan assigned to (JAR) | 5/25/2019 | 5/25/2019 | 5/25/2019 | | DEFR |
Julie Romig
|
|
|
05/30 L1 Engage Boise ePlan
|
Intake Approval | | | 5/24/2019 | | |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/22/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Provide as stated on checklist the missing Ceiling details sheet A6.2
|
Application received | | | 5/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2019 2:47PM
|