Permit Information
Permit NumberBLD19-00363
StatusIssued
Name K2 CONSTRUCTION
Site Address 924 W MCGREGOR CT
Project NameAceCo Precision Manufacturing
Customer Number 
ePlanReviewYes
Description
(ACE CO PRECISION MANUFACTURING COMPANY, INC. – NEW OFFICE, MANUFACTURING, AND STORAGE BUILDING) (DRH18-00313) (7-20-20 PLAN MODIFICATION TO CHANGE THE BACK FLOW PREVENTION DEVICE FROM A DOUBLE CHECK VALVE ASSEMBLY TO A REDUCED PRESSURE ZONE ASSEMBLY AT THE WATER SERVICE TO THE BUILDING.) (7-6-20 PLAN MODIFICATION TO IDENTIFY PRODUCTION EQUIPMENT WITHIN THE MANUFACTURING AREA OF THIS BUILDING AS BEING FUTURE, ETC.) (5-5-20 PLAN MODIFICATION TO INSTALL AN ADDITIONAL 10 FEET X 10 FEET OVERHEAD DOOR IN THE WEST EXTERIOR WALL TO SERVE “HEAT TREAT 144”. WORK INCLUDES A NEW STRUCTURAL TUBE STEEL HEADER AND A NEW TYPE OF SHEAR WALL WITH FIRE-RETARDANT-TREATED STRUCTURAL PANELS AND HOLD DOWNS. ETC.) (3-4-20 PLAN MODIFICATION TO CONSTRUCT ADDITIONAL OFFICES WITHIN FORMERLY OPEN OFFICE AREAS ON THE 1ST AND 2ND STORIES AND TO CONSTRUCT A SINGLE-USER TOILET ROOM ACCESSIBLE TO THE DISABLED. THE NEW TOILET ROOM WILL BE LOCATED ON THE 1ST STORY BETWEEN THE MULTI-USER MEN’S TOILET ROOM AND THE MULTI-USER WOMEN’S TOILET ROOM WHICH HAVE DIRECT ACCESS FROM THE MANUFACTURING/WAREHOUSE AREA. ETC.) (1-9-20 PLAN MODIFICATION TO PROVIDE TWO ELECTRICAL TRANSFORMERS INSTEAD OF ONE AS ORIGINALLY PROPOSED. ONE PARKING SPACE WILL BE OMITTED TO PROVIDE A LARGER AREA TO ACCOMMODATE THE TRANSFORMERS AND THE LANDSCAPING. ETC.) The fire sprinkler system is used for fire area, building area increase, and for fire flow. To construct a new 94,031 square foot building (about 78,475 square feet lower level and about 15,556 square feet upper level) for a new office, manufacturing, and storage facility. Work is to include concrete footings, concrete stem walls, concrete pedestals, concrete slab on grade, concrete vibration isolation slabs, concrete elevator pit and masonry elevator shaft, an exterior recessed concrete loading dock, steel columns, steel beams, steel column and beam moment frames, steel roof and wall purlins, steel rod cross braces, standing seam metal roof panes, metal wall panels, steel stud exterior walls, steel stud exterior shear walls with fire-retardant-treated wood structural panels, masonry tile exterior wall finish, porcelain stone exterior wall tile, stucco, exterior windows, exterior doors, exterior overhead doors, metal awning, concrete upper level floor on steel pan deck, a gypsum board ceiling with metal studs joists not designed as a floor above toilet rooms and other rooms, interior steel stairways with concrete filled metal pan treads and landings, interior nonbearing walls, a 1-hr fire sprinkler riser room (unless the post valve indicator is installed on the exterior of the building), a 2-hr hazardous materials storage room, spill control curbs, a flammable liquids interceptor, a crane with crane beams and lateral bracing, 6 toilet rooms accessible to the disabled, one shower room accessible to the disabled with an accessible alternate roll-in shower, interior windows, interior doors, suspended acoustical ceilings, suspended gypsum board ceilings, millwork, and finishes. Concrete retaining walls will be constructed near the canal. A stand-alone 98 square foot bike rack canopy will be constructed. A masonry trash enclosure with steel gates where the masonry walls also function as retaining walls will be constructed. Special inspection is required for soils, concrete, masonry, steel (including welding and high strength bolting), and anchors post-installed in hardened concrete. A separate permit is required for storage racks that are over 8 feet tall. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/28/20207/31/20207/31/2020ACANC
DetailsJim Page
SCREENED // Ty Phone #: ###-#### cancel per Ty
BLD-Final7/28/20207/31/20207/30/2020PCANC
DetailsBrandon Shaw
SCREENED // Ty Phone #: ###-#### cancel per ty
BLD-Final7/27/20207/27/20207/27/2020PNR
DetailsBrandon Shaw
Pre-final walk thru...
BLD-Conference7/2/20207/2/20207/2/2020PPART
DetailsBrandon Shaw
Ceiling grid, OK to cover perimeter, need trades approval for all ceiling grid...
BLD-Ceiling Grid Inspection7/1/20207/2/20207/2/2020PCANC
DetailsBrandon Shaw
Herb *screened* Phone #: ###-####
BLD-Ceiling Grid Inspection6/25/20206/29/20206/29/2020PCANC
DetailsBrandon Shaw
screened // Herb Phone #: ###-####
FIRE-Final Inspection6/26/20206/26/20206/26/2020PFAIL
DetailsTroy Cobbley
Inspection was actually for a conferene to go over life safety items. I agreed a fire lane sign could be mounted on the wall at the property entrance. I pointed out the requirement for panic hardware in the path of egress from the Break Room. Break Room would also need Occupant Load sign, need Fire Dept radio verified per notes, need signage on Riser Room and Electrical Rooms doors....ect.

