Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD19-02216
StatusIssued
Name EIGHTH & MAIN CONDOMINIUM ASSOCIATI
Site Address 800 W MAIN ST Unit: 210
Project NameBlackBox VR T.I.
Customer Number 
ePlanReviewYes
Description
(BLACKBOX VR - GARDNER COMPANY SUITE #210) This building is fire sprinkled as it is a high rise. Permit to remodel 2,667 sqft. of existing recreational space to create a virtual reality gym. Work to include: demo select interior non-load bearing walls and door, construct new non-load bearing wall to create new IT closet and infill wall, 8'-0" partition system to separate gym space, minor electrical work. Interior finishes shall be in compliance with chapter 8. Approval is contingent on adhering to the approved plans. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire Department. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  8/5/2019 DONE
BLD-Final8/2/20198/2/20198/2/2019PPASS
DetailsDave Hannah
Laren Phone #: ###-####
FIRE-Final Inspection8/2/20198/2/20198/2/2019PPASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, outlets for VR units shunt during fire alarm activation, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
BLD-Final7/31/20198/1/20198/1/2019PCANC
DetailsTell Riley
Leren Phone #: ###-####//cancel per Leren//need to pass fire final//
FIRE-Final Inspection7/31/20198/1/20198/1/2019AFAIL
DetailsMark Scharfen
E-lights/extinguisher in place. Tested interface for shunt with Protex on site. Manually turning on relay did shunt the breaker but did not work in normal operation. Told Leren and Protex that a fire alarm permit would need to be pulled and proof of a propper pretest before building or fire alarm final is to be called in again.

Leren Phone #: ###-####
CHANGE STATUS TO (ISS)  8/1/2019 DONE
Dave H. doc final accidently per Mark Scharfen change status to ISS
DOC - Permit Finaled7/31/20197/31/20197/31/2019PPASS
DetailsDave Hannah
Inspection Record Card- Bld  7/9/2019 DONE
Issue PAID IN FULL permit  7/9/2019 DONE
Routing - PLAN CHECK7/1/2019 7/1/2019 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  7/1/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  7/1/2019 DONE
MET
Need GC
Need Rev cert of val
Plan assigned to (M_H)6/24/2019 7/1/2019 DONE
DetailsMichael Hanson
1st review completed - 06/25 #518 L1 ePlan - BlackBox VR
Route to Impact Fee Review6/24/20196/27/20196/25/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Plan assigned to (JG)6/19/20196/19/20196/24/2019 DEFR
DetailsJavier Guzman
06/25 L1 BlackBox VR ePlan
Routing - PLAN CHECK6/19/2019 6/24/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
1st review completed  6/24/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
Intake Approval  6/19/2019 PASS
DetailsJavier Guzman
Routing - PUBLIC WORKS6/19/2019 6/19/2019 PASS
DetailsAngela Hardy
Routing - Addressing6/19/2019 6/19/2019 PASS
DetailsDoug Chausow
Application received  6/14/2019 DONE
Application submitted via PDS Online on Jun 14 2019 3:38PM