BLD-Final | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Ok for temp. occ. Will be ok for perm occ. once zoning/public works and electrical signs perm.
|
FIRE-Final Inspection | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Mike Phone #: ###-####
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to sign off when the project fire alarm and fire sprinkler permits are finaled
MIke Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | DONE |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Contractor provided documentation for wood ceiling smoke and flame spread values. Currently, this will not meet a lass C rating. Documentation provided for and intumescent fire retatrdent varnish to meet ASTM E-84. Falme Control No.166 wil be used to coat the wood ceiling.
|
BLD-Ceiling Grid Inspection | 11/20/2017 | 11/21/2017 | 11/21/2017 | P | PASS |
Mike Jordan
|
|
|
###-####- Mike.
|
BLD-Energy code compliance | 10/13/2017 | 10/16/2017 | 10/16/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Energy complete. ok to cover.
|
BLD-Energy code compliance | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. South and east exterior walls ok.
|
BLD-Framing/Rough-in | 10/9/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Wood framed walls and hardlids for restroom ok.
|
BLD-Framing/Rough-in | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Main entry and bar area.
|
BLD-Energy code compliance | 10/6/2017 | 10/6/2017 | 10/6/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. West exterior wall.
|
BLD-Framing/Rough-in | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Double top plate splice and additional studs added in overbuild. Trusses, lateral bracing and additional bracing on botom chords, all related hardware and bracing ok.
|
BLD-Wall Bracing | 9/29/2017 | 9/29/2017 | 9/29/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. North exterior shear wall ok.
|
BLD-Framing/Rough-in | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Exterior furred walls ok.
|
BLD-Wall Bracing | 9/18/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. South, east and west exterior shear walls ok.
|
BLD-Framing/Rough-in | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Remainder of overbuild. Needs to provide strap and double top plate splice and provide 2 additional studs under double LVL.
|
FIRE-Conference | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | DONE |
Troy Cobbley
|
|
|
Mike and I discussed combustible concealed spaces.
Phone #: ###-####
|
BLD-Framing/Rough-in | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Roof diaphragm nailing ok. Parapet and over builds ok.
|
BLD-Foundation | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Mike Jordan
|
|
|
Pour at 11 /// Mike Phone #: ###-####. CMU pilasters for hip roof ok.
|
BLD-Foundation | 7/14/2017 | 7/17/2017 | 7/17/2017 | A | PART |
Mike Jordan
|
|
|
Pour 11 // Mike Phone #: ###-####. Work in progress on cmu stemwall, permiter walls from top of footing to finish floor. Will have special inspection.
|
BLD-Footing | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PART |
Brandon Shaw
|
|
|
Building foot print and columns, garbage /recyling bin area at later time
|