BLD-Final | 2/15/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Jim Storey
|
|
|
Tim-please call 30 minutes prior to meet for access Phone #: ###-####
|
FIRE-Final Inspection | 2/15/2018 | 2/16/2018 | 2/16/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tim-please call 30 minutes prior to meet for access Phone #: ###-####
|
BLD-Final | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PART |
Mike Jordan
|
|
|
Tim Phone #: ###-####. OK for temp occ.
|
FIRE-Final Inspection | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scotts approval until the doors/hardware have been installed and verified.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scotts approval until the doors/hardware have been installed and verified.
Call half hour before to meet // Tim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | PASS |
Mike Jordan
|
|
|
Call half hour before to meet // Tim Phone #: ###-####
|
FIRE-Final Inspection | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | CANC |
Troy Cobbley
|
|
|
To be re-scheduled per Tim
Please call 30 min ahead for access - Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Mike Jordan
|
|
|
Call half hour before to meet // Tim Phone #: ###-####. Interior steel stud framed walls ok.
|