Permit to add 660sq' to the garage and do a major interior remodel of the home that reconfigures several walls & adds structural beams/posts/footings. Final layout of home is 3bd/3.5bth. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference10/18/201910/18/201910/18/2019PPASS
DetailsMike Jordan
All items have been taken care of. Phone #: ###-#### Inspection requested via web by Mark Fischer
DOC - Permit Finaled10/18/201910/18/201910/18/2019PPASS
DetailsMike Jordan
BLD-Final10/18/201910/18/201910/18/2019PPASS
DetailsMike Jordan
All items have been taken care of. Phone #: ###-#### Inspection requested via web by Mark Fischer
BLD-Final9/25/20199/25/20199/25/2019PFAIL
DetailsMike Jordan
Please call ###-#### prior to heading over. Thanks Phone #: ###-#### Inspection requested via web by Mark Fischer. Provide tempered glazing next to front door. Egress ladder required for egress from basement bedroom in backyard.
BLD-Wall cover7/1/20197/1/20197/1/2019PPASS
DetailsMike Jordan
Please call Mark Stevens half hour before arriving at ###-####. All insulation in garage and house is complete. There are some additional interior walls receiving insulation for sound barrier but I wanted to have everything inspected prior to the interior wall cavity was filled. All additional air sealing locations have been filled per Inspectors direction. Inspection requested via web by Mark Fischer. Ok to sheet rock.
BLD-Framing/Rough-in6/25/20196/26/20196/26/2019PPASS
DetailsMike Jordan
Approve framing for insulation on house and garage. Please come after 4pm. Inspection requested via web by Mark Fischer
BLD-Conference6/21/20196/21/20196/21/2019ADONE
DetailsMike Jordan
Come inspect framing portion to OK for spray foam of interior walls of house for first floor and basement. Review new portal frame support as well. Requested early morning inspection prior to insulation contractor arrival. Inspection requested via web by Mark Fischer. Needs mech. rough in inspection prior to insulation. Complete sealing of top plate and bottom plate penetrations on interior walls. Strap top plate at plumbing vent pentrations in master bedroom. Complete lateral bracing on A05 truss.
BLD-Conference6/17/20196/17/20196/17/2019APASS
DetailsMike Jordan
Inspect Garage Portal Frame Walls for Framing and Nailing Schedule. Need inspection approval as the Mason''s are wanting to finish exterior work and would like to cover the front walls. Also have the ESR report for the RTECH foam board used in the roofing. Please call Mark Stevens 30mins prior to arriving at ###-####. Inspection requested via web by Mark Fischer. The R tech foam insulation is ok as installed.
BLD-Wall Bracing6/17/20196/17/20196/17/2019APASS
DetailsMike Jordan
Inspect Garage Portal Frame Walls for Framing and Nailing Schedule. Need inspection approval as the Mason''s are wanting to finish exterior work and would like to cover the front walls. Also have the ESR report for the RTECH foam board used in the roofing. Please call Mark Stevens 30mins prior to arriving at ###-####. Inspection requested via web by Mark Fischer
BLD-Conference6/5/20196/6/20196/6/2019ADONE
DetailsMike Jordan
Preliminary inspection of framing progress to date. Please call Mark Stevens at 1 ###-#### 30 minutes prior to arrival. Inspection requested via web by Mark Fischer. Provide nails on portal frame. Need ESR report for foam insulation. Also walk through on framing.
BLD-Conference4/9/20194/9/20194/9/2019PCANC
DetailsMike Jordan
Need OK on depth of structural footers in basement before pour. Phone #: ###-#### Inspection requested via web by Mark Fischer
BLD-Footing4/9/20194/9/20194/9/2019PPART
DetailsMike Jordan
Need OK on depth of structural footers in basement before pour. Phone #: ###-#### Inspection requested via web by Mark Fischer. Interior column pad footings in basement.
BLD-Wall Bracing3/26/20193/27/20193/27/2019ACANC
DetailsMike Jordan
stem wall // Mark or ###-#### Phone #: ###-####
BLD-Foundation3/27/20193/27/20193/27/2019APASS
DetailsMike Jordan
stem wall // Mark or ###-#### Phone #: ###-####. Stemwall for new garage ok.
BLD-Footing3/22/20193/25/20193/25/2019APASS
DetailsMike Jordan
Travis Phone #: ###-####. footings for new garage ok.