Print Statement | | | 1/16/2020 | | DONE |
|
|
|
|
Second Notice | | 12/7/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
First Notice | | 11/22/2019 | 11/27/2019 | | DONE |
|
|
|
mailed 12-2-19
|
Permanent Occupancy | | | 11/12/2019 | | DONE |
|
|
|
|
BLD-Final | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
FIRE-Final Inspection | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Chris Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
Zoning Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Ceiling Grid Inspection | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-####
|
BLD-Wall Bracing | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | PART |
Tell Riley
|
|
|
Chris Phone #: ###-####//shear wall nailing ok per plans//hold downs and welding required for shear walls completed by third party//ok to cover pending third party approval of hold downs installation//
|
BLD-Ceiling Grid Inspection | 10/4/2019 | 10/7/2019 | 10/7/2019 | A | PART |
Jim Storey
|
|
|
Chris Phone #: ###-#### hardlids in bathrooms ok/ kicker at soffit instaled perplan.
|
BLD-Framing/Rough-in | 10/3/2019 | 10/4/2019 | 10/4/2019 | P | NR |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Hardlids in restrooms ok, Needs to add kickers to drop soffit over beverage area, also needs fire sprinkler rough in inspection as well.
|
BLD-Energy code compliance | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | PASS |
Mike Jordan
|
|
|
Restroom and cooler walls ok.
|
BLD-Energy code compliance | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | NR |
Mike Jordan
|
|
|
Chris Phone #: ###-####.
|
BLD-Framing/Rough-in | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PART |
Tell Riley
|
|
|
Chris Phone #: ###-####//ok to cover bathroom walls only//need shearwalls to reflect plans--anchoring, posts,mechanical connections and shear nailing//need mechanical inspection for ceilings//
|
Issue PAID IN FULL permit | | | 8/21/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/21/2019 | | DONE |
|
|
|
|
Telephone call | | | 8/14/2019 | | DONE |
|
|
|
emailed Andrea Speed fees due
|
Place hold on job | 8/8/2019 | | 8/12/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
DO NOT ISSUE UNTIL BLD19-02463 IS ISSUED FIRST PER CARL W
Permit was issued 8-8-19
|
Plan assigned to (CJW) | 6/25/2019 | 7/18/2019 | 8/8/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 07/11/19 (L-3 - 15 days) (eplan - 65 sheets) MOD pizza (back to applicant)
|
Routing - PLAN CHECK | 8/7/2019 | | 8/8/2019 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2019 | | DONE |
|
|
|
MET - DO NOT ISSUE UNTIL BLD19-02463 IS ISSUED FIRST
MET: andrea.speed@graphitedesigngroup.com
NEED
GC FORM
REVISED VALUE
|
Plan resubmittals received | | | 8/7/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/19/2019 | 7/22/2019 | 7/19/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 7/19/2019 | | DONE |
|
|
|
|
Routing - FIRE | 6/25/2019 | 6/25/2019 | 7/18/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 7/18/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/25/2019 | | 7/17/2019 | | FAIL |
Carl Westfall
|
|
|
1st IBC plan review completed
|
Routing PW Environmental | 6/25/2019 | | 7/2/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing Off Site - C.D.H | 6/25/2019 | | 7/1/2019 | | PASS |
Carl Westfall
|
|
|
Matt McDonald
|
Routing - MECHANICAL | 6/25/2019 | | 6/27/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/25/2019 | | 6/26/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - Addressing | 6/25/2019 | | 6/26/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2019 | | 6/25/2019 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT.
|
Routing - Erosion and Sediment | 6/25/2019 | | 6/25/2019 | | PASS |
Michael Zawacki
|
|
|
|
Routing - Design Review | 6/25/2019 | | 6/25/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 6/25/2019 | | 6/25/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Plan Reviewer's activity | | | 6/21/2019 | | PASS |
|
|
|
Plan intake review approved. Before this permit is issued, a separate permit is required to be issued to authorize the structural upgrades that are required to restore the capacity of this building to resist lateral loads in compliance with the 2015 IBC. The new openings in the East, West, and South walls were made without a lateral load structural evaluation to demonstrate that the capactity is either at least being maintained or not reduced below the levels of the 2015 IBC. A complete and thorough lateral analysis of this building taking into account all changes and improvements to the lateral load resisting system is required. CJW
|
Intake Approval | | | 6/21/2019 | | PASS |
|
|
|
|
Application received | | | 6/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 17 2019 5:08PM
|