Herb *screened* Phone #: ###-####
BLD-Conference6/25/20206/26/20206/26/2020ACANC
DetailsTony Young
screened // Herb Phone #: ###-####// wanted a fire conf.
BLD-Framing/Rough-in5/5/20205/6/20205/6/2020APASS
DetailsBrandon Shaw
Herb Phone #: ###-####
BLD-Energy code compliance4/27/20204/28/20204/28/2020APART
DetailsBrandon Shaw
East exterior wall...
FIRE-Conference4/23/20204/23/20204/23/2020PDONE
DetailsJim Page
Fire conference is complete. Conference was able to be completed by phone. Conference was to question whether a egress double door section could have one leaf made in-active. Instructed Herb to verify occupant load exiting amount to verify if a leaf can be made in-active or if both leafs on the double door need to be operational for egress purposes.

Screened- would prefer conference in person if possible, up to inspectors discretion- Herb Phone #: ###-####
BLD-Framing/Rough-in4/13/20204/13/20204/13/2020PPART
DetailsTony Young
Herb Phone #: ###-####,, 2nd floor interior walls ok after bracing tops better, pending trades
BLD-Framing/Rough-in3/25/20203/25/20203/25/2020PPASS
DetailsMike Jordan
Herb Phone #: ###-####. Interior steel stud framed walls only for 1st. floor office area. No grid or hardlids at this time.
BLD-Conference3/10/20203/11/20203/11/2020ADONE
DetailsBrandon Shaw
Pre-framing walk thru...
BLD-Wall Bracing2/25/20202/26/20202/26/2020APART
DetailsBrandon Shaw
Exteroir walls, South and East sides...
BLD-Framing/Rough-in2/12/20202/12/20202/12/2020PPART
DetailsBrandon Shaw
OK to cover parapet walls, at roof line and up only...
OK to cover wall at grid line G, one side only...
BLD-Framing/Rough-in1/22/20201/23/20201/23/2020APART
DetailsBrandon Shaw
East entry and North walls, OK to cover exterior only...
BLD-Conference12/12/201912/12/201912/12/2019PDONE
DetailsBrandon Shaw
Herb Phone #: ###-####
BLD-Concrete9/24/20199/25/20199/25/2019APASS
DetailsBrandon Shaw
SOG pour 2am. Special inspection performed by Geotek for rebar and concrete strength test.
Ok after spec inspection sign offs...
BLD-Concrete9/10/20199/10/20199/10/2019PPASS
DetailsBrandon Shaw
Pour SOG 8” floor from grid lines 14-3 and H-E. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing9/10/20199/10/20199/10/2019PPASS
DetailsBrandon Shaw
Pour 1:30 pm for footings on grid line c.3. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Concrete8/30/20199/5/20199/5/2019PPASS
DetailsBrandon Shaw
Rebar and concrete inspection on building finish floor pending special inspection by Geotek.
Ok after spec inspection sign offs...
BLD-Concrete8/30/20199/3/20199/3/2019APASS
DetailsBrandon Shaw
Rebar and concrete inspection on com room lower slab, pending special inspection by Geotek.
Ok after spec inspection sign offs...
BLD-Concrete8/26/20198/26/20198/26/2019PPASS
DetailsBrandon Shaw
Building pad pour Tuesday 2am. Grids 17-3 and J-H. Special inspection for rebar and concrete done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/20/20198/21/20198/21/2019APASS
DetailsBrandon Shaw
Rebar inspection on footing and stem wall along grids A and B.1 from 1-17. Special inspection performed by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/13/20198/14/20198/14/2019ACANC
DetailsBrandon Shaw
Footing pour grid A from 1-9. Walls on grid 1 from H-D. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/7/20198/9/20198/9/2019APASS
DetailsBrandon Shaw
Inspection of rebar In footings. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/7/20198/9/20198/9/2019APASS
DetailsBrandon Shaw
Inspection of rebar In footings. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/7/20198/8/20198/8/2019APASS
DetailsBrandon Shaw
Inspection of rebar In footings. Special inspection done by Geotek.
Ok after spec inspection sign offs...
BLD-Footing8/7/20198/7/20198/7/2019PPASS
DetailsBrandon Shaw
Inspection of rebar In footings. Special inspection done...
Ok after spec inspection sign offs...
BLD-Footing7/31/20198/1/20198/1/2019APEND
DetailsBrandon Shaw
Footing pour grid line I from 8-2 including elevator pit. Special inspection
Ok after spec inspection sign offs...
BLD-Footing7/29/20197/31/20197/31/2019APASS
DetailsBrandon Shaw
Pouring footing pads along grid line H from 13-1. Special inspection for rebar done by Geotek. Phone #: ###-#### Inspection requested via web by Jason Allen
BLD-Footing7/29/20197/30/20197/30/2019APASS
DetailsBrandon Shaw
Footing pour grid 5 to1 to H. Special inspection by Geotek in AM. Phone #: ###-#### Inspection requested via web by Jason Allen
BLD-Foundation7/24/20197/26/20197/25/2019APART
DetailsBrandon Shaw
Concrete foundation walls being poured 7am Friday July 26. Pending special inspection by Geotek. Phone #: ###-#### Inspection requested via web by Jason Allen
BLD-Footing7/16/20197/17/20197/17/2019APASS
DetailsBrandon Shaw
Work in progress...
Pending special inspection...
BLD-Footing7/8/20197/9/20197/9/2019PPART
DetailsBrandon Shaw
Pending special inspection...
Grid line 15- 17...