Permit Information
Permit NumberBLD18-01753
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 1005 W MAIN ST
Project NameKount
Customer Number 
ePlanReviewYes
Description
(KOUNT) ""PLAN MODIFICATION FOR MODIFICATIONS TO THE HVAC SYSTEM WITH THE ADDITION OF SOME FIRE/SMOKE DAMPERS""" Permit for tenant improvements to an existing 5 story building with work to include the build-out of the interior tenant spaces. The 2nd through the 5th stories are to be occupied by a single tenant. The 5th story is a first time T.I as the story was added under a previous permit. This permit will establish occupancy for the main entry lobby, and the 2nd through 5th floors with separate building permits required for add any new basement and 1st story tenants. The cable guardrails will be a deferred submittal. This building is fully fire sprinklered to eliminate corridor requirements. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/23/20194/23/20194/23/2019PPASS
DetailsDave Hannah
Call before you head to project. I am working in Nampa and will take at least 20 minutes to get downtown. Call me after lunch Phone #: ###-#### Inspection requested via web by Tom Hayes
FIRE-Final Inspection4/23/20194/23/20194/23/2019PPASS
DetailsJim Page
Associated inspections for FIR permits attached to this project have been completed to include approval of as-builts. Final life fire safety inspection for area of work complete.

BLD-Final4/4/20194/4/20194/5/2019PNR
DetailsDave Hannah
call ahead // Tom Phone #: ###-#### needs other trades to go perm occ
BLD-Final3/6/20193/7/20193/7/2019APASS
DetailsDave Hannah
Temp C of O only. Plans still in review for plan review // Tom Phone #: ###-#### ok for tec
FIRE-Final Inspection3/6/20193/7/20193/6/2019APART
DetailsJim Page
Final inspection for life fire safety inspection complete, TCO authorized for 30 days per conversation with Ron Johnson with the contingent of the fire alarm and fire sprinkler as-builts being submitted and approved. Once FIR permit as-builts are submitted, approved and the inspection status is finaled then life fire safety can be scheduled and completed.

temp Phone #: ###-####
BLD-Final2/28/20193/1/20193/1/2019PNR
DetailsBrandon Shaw
See previous entry.
Permit shows being under review at time of this request, no inspection was performed.
Fire alarms and fire sprinkler did not pass inspection.
FIRE-Final Inspection2/28/20193/1/20193/1/2019AFAIL
DetailsJim Page
Permit shows being under review at time of this request, no inspection was performed.
Fire alarms and fire sprinkler did not pass inspection.
Tom Phone #: ###-####
BLD-Ceiling Grid Inspection1/30/20191/30/20191/30/2019APASS
DetailsDave Hannah
Grids on 2nd and 5th floors Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Ceiling Grid Inspection1/23/20191/24/20191/24/2019AFAIL
DetailsJim Storey
Grid inspection, 5th and 2nd floors Phone #: ###-#### Inspection requested via web by Tom Hayes fire stop stair and elavator penatrations/ patch fire prooffing 5 floor// support mains with in 6 inches of ends of mains.
BLD-Ceiling Grid Inspection1/11/20191/14/20191/14/2019APASS
DetailsDave Hannah
4th floor ceiling grid Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Ceiling Grid Inspection1/2/20191/3/20191/3/2019APASS
DetailsDave Hannah
3rd floor grid inspection for boarder install Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Ceiling Grid Inspection12/26/201812/27/201812/27/2018ANR
DetailsDave Hannah
above ceiling for ceiling tile cover inspections Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Wall cover11/13/201811/14/201811/14/2018APASS
DetailsDave Hannah
Fire caulking at elevator door fronts before cover for 2 hour wall assembly Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Wall cover10/9/201810/10/201810/10/2018APASS
DetailsDave Hannah
Wall cover for 2nd and 5th floors Phone #: ###-#### Inspection requested via web by Tom Hayes
BLD-Framing/Rough-in9/10/20189/11/20189/11/2018PPASS
DetailsDave Hannah
Wall framing-- interior walls 2nd floor thru 4th floor
afternoon is fine, meeting in the morning and won''t be available
thanks
Tom Phone #: ###-#### Inspection requested via web by Tom Hayes