Permit Information
Permit NumberBLD19-00538
StatusUnder Review
Name ESI
Site Address 12000 W FAIRVIEW AVE
Project NameVillage East-Garages/Carports
Customer NumberBLD19-00526-00536, 538-539
ePlanReviewNo
Description
(13 PERMITS IN EPLAN UNDER BLD19-00526) (GARAGES, CARPORTS, AND TRASH ENCLOSURES – VILLAGE EAST APARTMENTS) (PUD18-00042) (DRH18-00528) The garages, carports, and trash enclosures do not have a fire sprinkler system. To construct 6 garage buildings having a total floor area of about 13,240 square feet (two 8 unit buildings at about 1,864 square feet each, two 10 unit buildings at about 2,330 square feet each, and two 10 unit buildings at about 2,426 square feet each), to construct 29 carports of various sizes having a total floor area of about 42,405 square feet, and to construct 6 uncovered trash enclosures having an interior floor area of about 192 square feet each all to serve a new residential development. The carports include two 3 stall carports at 648 square feet each, three 4 stall carport at 647 square feet, five six 6 stall carport at 972 square feet each, one 7 stall carport at 1,296 square feet, five 8 stall carports at 1,296 square feet each, two 9 stall carports at 1,620 square feet each, four 10 stall carports at 1,620 square feet each, two 12 stall carports at 2,160 square feet each, one 14 stall carport at 2,520 square feet, two 16 stall carports at 2,880 square feet each, and one 18 stall carport at 3,240 square feet. For the garages, work is to include concrete footings, concrete stem walls, concrete slabs on grades, wood stud exterior walls, structural wood panel shear walls with hold downs, interior 1-hr fire barrier walls that also function as gypsum shear walls, engineered wood trusses, structural wood panel roof deck and diaphragm, overhead doors, architectural shingles, and fiber cement horizontal lap siding. The truss design is a deferred submittal item. For the carports, work is to include concrete footings, steel columns, steel beams, steel purlins, and steel panel roofs. The design for the carports is a deferred submittal item. For the trash enclosures, work is to include concrete footings, concrete stem walls, masonry walls, steel pipe bollards, and steel gates. The work is required to comply with the approved drawings, with the structural designs, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Foundation8/5/20208/6/20208/6/2020ADEFR
DetailsTell Riley
Stem wall pour on garage 5. Pour time at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//defer to special inspections//was poured prior to my arrival//
BLD-Footing8/3/20208/4/20208/4/2020APART
DetailsTell Riley
Footing pour on garage 5. Concrete pour at noon Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add verts at 18" oc per the plans//special inspector onsite, will verify prior to pour//pend specials approvals//
BLD-Concrete7/17/20207/17/20207/17/2020PNR
DetailsTell Riley
screened // Lee Phone #: ###-####//NR need deferred submittals accepted//
BLD-Wall Bracing4/8/20204/10/20204/10/2020APASS
DetailsTell Riley
Shear inspection for cover on exterior of garage 6 Phone #: ###-#### Inspection requested via web by Travis Blackburn//hold downs ok//shear nailing ok//
BLD-Footing2/21/20202/21/20202/21/2020PPART
DetailsTell Riley
Pouring the footings for garage 6 at 1pm also Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//one area needed heated prior to pour--discussed with special inspector onsite//
BLD-Wall Bracing1/3/20201/7/20201/7/2020AFAIL
DetailsTell Riley
Garage 4 shear inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//CN issued for anchor bolts, need to add hold down, galv nails @ treated plate, nailing at back, blockin per detail at trusses//
BLD-Concrete12/11/201912/12/201912/12/2019ACANC
DetailsTell Riley
Trash Enclosure slabs are getting poured at 10am. If you can inspect about 9am that would be good. The slabs as a whole do not have rebar, they do have a thickened edge. Phone #: ###-#### >> Inspection requested via web by Matt Perry Inspection cancelled from web by: Matt Perry
BLD-Wall Bracing12/4/201912/5/201912/5/2019APART
DetailsTell Riley
This a shear inspection for garage 3 Phone #: ###-#### Inspection requested via web by Travis Blackburn//verify and use approved fasteners at sill plate//nail hold down//
BLD-Concrete12/3/201912/4/201912/4/2019APART
DetailsTell Riley
This inspection is for the stem walls for the garbage enclosures around the site. There are are 5 in total. The pour is at 11, please come as close to 10am as possible. Phone #: ###-#### Inspection requested via web by Matt Perry//first 4 trash enclosure stem wall ok, pending specials//
BLD-Concrete11/13/201911/14/201911/14/2019PPEND
DetailsDave Hannah
Pouring the slab for the Garage #4 at 6:30 AM on Friday. Please inspect late on Thursday Phone #: ###-#### Inspection requested via web by Matt Perry will be inspected by spec. insp
BLD-Concrete11/7/201911/8/201911/7/2019ACANC
DetailsTell Riley
Pouring the walls for the garage at 2pm. please inspect as close to that time frame as possible. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry Inspection cancelled from web by: Matt Perry
BLD-Footing11/4/201911/5/201911/5/2019APASS
DetailsTell Riley
Garage #4 footings being poured at 1pm on Tuesday. Please inspect as close to that time as possible. Thanks Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//
BLD-Concrete10/8/201910/9/201910/9/2019APART
DetailsTell Riley
Concrete pour at 630 am on garage 3 Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok if specials are passed//
BLD-Foundation9/24/20199/25/20199/25/2019PPASS
DetailsTell Riley
This inspection is for garage 3. Pour time is at 2pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok one bar clearances and obtained//pending specials//
BLD-Foundation9/24/20199/25/20199/24/2019PCANC
DetailsTell Riley
Inspection is for stem walls on garage 3 Phone #: ###-#### >> Inspection requested via web by Travis Blackburn Inspection cancelled from web by: Travis Blackburn
BLD-Footing9/18/20199/19/20199/19/2019PPART
DetailsTell Riley
This is for footings on garage #3. Pour time is at 4:30 Phone #: ###-#### Inspection requested via web by Travis Blackburn//rebar ok//ok to pour pending special inspections//