BLD-Final | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PART |
Mike Jordan
|
|
|
Screened- please call before- Taylor Phone #: ###-####. Ok for temp occ. Guard at loading dock is not code compliant.
|
FIRE-Final Inspection | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
Screened- Taylor Phone #: ###-####
|
BLD-Wall cover | 6/19/2020 | 6/23/2020 | 6/23/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Taylor Phone #: ###-####
|
BLD-Wall cover | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
fire wall .. call to meet // Taylor Phone #: ###-####
|
BLD-Concrete | 5/20/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Mike Jordan
|
|
|
rebar slab- late morning if poss- Taylor *screened* Phone #: ###-####
|
BLD-Footing | 5/8/2020 | 5/11/2020 | 5/11/2020 | A | PASS |
Mike Jordan
|
|
|
Tyalor *screened* Phone #: ###-####. Loading dock walls.
|
BLD-Footing | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Mike Jordan
|
|
|
*screened* Alex Phone #: ###-####. Footings for loading dock ok.
|
BLD-Footing | 5/6/2020 | 5/7/2020 | 5/7/2020 | P | NR |
Mike Jordan
|
|
|
Screened- please later in the AM call for more details-concrete schedule for 2pm- Taylor Phone #: ###-####
|
BLD-Foundation | 4/30/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Mike Jordan
|
|
|
REBAR // Taylor Phone #: ###-####. Slab on grade rebar.
|
BLD-Footing | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Mike Jordan
|
|
|
Screened- Rebar inspection-Taylor Phone #: ###-####. West half, interior slab on grade.
|
BLD-Foundation | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PART |
Mike Jordan
|
|
|
rebar- pouring at 1:45-Taylor **Cleared** Phone #: ###-####. perimeter frost wall. Ok to place concrete pending special inspection.
|
BLD-Footing | 4/17/2020 | 4/20/2020 | 4/20/2020 | A | PASS |
Mike Jordan
|
|
|
screened pour at 1 // Taylor Phone #: ###-####. Column pedestals
|
BLD-Concrete | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PART |
Mike Jordan
|
|
|
screened // rebar - pouring at 1:45 // Taylor Phone #: ###-####. perimeter column pad footings. Work in progress on completed reinforcement. Ok to place conc. pending special inspection.
|
BLD-Conference | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | DONE |
Mike Jordan
|
|
|
screened // Tyler Phone #: ###-####
|