BLD-Final | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Tony Young
|
|
|
Hi Tony. Requesting a final as we discussed earlier. If you do need to come out I will need to reschedule, but just let me know. Thank you! Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
DOC - Permit Finaled | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/14/2019 | 7/15/2019 | 7/15/2019 | A | PEND |
Dave Hannah
|
|
|
Please give me 30 minutes or so notice so I can meet you there. Thanks.
Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole ok for final after final letter for cable gaurd rail.
|
BLD-Aging Inspection | 5/1/2019 | 5/1/2019 | 5/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/30/2019 | 4/30/2019 | 5/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Other | 4/18/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Brandon Shaw
|
|
|
Inspection of Sheet rock in soffit prior to installing fire rated cedar. If this inspection is not needed, please just let me know. Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
BLD-Framing/Rough-in | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Dave Hannah
|
|
|
We are working on it today, please make this last of the day if possible. Upstairs will be done by noon with garage in the afternoon. Thanks Tony. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
BLD-Wall Bracing | 12/13/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Tony Young
|
|
|
Please call Steve at ###-#### with a little notice so that he can meet you on the job for the inspection. He should be there all day anyway. I''d like for you to look at the upstairs for framing rough in as well if possible. Thank you Tony. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
BLD-Conference | 11/30/2018 | 12/4/2018 | 12/4/2018 | A | PART |
Tony Young
|
|
|
Jay Phone #: ###-####,, new contractor taking over job,, walk through,, I recommended having the structural engineer walk the job to verify and/or give fixes of any issues
|
BLD-Foundation | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, new added to existing point load footings on front,, 5 total
|