BLD-Final | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Mike Jordan
|
|
|
Barney Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 11/20/2019 | 11/21/2019 | 11/21/2019 | A | PEND |
Mike Jordan
|
|
|
Barney Phone #: ###-####. Need final letter from special inspection agency and zoning final.
|
FIRE-Final Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Barney Phone #: ###-####
|
FIRE-Conference | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with the general contractor. I noted unfinished alarm and sprinkler permits, missing address, missing signage....ect.
|
BLD-Conference | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | DONE |
Mike Jordan
|
|
|
Barnie Phone #: ###-####
|
BLD-Energy code compliance | 11/13/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Mike Jordan
|
|
|
Barnie Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Mike Jordan
|
|
|
Barnie Phone #: ###-####
|
BLD-Energy code compliance | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | NR |
Mike Jordan
|
|
|
BARNEY- Phone #: ###-####. Work is in progress but not completed.
|
BLD-Framing/Rough-in | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | NR |
Mike Jordan
|
|
|
BARNEY- Phone #: ###-####. Needs MEP rough in inspections first.
|
BLD-Other | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | PEND |
Mike Jordan
|
|
|
red iron structural insp // Barney Harper Phone #: ###-####. High strength bolting. torque wrench method used. All plys in contact. Special inspection will be out this afternoon.
|
BLD-Concrete | 7/25/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Mike Jordan
|
|
|
rebar for tension beam // Ryan Phone #: ###-####. rreinforcement for tension beams ok.
|
BLD-Foundation | 7/16/2019 | 7/17/2019 | 7/17/2019 | P | PART |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. Work in progress. #6 tension ties along grid 5 need to 90 into column pedestals as per approved plans. Ok to place pending special inspection. Special inspector to verify 90's at this location.
|
BLD-Footing | 7/12/2019 | 7/15/2019 | 7/15/2019 | A | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. All clearance issues have been repaired.
|
BLD-Footing | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | FAIL |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. Noted several areas were reinforcement does not have the minimum 3 inch clearance from ground. A correction notice was issued. Perimeter footings and column pad footings at this time only.
|