Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD18-04514
StatusFinaled
Name BILTMORE COMPANY
Site Address 13827 W MEADOWDALE ST
Project NameBoise Premier Office Bldg
Customer Number 
ePlanReviewYes
Description
(BOISE PREMIER OFFICE BUILDING) **5/9/2019 PLAN MODIFICATION TO REDUCE THE NUMBER OF HVAC UNITS FROM 3 TO 2. REVISIONS TO M, P, AND E SHEETS. (DRH18-000481) This building does not have a fire sprinkler system. To construct a two-story office building having a total floor area of about 4,944 square feet. One tenant will be occupying both stories (First Floor = 3,131 SF and Second Floor = 1,813 SF). Work is to include concrete footings, concrete foundation walls, crawl space, exterior concrete stairway to serve the below grade level, concrete retaining walls at the stairway, wood joist floor system recessed down into the perimeter concrete foundation walls with wood sheathing, wood beams and columns to support the floor, wood stud bearing walls to support the floor, 2x6 wood stud exterior bearing walls, wood stud shear walls with structural sheathing and hold downs, exterior stucco wall finish, exterior stone veneer wall finish, exterior windows, exterior doors, wood roof structure using energy trusses with a vented attic, concrete tile roof covering, metal roof covering, roof gutters and downspouts, interior non-bearing walls with gypsum wall board, 2 single-user toilet rooms accessible to the disabled, interior doors, interior windows, millwork, and finishes. Special inspections are required per the structural drawings and form #310. The design for the roof trusses is a deferred submittal item. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **JHB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/13/20198/13/20198/13/2019PPASS
DetailsTell Riley
Pat Phone #: ###-####//ok per plans//
BLD-Final7/31/20198/1/20198/1/2019PNR
DetailsTell Riley
Pat Phone #: ###-####//exit signs ok//break room counter height needs to be 34" per plans//bathroom sink clearance needs 2'5" floor to bottom of sink//
FIRE-Final Inspection7/30/20197/31/20197/31/2019APASS
DetailsTroy Cobbley
Life safety passed. The exit discharge light at the main exit to be relocated to below the canopy and the south exit door exit sign/emergency light repaired prior to a building inspection

Pat Phone #: ###-####
BLD-Final7/30/20197/31/20197/31/2019PCANC
DetailsTell Riley
Pat Phone #: ###-####//Pat cancelled via text//
FIRE-Final Inspection7/30/20197/30/20197/30/2019PFAIL
DetailsTroy Cobbley
Provide small documents, repair the exit signs and emergency lights, relocate the main exit discharge light to be installed below the canopy.

Please call ahead for access - Pat Phone #: ###-####
BLD-Energy code compliance5/28/20195/29/20195/29/2019APASS
DetailsBrandon Shaw
pat Phone #: ###-####
BLD-Framing/Rough-in5/17/20195/20/20195/20/2019AFAIL
DetailsJim Sly
Pat Phone #: ###-####
C/N posted.....Misc corrections....including Stairways not per Commercial code.
BLD-Wall Bracing4/18/20194/19/20194/19/2019APART
DetailsJim Sly
Pat Phone #: ###-####
Exterior nailing only......OK
BLD-Foundation3/20/20193/21/20193/21/2019PPASS
DetailsJim Sly
Dane Phone #: ###-####
BLD-Footing3/18/20193/19/20193/19/2019PPASS
DetailsJim Sly
dane Phone #: ###-####
BLD-Footing3/15/20193/18/20193/18/2019PCANC
DetailsMike Jordan
Dane Phone #: ###-####. Cancelled per contractor