BLD-Final | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PART |
Mike Jordan
|
|
|
Kyle *screened* Phone #: ###-####. OK for temp occ. Needs to revise scope of work or submit aditional plans for occupancy. Provide final letter from special inspection agency and RFI from engineer for east footing.
|
BLD-Final | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | NR |
Mike Jordan
|
|
|
Kyle */Screened*/ Phone #: ###-####
|
FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given until the project related fire alarm permit is finaled.
Phone #: ###-####
|
BLD-Final | 7/31/2020 | 8/3/2020 | 8/3/2020 | P | NR |
Mike Jordan
|
|
|
screened // Kyle Phone #: ###-####. Needs fire/life/safety and zoning finals.
|
FIRE-Final Inspection | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related firer alarm and hood suppresion permits finaled. Need all small documents, need address, need the exit signs and emergency lights repaired, need verification the room/walls at the cooler/fire riser room is ok to delete.
screened // Kyle Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/28/2020 | 7/29/2020 | 7/29/2020 | P | PASS |
Mike Jordan
|
|
|
SCREENED // Kyle Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | NR |
Mike Jordan
|
|
|
screened // Kyle Phone #: ###-####
|
BLD-Framing/Rough-in | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Mike Jordan
|
|
|
support framing for overbuilds at parapets.
|
BLD-Framing/Rough-in | 7/17/2020 | 7/20/2020 | 7/20/2020 | A | PASS |
Mike Jordan
|
|
|
screened // Andrew Phone #: ###-####. Insualtion above freezer ok.
|
BLD-Framing/Rough-in | 7/14/2020 | 7/15/2020 | 7/15/2020 | A | PASS |
Mike Jordan
|
|
|
Andrew *screened** Phone #: ###-####
|
BLD-Framing/Rough-in | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | FAIL |
Mike Jordan
|
|
|
Kyle Phone #: ###-####. Needs to provide updated strucutural details for steel studs in lieu of LVL studs for exterior furouts. Need special inspection reports for concrete and epoxy to date. Also needs to provide fire conferance on exterior furouts. Called Kyle at above number and left message. do not cover furouts at this time.
|
BLD-Footing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Mike Jordan
|
|
|
screened // Andrew Phone #: ###-####. . remainder of footings for bumpouts.
|
BLD-Footing | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PART |
Mike Jordan
|
|
|
Screened- Andrew Phone #: ###-####. Footing for freezer slab and architectual bump outs ok. Need enginner of records approval for new footing at storefront.
|