BLD-Final | 5/18/2020 | 5/18/2020 | 5/18/2020 | A | PASS |
Tell Riley
|
|
|
zoning confirmed sign off via email////ACHD permit finaled//no fire lifesafety as this is a residential IRC building//final corrections were completed//
|
DOC - Permit Finaled | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 5/14/2020 | 5/15/2020 | 5/18/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat//waiting for zoning approval//
|
BLD-Blower Door Test Results | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | DONE |
Tell Riley
|
|
|
4.6 ACH 50
|
BLD-Final | 5/13/2020 | 5/14/2020 | 5/14/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat//still needs blower door test//need to verify u values on windows are .31 for the R38, or R49 will be required for the .32 u value//
|
BLD-Final | 5/7/2020 | 5/8/2020 | 5/8/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat//see CN posted onsite//
|
BLD-Wall cover | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat
|
BLD-Framing/Rough-in | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat
|
BLD-Wall Bracing | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat
|
BLD-Foundation | 1/22/2020 | 1/22/2020 | 1/22/2020 | A | DEFR |
Tell Riley
|
|
|
setbacks were not re-verified prior to pouring vertical walls as noted on footing inspection//foundation wall inspection was not completed//contractor assumes all liability for setbacks and foundation//
|
BLD-Wall Bracing | 1/22/2020 | 1/22/2020 | 1/22/2020 | A | FAIL |
Tell Riley
|
|
|
need approved plans//add hot dipped galvanized nails at PT sill//
|
BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat//needed wall bracing//
|
BLD-Footing | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Treat//setbacks close on side--string prior to pouring vertical//add ufer ground//WIP//
|