First Notice | | 11/17/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
BLD-Final | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Tell Riley
|
|
|
Please call 30 min in advance so that I can meet you on site Phone #: ###-#### Inspection requested via web by Chase Cheverton//complete per plans//no tennant furnishings were present at final inspection//
|
Permanent Occupancy | | | 11/7/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
FIRE-Conference | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | DONE |
Troy Cobbley
|
|
|
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
BLD-Ceiling Grid Inspection | 10/17/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Tell Riley
|
|
|
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
FIRE-Conference | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | DONE |
Troy Cobbley
|
|
|
The project superintendant and I discussed door hardware issues on doors #2 and #3. #2 shows to be deleted and #3 says to have panic. Right now they are both keyed deadbolts.
|
BLD-Framing/Rough-in | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Tell Riley
|
|
|
Please call 30 min ahead so I can meet you on site Phone #: ###-#### Inspection requested via web by Chase Cheverton//wall cover ok//call for grid when ready//
|
Telephone call | | | 8/29/2019 | | DONE |
|
|
|
Called Cheyanna and let her know additional fees were due for fire. I emailed her the fees.
|
Issue PAID IN FULL permit | | | 8/28/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/28/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/6/2019 | 8/6/2019 | 8/27/2019 | | DONE |
Julie Romig
|
|
|
08/28 - 2nd Rev - 1st Rev Comp - L2 IDEXX
|
Routing - PLAN CHECK | 8/26/2019 | | 8/27/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/27/2019 | | DONE |
|
|
|
MET- Need GC
Need rev cert of val
|
Route to Impact Fee Review | 8/23/2019 | 8/26/2019 | 8/23/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/22/2019 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 8/6/2019 | | 8/22/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 8/19/2019 | 8/19/2019 | 8/19/2019 | | PASS |
Mark Scharfen
|
|
|
2nd review passed 08.19.2019-uploaded rev_fire 1 08.19.2019.pdf.
|
Routing - FIRE | 8/6/2019 | 8/6/2019 | 8/19/2019 | | FAIL |
Mark Scharfen
|
|
|
08/16-IDEXX Remodel 518-completed fire review. Uploaded rev_fire 08.19.2109.pdf and emailed to architect.
|
Routing PW Environmental | 8/7/2019 | | 8/14/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 8/6/2019 | | 8/9/2019 | | PASS |
Troy James
|
|
|
Redlined outside air requirements.
|
Routing - PLANNING | 8/6/2019 | | 8/7/2019 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 8/6/2019 | | 8/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Addressing | 8/6/2019 | | 8/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 8/6/2019 | | 8/6/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 8/5/2019 | | |
Carl D Madsen
|
|
|
|
Application received | | | 8/1/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 1 2019 4:35PM
|