Information based on query as of Saturday, May 11, 2024.
Permit Information
Permit NumberBLD18-04470
StatusFinaled
Name SCOTT HEDRICK CONSTRUCTION
Site Address 390 S CAPITOL BLVD
Project NameCapitol & Front Pad 3 Shell
Customer Number 
ePlanReviewYes
Description
(CAPITOL & FRONT PAD 3 SHELL) Permit to construct a new 2,781 sq ft one-story shell building and related site improvements in the existing development at Capitol and Front Streets. Work to include: wood framed exterior walls with masonry veneer and stucco, metal canopies, and wood truss roof; exterior windows and doors; exterior lighting and power; mechanical roof top units; rough plumbing. Envelope, lighting, and mechanical in compliance with the 2015 IECC. This is a shell permit only; separate tenant improvement permit will be required to finish this building for occupancy. All work shall comply with the approved drawings, the plan review report, and all applicable codes. DRH12-00319, DRH18-00459, & CUP12-00067 per Planning and Zoning. Special Inspections required per the attached Form 310. NOTE: This building will be fully fire sprinkled and have an approved fire alarm system. The sprinklers are used for future A-2 occupancy. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/21/201910/21/201910/21/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Gary Band
DOC - Permit Finaled  10/21/2019 DONE
Per passing BLD Final from 425 on 10/21/19
BLD-Final10/17/201910/17/201910/17/2019APART
DetailsMike Jordan
Needs to repair and provide an additional handrail on the ramp on the north west side of building. his ramp is not part of the accesible route or egress.
BLD-Final10/16/201910/17/201910/17/2019ANR
DetailsMike Jordan
T.I. contractor was told we needed a structural inspection w/ Dave Hannah
We had a framing Inspection for shell in June or July, w/ Mike Jordan Phone #: ###-#### Inspection requested via web by Gary Band. Noted that zoning final failed back in July. Needs to resolve and get reinspection.

BLD-Conference10/16/201910/17/201910/17/2019ADONE
DetailsMike Jordan
T.I. contractor was told we needed a structural inspection w/ Dave Hannah
We had a framing Inspection for shell in June or July, w/ Mike Jordan
??? Phone #: ###-#### Inspection requested via web by Gary Band
FIRE-Final Inspection10/15/201910/15/201910/15/2019PPASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm permit under tenant improvement permit, fire extinguishers provided by tenant improvement. Final life fire safety inspection for this scope of work complete.

Looking for Life, Fire, Safety Inspection so T.I. contractor can get his final.
Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Wall cover7/26/20197/29/20197/30/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Gary Band covering int side of ext walls for shell and core
BLD-Framing/Rough-in7/13/20197/15/20197/15/2019APASS
DetailsDave Hannah
request is for a framing inspection of exterior soffit steel framing under the canopies. F/S ; elect inspections have been completed.
Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Wall cover6/28/20196/28/20196/28/2019ACANC
DetailsMike Jordan
looking for insulation inspection - by offered listings, not sure if it''s this or
"energy compliance" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Energy code compliance6/28/20196/28/20196/28/2019APASS
DetailsMike Jordan
looking for insulation inspection - by offered listings, not sure if it''s this or
"wall cover" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
FIRE-Conference6/27/20196/27/20196/27/2019PCANC
DetailsJim Page
FIRE-Conference6/27/20196/27/20196/27/2019PDONE
DetailsJim Page
Gas meter is set in the wrong location, city approved drawings show gas meter by north door, currently meter is set under PIV for fire sprinklers, needs to be relocated to give the required 36 inch clearance around PIV.
BLD-Framing/Rough-in6/25/20196/26/20196/26/2019PDONE
DetailsMike Jordan
Request for shell framing inspection -
Phone #: ###-#### Inspection requested via web by Gary Band. Completed in the am.
BLD-Framing/Rough-in6/25/20196/26/20196/26/2019APASS
DetailsMike Jordan
Request for shell framing inspection -
Phone #: ###-#### Inspection requested via web by Gary Band. Ok to insulate.
BLD-Wall Bracing4/29/20194/30/20194/30/2019APASS
DetailsDave Hannah
request shear and roof nailing inspection Tuesday morning.
Thank you.
Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Foundation3/29/20194/2/20194/2/2019APASS
DetailsDave Hannah
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request late morning for 2:00 pm pour
Best access @ E gate into project from W edge of parking lot
Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Foundation3/29/20194/2/20194/2/2019PCANC
DetailsDave Hannah
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request early afternoon insp for 2:00 pm pour
Best access @ E gate into project from W edge of parking lot
Thank you. Phone #: ###-#### >> Inspection requested via web by Gary Band Inspection cancelled from web by: Gary Band
BLD-Footing3/26/20193/27/20193/27/2019PPASS
DetailsDave Hannah
Request footing inspection early afternoon for 2;00 pm pour.
Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes.
Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band
BLD-Footing3/26/20193/27/20193/27/2019APEND
DetailsDave Hannah
Request footing inspection late morning for 2;00 pm pour.
Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes.
Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band ok after spec inspection is aproved