BLD-Final | 5/5/2020 | 5/6/2020 | 5/6/2020 | A | PASS |
Mike Jordan
|
|
|
Thanks Mike. Have a great day! Phone #: ###-#### Inspection requested via web by Scott Zierler
|
DOC - Permit Finaled | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 5/6/2020 | 5/6/2020 | 5/6/2020 | A | DONE |
Mike Jordan
|
|
|
3.5
|
BLD-Final | 4/30/2020 | 5/5/2020 | 5/5/2020 | A | NR |
Mike Jordan
|
|
|
Hey Mike. Please call with lead time so I can meet you there. Thanks Scott Phone #: ###-#### Inspection requested via web by Scott Zierler. Needs landings and stairs. Everything else ok.
|
BLD-Final | 4/27/2020 | 4/29/2020 | 4/28/2020 | A | CANC |
Mike Jordan
|
|
|
Hi Mike. Please give me some lead time so I can meet you onsite. Thanks Scott ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Final | 4/25/2020 | 4/28/2020 | 4/27/2020 | A | CANC |
Mike Jordan
|
|
|
Hi Mike. Please give me some lead time so I can meet you onsite. Thanks Scott ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Conference | 7/8/2019 | 7/11/2019 | 7/11/2019 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | FAIL |
Mike Jordan
|
|
|
Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler. All issues resolved except fot notched F3 truss at bearing.
|
BLD-Framing/Rough-in | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | FAIL |
Mike Jordan
|
|
|
Plans will be at the fireplace! Thanks Mike! Scott Phone #: ###-#### Inspection requested via web by Scott Zierler. Install straps for portal frames. Complete fire blockingat fir downs in main hallway by front door, both sides. Justify notched truss at bearing. (F3 truss). Roll block F1,F2,and F3 trusses, both sides. Nail C3 triple ply truss per the engineering and add stud under bearing. Complete lateral bracing on A4, A4A, A5, A6, A7 trusses. Correction notice posted. ok to insulate.
|
BLD-Energy code compliance | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Mike Jordan
|
|
|
Thank you! Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Wall Bracing | 5/28/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 4/23/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|