INSP-Final Inspection | 8/26/2019 | 8/28/2019 | 8/28/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Meeting | | | 8/28/2019 | | DONE |
|
|
|
permit was pulled under the wrong address okay to change per Tisha to the correct
|
INSP-Final Inspection | 8/5/2019 | 8/9/2019 | 8/9/2019 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, will be rescheduled for a later date.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler above drop down ceilings complete, approved for cover.
Austin Farnworth is the contact. There is another inspection for Skyline Bldg C for this date and time and the contact would like them to take place at the same time. He would also prefer sooner in the morning for both inspections, and for a call detailing the estimated time of the inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Gerardo Arce is the contact. He wants a hydro only inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/12/2019 | 3/13/2019 | 3/13/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/15/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jim Page
|
|
|
Install does not match city approved drawings. Adjust hangers in areas that are overspaced.
Gerardo Arce is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan resubmittals received | | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/9/2018 | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/9/2018 | | 11/9/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/9/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/7/2018 | | 11/7/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/7/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/7/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 11/6/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/6/2018 | | 11/6/2018 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 31 2018 7:52AM
|