Permit Information
Permit NumberGRD18-00064
StatusFinaled
Name PETRA INC
Site Address 12251 W FRANKLIN RD
Project Name 
Customer NumberDRH18-00204
ePlanReviewYes
Description
(CJD INVESTMENTS) - Grading permit to excavate, grade and compact site earth materials in preparation for a new shell building to be constructed under BLD18-02795. All work to be performed as approved by the Public Works Department and Planning & Zoning Department under DRH18-00204. Separate electrical and plumbing permits are required for site underground utilities. No buildings or footings are allowed to be constructed under this permit. (C_P)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection6/19/20196/19/20196/19/2019PPASS
DetailsTroy Cobbley
Life safety passed. Modified fire dept access has been re-submitted under the BLD permit.

Frankie Phone #: ###-####
GRD-Final6/11/20196/11/20196/11/2019PDONE
DetailsTiffany Lowery
PubWorks Occupancy Approval6/11/20196/11/20196/11/2019 DONE
DetailsTiffany Lowery
FIRE-Final Inspection6/7/20196/7/20196/7/2019PFAIL
DetailsTroy Cobbley
Provide "No Parking Zone" at space i front of the north fire hydrant, Provide fire dept/plan review approval for modified fire dept access road.
Inspection Record Card-GRD  6/7/2019 DONE
Issue PAID IN FULL permit  9/18/2018 DONE
Permit Ready to Issue  9/14/2018 DONE
Need
RP
Revised Cert of Value
Routing - FIRE9/10/20189/10/20189/13/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - FRONT DESK9/10/2018 9/13/2018 PASS
DetailsChristina Prado
Routing - PUBLIC WORKS9/13/2018 9/13/2018 PASS
DetailsBrian Murphy
Routing PW Drainage9/13/2018 9/13/2018 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  9/13/2018 DONE
Plan assigned to Christina8/6/2018 9/13/2018 DONE
DetailsChristina Prado
Routing PW Sewer Design9/10/2018 9/12/2018 PASS
DetailsDeAnn Brown
Routing - Design Review9/10/2018 9/10/2018 PASS
DetailsAndrea Tuning
Routing - FIRE8/6/20188/6/20188/17/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
1st review completed  8/17/2018 DONE
DetailsChristina Prado
Fail - pending approval from all departments
Routing - FRONT DESK8/6/2018 8/17/2018 FAIL
DetailsChristina Prado
pending full approval from all departments
Routing - Design Review8/6/2018 8/17/2018 FAIL
DetailsAndrea Tuning
The applicant is required to provide a copy of a recorded cross access agreement.

All compact parking spaces shall clearly be identified.

An additional interior planter island is required on the west side of the building as there are now more than 10 spaces in a row without an interior planter island that includes a Class II tree to break up the asphalt.

Light poles shall be required to be located outside of the required setbacks.
Routing - PLANNING8/6/2018 8/17/2018 CANC
DetailsChristina Prado
See DR review disposition from ANT, no Current Planning review required
Routing PW Sewer Design8/6/2018 8/10/2018 FAIL
DetailsDeAnn Brown
Please show and label the existing 3" pressure sewer pipeline that crosses east/west through the parking lot to connection manhole on sheet C-5 for Contractor info. This pipeline passes where the new 6" fire water line enters the site. I can provide record drawings. (drbrown@cityofboise.org)
Routing PW Solid Waste8/6/2018 8/7/2018 PASS
DetailsEvan Carpenter
Routing PW Drainage8/6/2018 8/7/2018 FAIL
DetailsBrian Murphy
NEEDS PERC TEST
Routing PW Street Lights8/6/2018 8/6/2018 PASS
DetailsTom Marshall
Plans ACCEPTED BY PLAN TECH  8/6/2018 DONE
Intake Approval  8/6/2018 PASS
Recd Pcfee & Taken To Pln CK  8/6/2018 DONE
Routing - Addressing8/6/2018 8/6/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/6/2018 8/6/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment8/6/2018 8/6/2018 PASS
DetailsMichael Zawacki
RP needed prior to ground disturbances.
Site prep inspection required.
Routing - PLUMBING8/6/2018 8/6/2018 PASS
DetailsBill VanDegrift
per plans and ISPC
Application received  8/3/2018 DONE
Application submitted via PDS Online on Aug 3 2018 11:24AM
Routing PW Drainage9/10/2018   FAIL
DetailsBrian Murphy
NEED PERC TEST