BLD-Final | 9/13/2018 | 9/14/2018 | 9/13/2018 | A | PASS |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. Ok for perm oc.
|
FIRE-Final Inspection | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Mike Jordan
|
|
|
Chuck Phone #: ###-####. Fire/life/safety was passed on 8-20-18 by Jim Page.
|
BLD-Final | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PEND |
Mike Jordan
|
|
|
Byron Phone #: ###-####. Pending plumbing final.
|
FIRE-Final Inspection | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed on 8/20/18
Byron Phone #: ###-####
|
FIRE-Final Inspection | 8/17/2018 | 8/20/2018 | 8/20/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers will be placed in discussed locations. Final life fire safety inspection for area of work complete.
Dustin Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Mike Jordan
|
|
|
Byron Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | NR |
Mike Jordan
|
|
|
Byron Phone #: ###-####. Needs mech and fire sprinkler rough in inspections. Also needs to install perimeter clips.
|
BLD-Framing/Rough-in | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | PART |
Jim Sly
|
|
|
Brian Phone #: ###-#### East/ West full height wall....approx 35 feet from South end of building.....OK
|
FIRE-Conference | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | DONE |
Troy Cobbley
|
|
|
I spoke with the project superintendant about the drawing sheet E4 that shows a fire alarm notification device and a manual pull station.
|
BLD-Framing/Rough-in | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Mike Jordan
|
|
|
Byron Phone #: 208-###-####. Interior steel stud framed wall, north side only.
|
BLD-Other | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Mike Jordan
|
|
|
Allen- structural steel bolt connection Phone #: ###-####
|
BLD-Footing | 5/4/2018 | 5/7/2018 | 5/7/2018 | A | PEND |
Mike Jordan
|
|
|
Byron Phone #: ###-####. INterior column pad footings. Noted city approved plans have been redlined to show (4) #4 rebar at 10 in. oc. each way. In place work has #5 bar, 3 each way per the orginal schedule. Contractor to replace as per city approved plan, or engineer of record to provide new calcs and letter showing existing work is ok.
|