Permit Information
Permit NumberBLD16-04253
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 6051 W EMERALD ST
Project NameSAMG Emerald Clinic
Customer Number 
ePlanReviewYes
Description
(SAINT ALPHONSUS MEDICAL GROUP – EMERALD MEDICAL CLINIC) (DRH16-00325) The fire sprinkler system is used for code trade-offs including allowing a non-rated corridor and for fire flow. To construct a 12,803 square foot medical office building (outpatient clinic) and to finish it for occupancy. Work is to include concrete footings, concrete stem walls, concrete piers, concrete slab on grade, steel bearings studs, light gauge steel headers, steel stud shear walls with wood structural panels and hold-downs, steel stud nonbearing walls, steel stud exterior walls with drainable exterior insulation and finish system (EIFS), adhered stone masonry exterior veneer, exterior windows, permanent metal shade awnings at exterior windows, steel roof beams, steel columns, open web steel roof joists, steel pan deck roof diaphragm, foam plastic insulation installed on top of the steel roof deck, TPO roofing membrane, 6 restrooms accessible to the disabled, interior doors, millwork, and finishes. Special Inspection is required for soils, concrete, steel, bolting, welding, and possibly EIFS. The design for the open web steel roof joists is a deferred submittal item. The work is required to comply with the approved drawings, with the approved structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. The installation and use of X-ray equipment, including shielding, is required to comply with all applicable Industry, State, and Federal regulations. All equipment shall be listed and labeled per the adopted Electrical Code with approval from the PDS Electrical Inspection Team. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/201710/31/201710/31/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok for temp occ. Will be ok for perm oc. once electrical signs off.
FIRE-Final Inspection10/30/201710/31/201710/31/2017APASS
DetailsTroy Cobbley
Life safety passed. Contractor provided documentation that the thumbturn deadbolt hardware met ADA
FIRE-Final Inspection10/24/201710/25/201710/25/2017PFAIL
DetailsTroy Cobbley
Need the project related fire sprinkler and fire alarm permits finaled. Only item for life safety inspected today was the exit signs and emergency lights. I noted two lights that are non-functional.
BLD-Final10/24/201710/25/201710/25/2017PNR
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Darius Saxton needs fire and mec finals
FIRE-Final Inspection10/24/201710/24/201710/24/2017PCANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
BLD-Final10/24/201710/24/201710/24/2017PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
BLD-Conference10/20/201710/23/201710/23/2017PDONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Ceiling Grid Inspection10/5/201710/6/201710/6/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Ceiling Grid Inspection10/5/201710/5/201710/5/2017AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Noted several areas were clips are missing.
BLD-Energy code compliance8/21/20178/21/20178/21/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of north west portion of soffits at main entry ok.
BLD-Wall cover8/15/20178/16/20178/16/2017APASS
DetailsMike Jordan
Two interior sheer walls for cover. Early as possible. Thanks Phone #: ###-#### Inspection requested via web by Darius Saxton. interior shear walls on east side of building ok.
BLD-Energy code compliance8/10/20178/10/20178/10/2017PPART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Work in progress on completing the soffit areas north west portion of building.
BLD-Energy code compliance8/2/20178/3/20178/3/2017APASS
DetailsMike Jordan
Early if possible Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Energy code compliance7/28/20177/31/20177/31/2017ANR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Framing/Rough-in7/31/20177/31/20177/31/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of interior steel stud framed walls at south west portion of building.
BLD-Energy code compliance7/27/20177/28/20177/28/2017APART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Darius Saxton north ext wall ok to cover
BLD-Energy code compliance7/27/20177/27/20177/27/2017PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
BLD-Energy code compliance7/26/20177/26/20177/26/2017PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
BLD-Framing/Rough-in7/20/20177/24/20177/24/2017PPART
DetailsMike Jordan
If you have any questions, Andrew will be onsite. His number is ###-#### Phone #: ###-#### Inspection requested via web by Darius Saxton. Pending plumbing rough in inspection.
BLD-Framing/Rough-in7/17/20177/17/20177/17/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Interior steel stud framed walls ok on north half of building.
BLD-Wall cover7/13/20177/14/20177/14/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. All exterior shear walls ok to cover.
BLD-Framing/Rough-in7/14/20177/14/20177/14/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. exterior soffits and column wraps ok.
BLD-Wall cover7/7/20177/10/20177/10/2017APART
DetailsMike Jordan
Around 10 a.m. if possible Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior shear walls, noted some areas that reaquire additional fasteners.
BLD-Energy code compliance7/6/20177/7/20177/7/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Portion of exterior south east wall only.
BLD-Framing/Rough-in6/6/20176/6/20176/6/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior steel stud framed walls.
BLD-Framing/Rough-in6/5/20176/5/20176/5/2017PPART
DetailsMike Jordan
Exterior wall inspection Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Concrete5/5/20175/8/20175/8/2017ADEFR
DetailsMike Jordan
60 yard slab pour. MTI scheduled to test concrete and to inspect wire mesh and vapor barrier. Concrete at 5 am. Phone #: ###-#### Inspection requested via web by Darius Saxton. special inspector on site.
BLD-Foundation4/27/20174/28/20174/28/2017APASS
DetailsMike Jordan
As close to noon if possible. MTI scheduled for rebar and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Footing4/25/20174/25/20174/25/2017PPASS
DetailsMike Jordan
Rebar on trash enclosure. 2 pm if possible. Concrete at 3 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Footing4/24/20174/24/20174/24/2017PPART
DetailsJim Sly
Darius Saxton Anderson.
North East corner OK pending MTI special inspection, tests and approval.
BLD-Footing4/21/20174/24/20174/24/2017APASS
DetailsJim Sly
Around 11 if possible or late morning. MTI is scheduled for 11 and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
Septic appears to be full (grout, per Eng.) OK to pour footing.
BLD-Foundation4/12/20174/14/20174/14/2017ADEFR
DetailsMike Jordan
Stem walls with rebar. Concrete pour at 1 p.m. Phone #: ###-#### Inspection requested via web by Darius Saxton. Pend. special inspection.
BLD-Footing4/4/20174/5/20174/5/2017APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Nathan Shute. East and south footings. Partial footings on west and north ends. Needs to install corner bars. Will have special inspection.