Miscellaneous action | | | 5/15/2015 | | DONE |
|
|
|
Tom Gainor and Jason Blais requested an update on when the contractor would be complete. I emailed the contractor with a request for an update.
|
INSP-Alarm Testing | 8/31/2014 | 9/3/2014 | 9/3/2014 | A | NR |
Forrest France
|
|
|
Completed initial project walkthrough. Items noted include; adjust notification at locations marked on plans at the 3rd, 2nd and 1st floors, (cd settings, spacing, height AFF), provide WP device at a 2nd floor bathroom, relocate a/v at the 2nd floor TV room, provide SD at the 2nd floor NAC, monitor sprinkler tamper at the 1st floor elevator control, relocate a/v at the kitchen exit access, post signage at the door to the FACP room, provide lock at circut breaker, post points map per review comments, provide documents cabinet. Provide plan modification for resubmittal to reflect field changes such as deleted ID's, door mag relays, elevator hat, changed room uses, added 1st floor vestibule, new ceiling mount devices in place of wall mount, - include IP DACT in place of phone lines. Remove all non-functional devices and system components from the previous panel including MP, SD, HD, power supplies, etc. prior to final.
|
INSP-Alarm Testing | 8/26/2014 | 8/26/2014 | 8/29/2014 | P | DEFR |
Forrest France
|
|
|
Phone #: ###-#### Inspection requested via web by Keith Olstrom
|
INSP-Alarm Testing | 8/14/2014 | 8/20/2014 | 8/19/2014 | P | DEFR |
Forrest France
|
|
|
Rescheduled for next week per conversation with contractor.
|
INSP-Conference | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | DONE |
Forrest France
|
|
|
Regarding project inspection and testing schedule.
|
Miscellaneous action | | | 7/16/2014 | | DONE |
|
|
|
Stephanie Cobbley emailed to let me know she had been informed that the detector bases have independant bases form the smoke detectors. She wanted to know if there was an additional charge for the addresses and could she note them on as built drawings. I informed her that I felt the bases were part of the detector assembly so no additional charge and that as built documentation was adequate. She also stated that due to other changes, she will be submitting a plan modification in the near future.
|
Permit Ready to Issue | | | 6/17/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 6/17/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 6/17/2014 | | 6/17/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 6/16/2014 | | 6/16/2014 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 6/16/2014 | | DONE |
|
|
|
Emailed Stephanie for use clarification on Isolation Room 128. She responded stating the room is now an office so notification and detection are not required.
|
1st review completed | | | 6/16/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 6/16/2014 | | 6/16/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/16/2014 | | DONE |
|
|
|
Plans approved with review comments.
|
Application received | | | 6/13/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 13 2014 10:47AM
|
FIR-Aging Inspection | 8/5/2020 | 8/5/2020 | | | |
Jim Page
|
|
|
|