Permit Information
Permit NumberBLD20-00704
StatusIssued
Name ARMADA HOMES
Site Address 9718 W MACAW ST
Project NameEronel 4-3
Customer Number 
ePlanReviewYes
Description
***07/29 PLAN MODIFICATION TO CHANGE WINDOW U VALUES AND INSULATION VALUES AND REMOVE REBAR FROM FOUNDATION AND PATIO*** Permit for the construction of a new 1884 sq. ft., two story (first story 1201 sq. ft., second story 683 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 132 sq. ft. of covered patio/porch and a 445 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. R-1C zoning and setbacks per planning. ***RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (ISS)  7/30/2020 DONE
OVERRIDE  7/29/2020  
Plan assigned to (RDP)7/24/20207/24/20207/29/2020 DONE
DetailsRob Patrick
plan mod
Routing - PLAN CHECK7/27/2020 7/29/2020 PASS
DetailsRob Patrick
1 hour review fee
PLANS/APPL TAKEN TO FRONT DESK  7/29/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  7/29/2020 DONE
**DO NOT REISSUE - PLAN PLAN MOD**
Plan Modification Accepted  7/24/2020 DONE
Kelly from Armada homes called to request a plan modification. change window U values, insulation values, remove rebar from foundation and patio slabs
BLD-Energy code compliance7/6/20207/6/20207/6/2020APASS
DetailsTell Riley
ok when insulation is installed back in areas that were opened up//
BLD-Framing/Rough-in7/2/20207/6/20207/6/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Framing/Rough-in6/29/20206/30/20206/30/2020APART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//CN posted for minor framing corrections noted on plans and truss docs//ok to insulate only//
BLD-Framing/Rough-in6/25/20206/26/20206/26/2020PCANC
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Framing/Rough-in6/24/20206/25/20206/25/2020ACANC
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//need mechanical rough in completed prior to framing inspection//let Mark know//
BLD-Wall Bracing6/10/20206/10/20206/10/2020PPASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Foundation5/13/20205/19/20205/19/2020PPART
DetailsTell Riley
Mark pour time at 1:30 Phone #: ###-####//WIP//
BLD-Footing5/12/20205/13/20205/13/2020PPART
DetailsTell Riley
Screened-pour time is at 2pm-Mark Phone #: ###-####//talked with Sue at zoning, verified minumum setback is 20 feet from front pin to garage//setbacks per plans, and minimum per zoning in front//need to delete rebar note from plans as general does not want it installed//
Issue PAID IN FULL permit  5/7/2020 DONE
Inspection Record Card- Bld  5/7/2020 DONE
OVERRIDE  3/6/2020  
Plan assigned to (RDP)3/2/20203/2/20203/6/2020 DONE
DetailsRob Patrick
3/13 sfd L1 ePlan
Routing - PLAN CHECK3/2/2020 3/6/2020 PASS
DetailsRob Patrick
Routing - PLANNING3/2/2020 3/6/2020 PASS
DetailsSue Cummings
1st review completed  3/6/2020 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  3/6/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  3/6/2020 DONE
met
Route to Impact Fee Review3/2/20203/5/20203/3/2020 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - Addressing3/2/2020 3/2/2020 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/2/2020 3/2/2020 PASS
DetailsMorgan Webb
Routing - MECHANICAL3/2/2020 3/2/2020 PASS
DetailsTroy James
Intake Approval  3/2/2020 PASS
Application received  2/29/2020 DONE
Application submitted via PDS Online on Feb 29 2020 10:55AM