BLD-Final | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Dave Hannah
|
|
|
Call before you head to project. I am working in Nampa and will take at least 20 minutes to get downtown. Call me after lunch Phone #: ###-#### Inspection requested via web by Tom Hayes
|
FIRE-Final Inspection | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Page
|
|
|
Associated inspections for FIR permits attached to this project have been completed to include approval of as-builts. Final life fire safety inspection for area of work complete.
|
BLD-Final | 4/4/2019 | 4/4/2019 | 4/5/2019 | P | NR |
Dave Hannah
|
|
|
call ahead // Tom Phone #: ###-#### needs other trades to go perm occ
|
BLD-Final | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Dave Hannah
|
|
|
Temp C of O only. Plans still in review for plan review // Tom Phone #: ###-#### ok for tec
|
FIRE-Final Inspection | 3/6/2019 | 3/7/2019 | 3/6/2019 | A | PART |
Jim Page
|
|
|
Final inspection for life fire safety inspection complete, TCO authorized for 30 days per conversation with Ron Johnson with the contingent of the fire alarm and fire sprinkler as-builts being submitted and approved. Once FIR permit as-builts are submitted, approved and the inspection status is finaled then life fire safety can be scheduled and completed.
temp Phone #: ###-####
|
BLD-Final | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | NR |
Brandon Shaw
|
|
|
See previous entry. Permit shows being under review at time of this request, no inspection was performed. Fire alarms and fire sprinkler did not pass inspection.
|
FIRE-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | FAIL |
Jim Page
|
|
|
Permit shows being under review at time of this request, no inspection was performed. Fire alarms and fire sprinkler did not pass inspection. Tom Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/30/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Dave Hannah
|
|
|
Grids on 2nd and 5th floors Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Ceiling Grid Inspection | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | FAIL |
Jim Storey
|
|
|
Grid inspection, 5th and 2nd floors Phone #: ###-#### Inspection requested via web by Tom Hayes fire stop stair and elavator penatrations/ patch fire prooffing 5 floor// support mains with in 6 inches of ends of mains.
|
BLD-Ceiling Grid Inspection | 1/11/2019 | 1/14/2019 | 1/14/2019 | A | PASS |
Dave Hannah
|
|
|
4th floor ceiling grid Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Ceiling Grid Inspection | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PASS |
Dave Hannah
|
|
|
3rd floor grid inspection for boarder install Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Ceiling Grid Inspection | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | NR |
Dave Hannah
|
|
|
above ceiling for ceiling tile cover inspections Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Wall cover | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Dave Hannah
|
|
|
Fire caulking at elevator door fronts before cover for 2 hour wall assembly Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Wall cover | 10/9/2018 | 10/10/2018 | 10/10/2018 | A | PASS |
Dave Hannah
|
|
|
Wall cover for 2nd and 5th floors Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Framing/Rough-in | 9/10/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Dave Hannah
|
|
|
Wall framing-- interior walls 2nd floor thru 4th floor afternoon is fine, meeting in the morning and won''t be available thanks Tom Phone #: ###-#### Inspection requested via web by Tom Hayes
|