Permit NumberBLD18-03684
StatusFinaled
Name NNI CONSTRUCTION CO
Site Address 1123 N MILWAUKEE ST
Project NamePlanet Fitness - Milwaukee
Customer Number 
ePlanReviewYes
Description
(MILWAUKEE MARKETPLACE) (PLANET FITNESS) (CZC18-00259) // 2-28-19 PLAN MOD FOR REVISIONS TO THE RTU WEIGHTS AND STRUCTURAL CALCS. JAR // Permit for tenant improvements to an existing 30,183 sq ft retail space within the existing Milwaukee Marketplace for a new fitness center. The building was previously a retail store occupied by Taipan Trading under BLD12-00850 and by Borders Books and Music under BLD95-00294. Work to include: demo of interior non-structural partitions; minor exterior improvements; new interior non-bearing walls; exterior doors; restrooms and locker rooms with new plumbing; lighting and power; mechanical including roof top units and structural roof reinforcement; and interior finishes in compliance with Ch. 8 of the 2015 IBC. Special inspections required per attached Form 310. The fire sprinkler system is used for building area increase and for fire area. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/6/20195/7/20195/7/2019APASS
DetailsMike Jordan
Brian Phone #: ###-####. Ok for trmp occ. All issues resolved. Will be ok for perm occ. once plumbing signs perm.
BLD-Final5/3/20195/6/20195/6/2019PPART
DetailsMike Jordan
Brian Phone #: ###-####. Ok for temp occ. Needs to provide code compliant lever hardware on tanning room doors. Also reviewed special inspection report mfor the welding for new RTU supports. Also provde prrof of tempered glass in doors to tanning area.
FIRE-Final Inspection5/6/20195/6/20195/6/2019PPASS
DetailsMark Scharfen
Checked extinguishers, exit lighting and emergency lighting. Passed fire life safety.
BLD-Final5/2/20195/3/20195/3/2019PNR
DetailsMike Jordan
Brian Phone #: ###-####. Needs fire sprinkler and fire/life/safety finals.
BLD-Ceiling Grid Inspection4/30/20194/30/20194/30/2019PPASS
DetailsJim Sly
Brian Phone #: ###-####
BLD-Ceiling Grid Inspection4/26/20194/29/20194/29/2019PNR
DetailsMike Jordan
Bryan Phone #: ###-####. Needs sprinkler rough in inspection first.
BLD-Framing/Rough-in3/22/20193/25/20193/25/2019APASS
DetailsMike Jordan
Brian Phone #: ###-####. Interior steel stud framed walls for phase 2, restrooms and locker rooms ok.
BLD-Framing/Rough-in3/18/20193/19/20193/19/2019APASS
DetailsMike Jordan
Brian Phone #: ###-####. Interior steel stud framed walls, phase 2, tanning area and IT room.
BLD-Framing/Rough-in3/14/20193/15/20193/18/2019PPART
DetailsDave Hannah
Bryan Phone #: ###-#### north high wall between gym and rooms ok to cover
BLD-Framing/Rough-in3/4/20193/4/20193/4/2019PPASS
DetailsMike Jordan
Bryan Phone #: ###-####. Interior steel stud framed walls and soffits only for phase 1.