BLD-Final | 10/30/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok for temp occ. Will be ok for perm oc. once electrical signs off.
|
FIRE-Final Inspection | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor provided documentation that the thumbturn deadbolt hardware met ADA
|
FIRE-Final Inspection | 10/24/2017 | 10/25/2017 | 10/25/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler and fire alarm permits finaled. Only item for life safety inspected today was the exit signs and emergency lights. I noted two lights that are non-functional.
|
BLD-Final | 10/24/2017 | 10/25/2017 | 10/25/2017 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton needs fire and mec finals
|
FIRE-Final Inspection | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Final | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Conference | 10/20/2017 | 10/23/2017 | 10/23/2017 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Ceiling Grid Inspection | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Ceiling Grid Inspection | 10/5/2017 | 10/5/2017 | 10/5/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Noted several areas were clips are missing.
|
BLD-Energy code compliance | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of north west portion of soffits at main entry ok.
|
BLD-Wall cover | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Mike Jordan
|
|
|
Two interior sheer walls for cover. Early as possible. Thanks Phone #: ###-#### Inspection requested via web by Darius Saxton. interior shear walls on east side of building ok.
|
BLD-Energy code compliance | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Work in progress on completing the soffit areas north west portion of building.
|
BLD-Energy code compliance | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PASS |
Mike Jordan
|
|
|
Early if possible Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Energy code compliance | 7/28/2017 | 7/31/2017 | 7/31/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Framing/Rough-in | 7/31/2017 | 7/31/2017 | 7/31/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Remainder of interior steel stud framed walls at south west portion of building.
|
BLD-Energy code compliance | 7/27/2017 | 7/28/2017 | 7/28/2017 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton north ext wall ok to cover
|
BLD-Energy code compliance | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Energy code compliance | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
BLD-Framing/Rough-in | 7/20/2017 | 7/24/2017 | 7/24/2017 | P | PART |
Mike Jordan
|
|
|
If you have any questions, Andrew will be onsite. His number is ###-#### Phone #: ###-#### Inspection requested via web by Darius Saxton. Pending plumbing rough in inspection.
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Interior steel stud framed walls ok on north half of building.
|
BLD-Wall cover | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. All exterior shear walls ok to cover.
|
BLD-Framing/Rough-in | 7/14/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. exterior soffits and column wraps ok.
|
BLD-Wall cover | 7/7/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Mike Jordan
|
|
|
Around 10 a.m. if possible Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior shear walls, noted some areas that reaquire additional fasteners.
|
BLD-Energy code compliance | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Portion of exterior south east wall only.
|
BLD-Framing/Rough-in | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Exterior steel stud framed walls.
|
BLD-Framing/Rough-in | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PART |
Mike Jordan
|
|
|
Exterior wall inspection Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Concrete | 5/5/2017 | 5/8/2017 | 5/8/2017 | A | DEFR |
Mike Jordan
|
|
|
60 yard slab pour. MTI scheduled to test concrete and to inspect wire mesh and vapor barrier. Concrete at 5 am. Phone #: ###-#### Inspection requested via web by Darius Saxton. special inspector on site.
|
BLD-Foundation | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Mike Jordan
|
|
|
As close to noon if possible. MTI scheduled for rebar and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Footing | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | PASS |
Mike Jordan
|
|
|
Rebar on trash enclosure. 2 pm if possible. Concrete at 3 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Footing | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | PART |
Jim Sly
|
|
|
Darius Saxton Anderson. North East corner OK pending MTI special inspection, tests and approval.
|
BLD-Footing | 4/21/2017 | 4/24/2017 | 4/24/2017 | A | PASS |
Jim Sly
|
|
|
Around 11 if possible or late morning. MTI is scheduled for 11 and concrete at 2 pm. Phone #: ###-#### Inspection requested via web by Darius Saxton Septic appears to be full (grout, per Eng.) OK to pour footing.
|
BLD-Foundation | 4/12/2017 | 4/14/2017 | 4/14/2017 | A | DEFR |
Mike Jordan
|
|
|
Stem walls with rebar. Concrete pour at 1 p.m. Phone #: ###-#### Inspection requested via web by Darius Saxton. Pend. special inspection.
|
BLD-Footing | 4/4/2017 | 4/5/2017 | 4/5/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nathan Shute. East and south footings. Partial footings on west and north ends. Needs to install corner bars. Will have special inspection.
|