Permit Information
Permit NumberBLD17-03833
StatusFinaled
Name STANDER CONSTRUCTION COMPANY
Site Address 7672 W FAIRVIEW AVE
Project NameFly High Trampoline Park
Customer Number 
ePlanReviewYes
Description
(FLY HIGH TRAMPOLINE PARK) **This building is fully fire sprinklered to allow for area increase. Permit to remodel an existing 22,476 sq ft retail tenant space for a new fitness trampoline park. Work to include demo of interior non-structural partitions; new interior non-bearing walls; new elevated walkway platforms connecting trampoline areas; new mezzanine; new plumbing, electrical, and mechanical work; and new interior finishes in compliance with Ch. 8 of the 2012 IBC. Special inspections required per attached Form 310. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/23/20191/24/20191/24/2019APASS
DetailsJim Sly
Clive Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection1/14/20191/14/20191/14/2019PPASS
DetailsTroy Cobbley
life safety passed. Panic hardware has been provided on the south east door and the southwest door hardware has been removed.
BLD-Final12/21/201812/21/201812/21/2018PCANC
DetailsJim Sly
BLD-Final11/16/201811/19/201811/19/2018APART
DetailsJim Sly
Carson Phone #: ###-####
OK for Temp Occ. OK for Perm Occ. when Elevator to mezzanine installed, .......CDHD, and Fire signs off Perm. Zoning and Public Works N/A.
FIRE-Final Inspection11/16/201811/19/201811/19/2018APART
DetailsTroy Cobbley
The temporary has been extended to the 30th of this month so that the panic hardware can get installed and the other hardware removed.

Carson Phone #: ###-####
BLD-Final11/16/201811/16/201811/16/2018PPART
DetailsJim Sly
OK for Temp Occ. OK for Perm Occ. when..........Fire, CDHD and Zoning signs off Perm Occ. Public Works N/A
FIRE-Final Inspection11/16/201811/16/201811/16/2018PPART
DetailsTroy Cobbley
A temporary until Monday is ok so that panic hardware can be installed on the front/east side doors. Hardware to be removed from the front/west side doors. Building inspector and I discussed this as well as plan review (Carl). All other life safety items, fire sprinkler and fire alarm are passed.

Carson Phone #: ###-####
FIRE-Final Inspection11/2/201811/5/201811/5/2018AFAIL
DetailsTroy Cobbley
Not ready for final. Todays final was for approval for cover of the platform. It appears to have been completely filled with insulation and is ok for cover.


Clive Phone #: ###-####
FIRE-Final Inspection10/31/201811/1/201811/1/2018AFAIL
DetailsTroy Cobbley
Not ready for final yet. The project related fire alarm and fire sprinkler permits need addressed and the non-combustible insulation filling the raised platform needs to be completed and inspected.

Clive Phone #: ###-####
BLD-Framing/Rough-in10/17/201810/17/201810/17/2018PPASS
DetailsJim Sly
Clive Phone #: ###-####
Platforms Ramp, Stairs.
FIRE-Conference6/26/20186/27/20186/27/2018ADONE
DetailsTroy Cobbley
We discussed the placement of the emergency lights.

Junior Phone #: ###-####
BLD-Framing/Rough-in6/20/20186/21/20186/21/2018APASS
DetailsJim Sly
Clive Phone #: ###-####
BLD-Framing/Rough-in6/4/20186/5/20186/5/2018APASS
DetailsJim Sly
Clive---around 10 am or after would be best Phone #: ###-####
BLD-Conference5/18/20185/18/20185/18/2018PDONE
DetailsTroy Cobbley
We went over sprinkler protection under the raised platforms (I deferred them to a sprinkler contractor for guidance and showed NFPA 13 code references), We went over fire alarm requirements which appear to require full notification due to an A3 occupancy with two A3 occupant loads of 321 and 81. We also discussed having the plans match the actual field conditions ( doors are shown on the plans that they want to delete). Also there is an ageing permit for sprinkler work that has never been inspected for this space that will need to be finaled prior to a final for this tenant.


Clive- need a conference on fire issues Phone #: ###-####
FIRE-Final Inspection4/17/20184/17/20184/17/2018PFAIL
DetailsTroy Cobbley
Project is not ready for a final. Todays inspection was a conference with the electrician about the placement of exit signs and emergency lights. There were no approved plans on site so there was not much I could do. I met with one of the owners and let him know that I would not be signing off untill the aging permit FIR12-004


74 was finaled.


Dale Campbell Jr. Phone #: ###-####
BLD-Footing3/2/20183/5/20183/5/2018APASS
DetailsJim Sly
interior footings - Clive Phone #: ###-####
BLD-Footing3/1/20183/2/20183/2/2018PPASS
DetailsJim Sly
Cliv or JR Phone #: ###-####